Magnolia Cluster 3
by Wadhwa Construction and Infrastructure Private Limited · Wise City, Raigarh
Possession date of Magnolia Cluster 3: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000021144, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Magnolia Cluster 3?
How the possession date of Magnolia Cluster 3 has moved
30 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Magnolia Cluster 3’s extension records on MahaRERA (P52000021144), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Magnolia Cluster 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Magnolia Cluster 1P52000021143 · possession 30 Apr 2027
- Magnolia Cluster 2P52000021142 · possession 30 Apr 2027
- Magnolia Cluster 4P52000021746 · possession 30 Apr 2027
- MahaRERA registration
- P52000021144
- Status
- Registered and active
- Builder
- Wadhwa Construction and Infrastructure Private Limited
- Location
- Wise City, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 10 Jun 2019
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 1
- Sold or booked
- 100%
- Towers
- 56
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 27
Construction progress of Magnolia Cluster 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Magnolia Cluster 3 - G-22 | 100% | 100% | 10% | 3% |
| Magnolia Cluster 3 - A-42 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - A-36 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - A-37 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - A-38 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - A-39 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - A-40 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - A-41 | 0% | 0% | 0% | 0% |
| Magnolia Cluster 3 - B-09 | 100% | 100% | 60% | 50% |
| Magnolia Cluster 3 - B-15 | 100% | 100% | 33% | 33% |
| Magnolia Cluster 3 - B-10 | 100% | 100% | 60% | 50% |
| Magnolia Cluster 3 - B-11 | 100% | 100% | 39% | 44% |
| Magnolia Cluster 3 - B-12 | 100% | 100% | 39% | 44% |
| Magnolia Cluster 3 - B-13 | 100% | 100% | 38% | 36% |
| Magnolia Cluster 3 - B-14 | 100% | 100% | 38% | 36% |
| Magnolia Cluster 3 - C-09 | 100% | 100% | 40% | 35% |
| Magnolia Cluster 3 - C-15 | 100% | 100% | 29% | 6% |
| Magnolia Cluster 3 - C-10 | 100% | 100% | 40% | 35% |
| Magnolia Cluster 3 - C-11 | 100% | 100% | 40% | 35% |
| Magnolia Cluster 3 - C-12 | 100% | 100% | 40% | 35% |
| Magnolia Cluster 3 - C-13 | 100% | 100% | 40% | 36% |
| Magnolia Cluster 3 - C-14 | 100% | 100% | 40% | 36% |
| Magnolia Cluster 3 - D-07 | 100% | 100% | 100% | 99% |
| Magnolia Cluster 3 - D-08 | 100% | 100% | 100% | 99% |
| Magnolia Cluster 3 - D-09 | 100% | 100% | 100% | 99% |
| Magnolia Cluster 3 - D-10 | 100% | 100% | 100% | 99% |
| Magnolia Cluster 3 - D-11 | 100% | 100% | 100% | 100% |
| Magnolia Cluster 3 - D-12 | 100% | 100% | 100% | 100% |
| Magnolia Cluster 3 - E-11 | 100% | 100% | 56% | 78% |
| Magnolia Cluster 3 - E-12 | 100% | 100% | 54% | 78% |
Showing 30 of 56 towers.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Magnolia Cluster 3 every month.
Magnolia Cluster 3: buildings, flats and land, as filed on MahaRERA
- Buildings: Magnolia Cluster 3 - G-22 (3 floors) · Magnolia Cluster 3 - A-42 (3 floors) · Magnolia Cluster 3 - A-36 (3 floors) · Magnolia Cluster 3 - A-37 (3 floors) · Magnolia Cluster 3 - A-38 (3 floors) · Magnolia Cluster 3 - A-39 (3 floors) · Magnolia Cluster 3 - A-40 (3 floors) · Magnolia Cluster 3 - A-41 (3 floors) · and 22 more
- Land: 8,825 sq m (about 2.2 acres) · sanctioned built-up 7,521 sq m · recreational space 802 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Magnolia Cluster 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Magnolia Cluster 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Magnolia Cluster 3
What is the possession date of Magnolia Cluster 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Magnolia Cluster 3 in Wise City, Raigarh is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Magnolia Cluster 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Magnolia Cluster 3's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Magnolia Cluster 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Magnolia Cluster 3 in Wise City, Raigarh is P52000021144.
Is Magnolia Cluster 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3 is registered as P52000021144 and its status is "Registered and active".
What is the construction status of Magnolia Cluster 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.
Does Magnolia Cluster 3 have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Magnolia Cluster 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3 is registered on MahaRERA as P52000021144, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Magnolia Cluster 3 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Magnolia Cluster 1 (P52000021143, possession 30 Apr 2027); Magnolia Cluster 2 (P52000021142, possession 30 Apr 2027); Magnolia Cluster 4 (P52000021746, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Magnolia Cluster 3's possession date changes?
The latest dates are on Magnolia Cluster 3's MahaRERA page (P52000021144). GharKundli's Kundli Watch sends a free WhatsApp update on Magnolia Cluster 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Magnolia Cluster 3 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3 has 30 buildings filed: Magnolia Cluster 3 - G-22 with 3 floors; Magnolia Cluster 3 - A-42 with 3 floors; Magnolia Cluster 3 - A-36 with 3 floors; Magnolia Cluster 3 - A-37 with 3 floors; Magnolia Cluster 3 - A-38 with 3 floors; Magnolia Cluster 3 - A-39 with 3 floors; and 24 more.
How big is the land of Magnolia Cluster 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3 stands on 8,825 sq m of land (about 2.2 acres), with 7,521 sq m of sanctioned built-up area and 802 sq m of recreational open space.
Where can I read reviews of Magnolia Cluster 3?
Google Maps has reviews of Magnolia Cluster 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Magnolia Cluster 3?
Magnolia Cluster 3 by Wadhwa Construction and Infrastructure Private Limited is in Wise City, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000021144, per GharKundli's check of MahaRERA records.
How many homes are in Magnolia Cluster 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3 has 1 home in 56 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Magnolia Cluster 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Magnolia Cluster 3 was registered on MahaRERA on 10 June 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Magnolia Cluster 3?
No court cases are listed for Magnolia Cluster 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Magnolia Cluster 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Wadhwa Construction and Infrastructure Private Limited, which has 27 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Magnolia Cluster 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Panvel
- Magnolia Cluster 2
- SAI SIDDHI MADHUBAN
- PRAKASH TOWER
- Crystal Co-Operative Housing Society Limited
- Shivesh Mahavir
- Sai Nilay
- Indiabulls Park 1
- Aaiji Residency
Other projects by Wadhwa Construction and Infrastructure Private Limited
- Wise City RZ-01 Plotted Development - Phase 3
- Wise City RZ-01 Plotted Development - Phase 2
- Wise City RZ-01 Plotted Development - Phase 1
- wise city, south Block, Phase I, Plot RZ8 Building 1 wing A3
- Wise City RZ8 Wing D5
- Wise City, South Block Phase I, Plot RZ8, Building 5 Wing D4
- Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4
- Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C3
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.