Skip to content
GharKundli

The Mulund Ankoor CHS. LTD.

by Indu Enterprise · Mulund East, Mumbai 400081Also near Mulund West, Tata Colony

What’s in the report? →

Possession date of The Mulund Ankoor CHS. LTD. (MahaRERA P51800002668): 31 July 2025, moved from 31 May 2020 (62 months later), and it has already passed. It has 36 homes (1 BHK, 1 Room Kitchen and 2 BHK, 259–988 sq ft carpet), 82% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002668. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800002668, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2025) has passed.

What do you want to know about The Mulund Ankoor CHS. LTD.?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Mulund Ankoor CHS. LTD. has moved

  1. 31 May 2020

    Completion date given when the project was registered

  2. 31 July 2022

    Extended at the builder's request (MahaRERA application EXT51800009241)

    Reason the builder gave MahaRERA:
    “I Mr. Mandar Dattatraya Vaidya, Partner of “Indu Enterprise” do hereby declare that the project “The Mulund Ankoor CHS. Ltd.” is registered with MahaRERA vide Registration Number “P51800002668” and end date for the project is 30th November…” Read the full reason“I Mr. Mandar Dattatraya Vaidya, Partner of “Indu Enterprise” do hereby declare that the project “The Mulund Ankoor CHS. Ltd.” is registered with MahaRERA vide Registration Number “P51800002668” and end date for the project is 30th November 2020. I wish to extend the project till 31st July 2022. I further declare that project could not be completed due to various reasons beyond the control of the developer. Therefore, we have decided to apply for the extension of the project under Section 7(3) of The Real Estate (Regulation and Development) Act, 2016.”
  3. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT51800015243)

    Reason the builder gave MahaRERA:
    “I Mr. Anish Joshi, Partner of “Indu Enterprise” do hereby declare that the project “The Mulund Ankoor CHS. Ltd.” is registered with MahaRERA vide Registration Number “P51800002668” and end date for the project is 31st January 2023. I wish t…” Read the full reason“I Mr. Anish Joshi, Partner of “Indu Enterprise” do hereby declare that the project “The Mulund Ankoor CHS. Ltd.” is registered with MahaRERA vide Registration Number “P51800002668” and end date for the project is 31st January 2023. I wish to extend the project till 31st July 2023. I further declare that project could not be completed due to various reasons beyond the control of the developer. Therefore, we have decided to apply for the extension of the project under Section 7(3) of The Real Estate (Regulation and Development) Act, 2016.”
  4. 31 July 2025

    Extended at the builder's request (MahaRERA application EXT51800025160)

    Reason the builder gave MahaRERA: “As attached”

Source: The Mulund Ankoor CHS. LTD.’s extension records on MahaRERA (P51800002668), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Mulund Ankoor CHS. LTD.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002668
Status
Lapsed (registration period ended)
Builder
Indu Enterprise
Location
Mulund East, Mumbai · 400081
Project type
Others
Registered on
2 Aug 2017
Completion date at registration
May 2020
Latest completion date
July 2025
Delay so far
62 months
Homes
36
Sold or booked
82%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of The Mulund Ankoor CHS. LTD., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
The Mulund Ankoor CHS LTD100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • The Mulund Ankoor CHS LTD: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Mulund Ankoor CHS. LTD. every 1–2 months.

The Mulund Ankoor CHS. LTD.: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK525 – 61517
3 BHK75115
Shops118 – 3656
1 BHK390 – 9883
1 Room Kitchen2591

The builder’s record and reviews

Indu Enterprise has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 44 months); 1 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of The Mulund Ankoor CHS. LTD. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Mulund Ankoor CHS. LTD.: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Mulund Ankoor CHS. LTD.

What is the possession date of The Mulund Ankoor CHS. LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Mulund Ankoor CHS. LTD. in Mulund East, Mumbai is 31 July 2025 — 62 months later than 31 May 2020, the date given at registration. That date has already passed.

