MULUND KAVITA KIRAN CHS
by Indu Enterprise · mulund East, MumbaiAlso near Mulund West, Bhandup west, Wagle I.E
Possession: MULUND KAVITA KIRAN CHS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011080. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MULUND KAVITA KIRAN CHS?
How the possession date of MULUND KAVITA KIRAN CHS has moved
31 December 2020
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51800001433)
Reason the builder gave MahaRERA: “Commencement Certificate received on 04/01/2019 and the completion period is of 36 months from the date of the commencement certificate.”
30 June 2023
Extended at the builder's request (MahaRERA application EXT51800013511)
Reason the builder gave MahaRERA: “As per attachment”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800017188)
Reason the builder gave MahaRERA: “As per attachment”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800019605)
Reason the builder gave MahaRERA: “As per attachment”
Source: MULUND KAVITA KIRAN CHS’s extension records on MahaRERA (P51800011080), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MULUND KAVITA KIRAN CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011080
- Status
- Completed
- Builder
- Indu Enterprise
- Location
- mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- December 2024
- Delay so far
- 48 months
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of MULUND KAVITA KIRAN CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MULUND KAVITA KIRAN | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MULUND KAVITA KIRAN CHS every month.
MULUND KAVITA KIRAN CHS: buildings, flats and land, as filed on MahaRERA
- Buildings: MULUND KAVITA KIRAN (17 floors)
- Land: 1,576 sq m (about 0.4 acres) · sanctioned built-up 3,275 sq m
- Boundaries filed include: S P GUJAR MARG
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Indu Enterprise has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 44 months); 1 lapsed. 2 complaints on MahaRERA across 1 project.
Read Google reviews of MULUND KAVITA KIRAN CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MULUND KAVITA KIRAN CHS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MULUND KAVITA KIRAN CHS
What is the possession date of MULUND KAVITA KIRAN CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MULUND KAVITA KIRAN CHS in mulund East, Mumbai is 31 December 2024 — 48 months later than 31 December 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for MULUND KAVITA KIRAN CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MULUND KAVITA KIRAN CHS's builder has filed on MahaRERA, the official one, is 31 December 2024, already 48 months later than the 31 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MULUND KAVITA KIRAN CHS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2021, giving the reason "Commencement Certificate received on 04/01/2019 and the completion period is of 36 months from the date of the commencement certificate."; to 30 June 2023, giving the reason "As per attachment"; to 31 December 2023, giving the reason "As per attachment"; to 31 December 2024, giving the reason "As per attachment".
What is the RERA number of MULUND KAVITA KIRAN CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MULUND KAVITA KIRAN CHS in mulund East, Mumbai is P51800011080.
Is MULUND KAVITA KIRAN CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS is registered as P51800011080 and its status is "Completed".
What is the construction status of MULUND KAVITA KIRAN CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS's status on MahaRERA is "Completed". As filed by the builder, slab work on MULUND KAVITA KIRAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MULUND KAVITA KIRAN CHS have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MULUND KAVITA KIRAN CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS is registered on MahaRERA as P51800011080, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MULUND KAVITA KIRAN CHS's possession date changes?
The latest dates are on MULUND KAVITA KIRAN CHS's MahaRERA page (P51800011080). GharKundli's Kundli Watch sends a free WhatsApp update on MULUND KAVITA KIRAN CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MULUND KAVITA KIRAN CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS has one building filed: MULUND KAVITA KIRAN with 17 floors.
How big is the land of MULUND KAVITA KIRAN CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS stands on 1,576 sq m of land (about 0.4 acres), with 3,275 sq m of sanctioned built-up area.
What is the track record of MULUND KAVITA KIRAN CHS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Indu Enterprise has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 44 months); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MULUND KAVITA KIRAN CHS?
Google Maps has reviews of MULUND KAVITA KIRAN CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MULUND KAVITA KIRAN CHS?
MULUND KAVITA KIRAN CHS by Indu Enterprise is in mulund East, Mumbai (pincode 400081), near Mulund West, Bhandup west, Wagle I.E, Maharashtra, and is registered on MahaRERA as P51800011080, per GharKundli's check of MahaRERA records. Its boundaries filed there include S P GUJAR MARG.
When was MULUND KAVITA KIRAN CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MULUND KAVITA KIRAN CHS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MULUND KAVITA KIRAN CHS?
No court cases are listed for MULUND KAVITA KIRAN CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MULUND KAVITA KIRAN CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Indu Enterprise, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MULUND KAVITA KIRAN CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400081
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
- GOVIND PRAKASH SRA CHS LTD
- BIMAL APARTMENT CHSL
- Ganesh Dham
- SATRE ELITE
- PEARL
- New Usha Vihar Chsl
Other projects by Indu Enterprise
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.