by 5P Developers · Dhamote, Raigarh

Possession: 5P ARIA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000013706. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about 5P ARIA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 5P ARIA has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52000001471)

    Reason the builder gave MahaRERA: “Due to labor and material supply issue the project is delayed. Kindly issue us the extension”

Source: 5P ARIA’s extension records on MahaRERA (P52000013706), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 5P ARIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000013706
Status
Completed
Builder
5P Developers
Location
Dhamote, Raigarh · 410101
Project type
Residential / Group Housing
Registered on
23 Oct 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
27
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of 5P ARIA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
5P ARIA100%5%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 5P ARIA every month.

5P ARIA: buildings, flats and land, as filed on MahaRERA

  • Buildings: 5P ARIA (6 floors)
  • Land: 699 sq m (about 0.2 acres) · sanctioned built-up 838 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 5P ARIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

5P ARIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 5P ARIA

What is the possession date of 5P ARIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 5P ARIA in Dhamote, Raigarh is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 5P ARIA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 5P ARIA's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 5P ARIA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "Due to labor and material supply issue the project is delayed. Kindly issue us the extension".

What is the RERA number of 5P ARIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 5P ARIA in Dhamote, Raigarh is P52000013706.

Is 5P ARIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA is registered as P52000013706 and its status is "Completed".

What is the construction status of 5P ARIA?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA's status on MahaRERA is "Completed". As filed by the builder, slab work on 5P ARIA is 5% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does 5P ARIA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 5P ARIA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA is registered on MahaRERA as P52000013706, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 5P ARIA's possession date changes?

The latest dates are on 5P ARIA's MahaRERA page (P52000013706). GharKundli's Kundli Watch sends a free WhatsApp update on 5P ARIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 5P ARIA have?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA has one building filed: 5P ARIA with 6 floors.

How big is the land of 5P ARIA?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA stands on 699 sq m of land (about 0.2 acres), with 838 sq m of sanctioned built-up area.

Where can I read reviews of 5P ARIA?

Google Maps has reviews of 5P ARIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 5P ARIA?

5P ARIA by 5P Developers is in Dhamote, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000013706, per GharKundli's check of MahaRERA records.

How many homes are in 5P ARIA?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA has 27 homes in 1 tower registered on MahaRERA.

When was 5P ARIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 5P ARIA was registered on MahaRERA on 23 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 5P ARIA?

No court cases are listed for 5P ARIA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of 5P ARIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is 5P Developers.

Other projects in Karjat

All 362 projects in Neral (410101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.