North Sea Heights (A1) - 19th floor
by Rare Townships Private Limited · Ghatkopar East, Mumbai
Possession: North Sea Heights (A1) - 19th floor is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800001037. Status: Completed. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about North Sea Heights (A1) - 19th floor?
How the possession date of North Sea Heights (A1) - 19th floor has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800018615)
Reason the builder gave MahaRERA:
“Reason for delay:- A Public Interest Litigation had been filed in High Court pleading to restrict the height to 77.68 Mts. The Honorable High Court issued its order on 06.04.2018 restricting the height of the building. Thereafter we receive…” Read the full reason
“Reason for delay:- A Public Interest Litigation had been filed in High Court pleading to restrict the height to 77.68 Mts. The Honorable High Court issued its order on 06.04.2018 restricting the height of the building. Thereafter we received the commencement certificate on 12.04.2022. And only on 25.08.2023, we got revised Environmental Clearance. Due to the said delays and constraints beyond our control the project got delayed. All documents referred to above are attached for your reference. Based on the same, request you to extend the Project completion date for a period of one year i.e.…”30 June 2026
Extended at the builder's request (MahaRERA application EA20022619919)
Reason the builder gave MahaRERA: “Construction completed before due date , however OC received late due to election duties for the government officers.”
Source: North Sea Heights (A1) - 19th floor’s extension records on MahaRERA (P51800001037), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on North Sea Heights (A1) - 19th floor
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800001037
- Status
- Completed
- Builder
- Rare Townships Private Limited
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 25 Jul 2017
- Completion date at registration
- December 2024
- Latest completion date
- June 2026
- Delay so far
- 18 months
- Homes
- 8
- Sold or booked
- 75%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 15
Construction progress of North Sea Heights (A1) - 19th floor, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| North Sea Heights - Above 19 Floor | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- North Sea Heights - Above 19 Floor: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on North Sea Heights (A1) - 19th floor every month.
North Sea Heights (A1) - 19th floor: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,071 – 1,177 | 4 |
| 2 BHK | 867 – 890 | 2 |
| Other | 1,029 | 2 |
- Buildings: North Sea Heights - Above 19 Floor (4 floors, 8 units)
- Car parking: 11 covered
- Land: 5,090 sq m (about 1.3 acres) · sanctioned built-up 860 sq m
The builder’s record and reviews
Rare Townships (a group of 2 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 15 finished, 4 within the promised date and 11 needed more time (typically 6 months); 8 still being built, none past the promised date yet. 219 complaints on MahaRERA across 18 projects.
Read Google reviews of North Sea Heights (A1) - 19th floor →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
North Sea Heights (A1) - 19th floor: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about North Sea Heights (A1) - 19th floor
What is the possession date of North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for North Sea Heights (A1) - 19th floor in Ghatkopar East, Mumbai is 30 June 2026 — 18 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for North Sea Heights (A1) - 19th floor?
Builders and listing sites often quote an earlier "target" date for handover. The completion date North Sea Heights (A1) - 19th floor's builder has filed on MahaRERA, the official one, is 30 June 2026, already 18 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of North Sea Heights (A1) - 19th floor extended?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "Reason for delay:- A Public Interest Litigation had been filed in High Court pleading to restrict the height to 77.68 Mts. The Honorable High Court issued its order on 06.04.2018 restricting the height of the building. Thereafter we received the commencement certificate on 12.04.2022. And only on 25.08.2023, we got revised Environmental Clearance. Due to the said delays and constraints beyond our control the project got delayed. All documents referred to above are attached for your reference. Based on the same, request you to extend the Project completion date for a period of one year i.e.…"; to 30 June 2026, giving the reason "Construction completed before due date , however OC received late due to election duties for the government officers.".
What is the RERA number of North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of North Sea Heights (A1) - 19th floor in Ghatkopar East, Mumbai is P51800001037.
Is North Sea Heights (A1) - 19th floor registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor is registered as P51800001037 and its status is "Completed".
What is the construction status of North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor's status on MahaRERA is "Completed". As filed by the builder, slab work on North Sea Heights - Above 19 Floor is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does North Sea Heights (A1) - 19th floor have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is North Sea Heights (A1) - 19th floor safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor is registered on MahaRERA as P51800001037, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if North Sea Heights (A1) - 19th floor's possession date changes?
The latest dates are on North Sea Heights (A1) - 19th floor's MahaRERA page (P51800001037). GharKundli's Kundli Watch sends a free WhatsApp update on North Sea Heights (A1) - 19th floor every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does North Sea Heights (A1) - 19th floor have?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor has one building filed: North Sea Heights - Above 19 Floor with 4 floors and 8 units.
What are the flat sizes (carpet area) in North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for North Sea Heights (A1) - 19th floor: 3 BHK: 1071 to 1177 sq ft carpet (4 homes); 2 BHK: 867 to 890 sq ft carpet (2 homes); Other: 1029 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does North Sea Heights (A1) - 19th floor have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 11 covered car parking spaces for North Sea Heights (A1) - 19th floor.
How big is the land of North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor stands on 5,090 sq m of land (about 1.3 acres), with 860 sq m of sanctioned built-up area.
What is the track record of North Sea Heights (A1) - 19th floor's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rare Townships (a group of 2 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 15 finished, 4 within the promised date and 11 needed more time (typically 6 months); 8 still being built, none past the promised date yet. 219 complaints on MahaRERA across 18 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of North Sea Heights (A1) - 19th floor?
Google Maps has reviews of North Sea Heights (A1) - 19th floor written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is North Sea Heights (A1) - 19th floor?
North Sea Heights (A1) - 19th floor by Rare Townships Private Limited is in Ghatkopar East, Mumbai (pincode 400077), Maharashtra, and is registered on MahaRERA as P51800001037, per GharKundli's check of MahaRERA records.
How many homes are in North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor has 8 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.
When was North Sea Heights (A1) - 19th floor registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), North Sea Heights (A1) - 19th floor was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on North Sea Heights (A1) - 19th floor?
No court cases are listed for North Sea Heights (A1) - 19th floor on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of North Sea Heights (A1) - 19th floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rare Townships Private Limited, which has 15 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of North Sea Heights (A1) - 19th floor
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ghatkopar East
- Jai Arihant
- Terraform Dwarka - Wing D
- Avis Residency
- Omkaar Pride
- Om Shreepal
- Damji Shamji Corporate Square - Wing C
- PALATINA
- North Sea Heights (A1) - upto 14th floor
Other projects by Rare Townships Private Limited
- North Sea Heights (A1) - upto 14th floor
- Manhattan Residency (A4) - upto 14th Floor
- Atlanta Heights (A3) - 19th Floor
- Houston Residency (A2) - 19th floor
- Atlanta Heights (A3) - 15th to 18th Floor
- North Sea Heights (A1) - 15th to 18th floor
- Houston Residency (A2) - upto 14th floor
- Houston Residency (A2) - 15th to 18th floor
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.