The date has already moved 62 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for The Mulund Ankoor CHS. LTD.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Mulund Ankoor CHS. LTD.'s builder has filed on MahaRERA, the official one, is 31 July 2025, already 62 months later than the 31 May 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Mulund Ankoor CHS. LTD. extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD.'s builder applied to MahaRERA to extend the completion date 3 times: to 31 July 2022, giving the reason "I Mr. Mandar Dattatraya Vaidya, Partner of “Indu Enterprise” do hereby declare that the project “The Mulund Ankoor CHS. Ltd.” is registered with MahaRERA vide Registration Number “P51800002668” and end date for the project is 30th November 2020. I wish to extend the project till 31st July 2022. I further declare that project could not be completed due to various reasons beyond the control of the developer. Therefore, we have decided to apply for the extension of the project under Section 7(3) of The Real Estate (Regulation and Development) Act, 2016."; to 31 July 2023, giving the reason "I Mr. Anish Joshi, Partner of “Indu Enterprise” do hereby declare that the project “The Mulund Ankoor CHS. Ltd.” is registered with MahaRERA vide Registration Number “P51800002668” and end date for the project is 31st January 2023. I wish to extend the project till 31st July 2023. I further declare that project could not be completed due to various reasons beyond the control of the developer. Therefore, we have decided to apply for the extension of the project under Section 7(3) of The Real Estate (Regulation and Development) Act, 2016."; to 31 July 2025, giving the reason "As attached".

What is the RERA number of The Mulund Ankoor CHS. LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Mulund Ankoor CHS. LTD. in Mulund East, Mumbai is P51800002668.

Is The Mulund Ankoor CHS. LTD. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. is registered as P51800002668 and its status is "Lapsed (registration period ended)".

What is the current construction status of The Mulund Ankoor CHS. LTD.? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD.'s status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on The Mulund Ankoor CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does The Mulund Ankoor CHS. LTD. have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The Mulund Ankoor CHS. LTD. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. is registered on MahaRERA as P51800002668, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 62 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Mulund Ankoor CHS. LTD.?

The Mulund Ankoor CHS. LTD. isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in The Mulund Ankoor CHS. LTD. are 259 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Mulund Ankoor CHS. LTD.?

For a flat in The Mulund Ankoor CHS. LTD. (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The Mulund Ankoor CHS. LTD. received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for The Mulund Ankoor CHS. LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD.'s registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is The Mulund Ankoor CHS. LTD. a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has The Mulund Ankoor CHS. LTD. uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Mulund Ankoor CHS. LTD. was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Mulund Ankoor CHS. LTD.'s possession date changes?

The latest dates are on The Mulund Ankoor CHS. LTD.'s MahaRERA page (P51800002668). GharKundli's Kundli Watch sends a free WhatsApp update on The Mulund Ankoor CHS. LTD. every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Mulund Ankoor CHS. LTD. have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. has one building filed: The Mulund Ankoor CHS LTD with 19 floors and 42 units.

What are the flat sizes (carpet area) in The Mulund Ankoor CHS. LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Mulund Ankoor CHS. LTD.: 2 BHK: 525 to 615 sq ft carpet (17 homes); 3 BHK: 751 sq ft carpet (15 homes); 1 BHK: 390 to 988 sq ft carpet (3 homes); 1 Room Kitchen: 259 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of The Mulund Ankoor CHS. LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. stands on 899 sq m of land (about 0.2 acres), with 1,060 sq m of sanctioned built-up area.

What is the track record of The Mulund Ankoor CHS. LTD.'s builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Indu Enterprise has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 44 months); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Mulund Ankoor CHS. LTD.?

Google Maps has reviews of The Mulund Ankoor CHS. LTD. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Mulund Ankoor CHS. LTD.?

The Mulund Ankoor CHS. LTD. by Indu Enterprise is in Mulund East, Mumbai, pincode 400081 (near Mulund West, Tata Colony), Maharashtra, and is registered on MahaRERA as P51800002668, per GharKundli's check of MahaRERA records. Its boundaries filed there include Chafekar Bandhu Marg, Dhingra Garden. Its land is filed as 1108, 1108 A. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).

How many flats are in The Mulund Ankoor CHS. LTD., and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. has 36 homes in 1 tower registered on MahaRERA, and 82% of them are sold or booked.

When was The Mulund Ankoor CHS. LTD. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Mulund Ankoor CHS. LTD. was registered on MahaRERA on 2 August 2017. GharKundli did not find a title report on the land on file there.

Does The Mulund Ankoor CHS. LTD. have any legal issues or court cases?

No court cases are listed for The Mulund Ankoor CHS. LTD. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The Mulund Ankoor CHS. LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Indu Enterprise, which has 2 other projects registered on MahaRERA.

Other projects in Mulund East (400081)

All 124 projects in Mulund East (400081) →

Other projects by Indu Enterprise

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.