Magnolia Cluster 1

by Wadhwa Construction and Infrastructure Private Limited · Wise city, Raigarh

Possession date of Magnolia Cluster 1: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000021143, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Magnolia Cluster 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Magnolia Cluster 1 has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Magnolia Cluster 1’s extension records on MahaRERA (P52000021143), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Magnolia Cluster 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000021143
Status
Registered and active
Builder
Wadhwa Construction and Infrastructure Private Limited
Location
Wise city, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
10 Jun 2019
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
61
Sold or booked
72%
Towers
60
Complaints on MahaRERA
3
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
27

Construction progress of Magnolia Cluster 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Magnolia Cluster 1 - A-01100%67%0%13%
Magnolia Cluster 1 - A-02100%67%0%13%
Magnolia Cluster 1- A-03100%100%41%65%
Magnolia Cluster 1 - A-04100%100%41%65%
Magnolia Cluster 1 - A-06100%100%100%99%
Magnolia Cluster 1 - A-070%0%0%0%
Magnolia Cluster 1 - A-05100%100%100%100%
Magnolia Cluster 1 - A-08100%100%100%100%
Magnolia Cluster 1 - A-09100%100%100%100%
Magnolia Cluster 1 - A-10100%100%100%100%
Magnolia Cluster 1 - A-13100%100%100%93%
Magnolia Cluster 1 - A-14100%100%100%100%
Magnolia Cluster 1 - A-15100%100%75%88%
Magnolia Cluster 1 - A-16100%100%100%99%
Magnolia Cluster 1 - A-11100%100%100%100%
Magnolia Cluster 1 - A-12100%100%100%93%
Magnolia Cluster 1 - A-17100%100%13%0%
Magnolia Cluster 1 - A-18100%100%13%0%
Magnolia Cluster 1 - A-190%0%0%0%
Magnolia Cluster 1 - A-260%0%0%0%
Magnolia Cluster 1 - A-200%0%0%0%
Magnolia Cluster 1 - A-210%0%0%0%
Magnolia Cluster 1 - A-220%0%0%0%
Magnolia Cluster 1 - A-230%0%0%0%
Magnolia Cluster 1 - A-240%0%0%0%
Magnolia Cluster 1 - A-250%0%0%0%
Magnolia Cluster 1 - E-01100%100%100%100%
Magnolia Cluster 1 - E-02100%100%100%100%
Magnolia Cluster 1 - E-03100%100%100%100%
Magnolia Cluster 1 - E-04100%100%52%71%

Showing 30 of 60 towers.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Magnolia Cluster 1 every month.

Magnolia Cluster 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: Magnolia Cluster 1 - A-01 (3 floors) · Magnolia Cluster 1 - A-02 (3 floors) · Magnolia Cluster 1- A-03 (3 floors) · Magnolia Cluster 1 - A-04 (3 floors) · Magnolia Cluster 1 - A-06 (3 floors) · Magnolia Cluster 1 - A-07 (3 floors) · Magnolia Cluster 1 - A-05 (3 floors) · Magnolia Cluster 1 - A-08 (3 floors) · and 22 more
  • Land: 10,527 sq m (about 2.6 acres) · sanctioned built-up 7,231 sq m · recreational space 957 sq m
  • Boundaries filed include: Town level play ground TL-PG-1

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Magnolia Cluster 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Magnolia Cluster 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Magnolia Cluster 1

What is the possession date of Magnolia Cluster 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Magnolia Cluster 1 in Wise city, Raigarh is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Magnolia Cluster 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Magnolia Cluster 1's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Magnolia Cluster 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Magnolia Cluster 1 in Wise city, Raigarh is P52000021143.

Is Magnolia Cluster 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1 is registered as P52000021143 and its status is "Registered and active".

What is the construction status of Magnolia Cluster 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does Magnolia Cluster 1 have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Magnolia Cluster 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1 is registered on MahaRERA as P52000021143, its completion date has not been moved by the builder and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Magnolia Cluster 1 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Magnolia Cluster 2 (P52000021142, possession 30 Apr 2027); Magnolia Cluster 3 (P52000021144, possession 30 Apr 2027); Magnolia Cluster 4 (P52000021746, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Magnolia Cluster 1's possession date changes?

The latest dates are on Magnolia Cluster 1's MahaRERA page (P52000021143). GharKundli's Kundli Watch sends a free WhatsApp update on Magnolia Cluster 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Magnolia Cluster 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1 has 30 buildings filed: Magnolia Cluster 1 - A-01 with 3 floors; Magnolia Cluster 1 - A-02 with 3 floors; Magnolia Cluster 1- A-03 with 3 floors; Magnolia Cluster 1 - A-04 with 3 floors; Magnolia Cluster 1 - A-06 with 3 floors; Magnolia Cluster 1 - A-07 with 3 floors; and 24 more.

How big is the land of Magnolia Cluster 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1 stands on 10,527 sq m of land (about 2.6 acres), with 7,231 sq m of sanctioned built-up area and 957 sq m of recreational open space.

Where can I read reviews of Magnolia Cluster 1?

Google Maps has reviews of Magnolia Cluster 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Magnolia Cluster 1?

Magnolia Cluster 1 by Wadhwa Construction and Infrastructure Private Limited is in Wise city, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000021143, per GharKundli's check of MahaRERA records. Its boundaries filed there include Town level play ground TL-PG-1.

How many homes are in Magnolia Cluster 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1 has 61 homes in 60 towers registered on MahaRERA, and 72% of them are sold or booked.

When was Magnolia Cluster 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Magnolia Cluster 1 was registered on MahaRERA on 10 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Magnolia Cluster 1?

No court cases are listed for Magnolia Cluster 1 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Magnolia Cluster 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Wadhwa Construction and Infrastructure Private Limited, which has 27 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Panvel

All 2,664 projects in Panvel (410206) →

Other projects by Wadhwa Construction and Infrastructure Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.