Manhattan Residency (A4) - 19th Floor
by Rare Township Private Limited · Ghatkopar East, MumbaiAlso near Gowandi, Santacruz East, Pant Nagar
Possession: Manhattan Residency (A4) - 19th Floor is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800001035. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Manhattan Residency (A4) - 19th Floor?
How the possession date of Manhattan Residency (A4) - 19th Floor has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800018624)
Reason the builder gave MahaRERA:
“The project completion date in the aforementioned projects needs to be extended on the MAHARERA PORTAL as the aforementioned Projects have faced several circumstances that were beyond the control of the Promoter and which the Promoter could…” Read the full reason
“The project completion date in the aforementioned projects needs to be extended on the MAHARERA PORTAL as the aforementioned Projects have faced several circumstances that were beyond the control of the Promoter and which the Promoter could not have reasonably anticipated. The circumstances that arose in the aforesaid projects have led to a extension in the timeline for completion of the aforesaid projects, which is presently necessitating the Promoter to seek an Extension of the completion date of the aforesaid projects from MahaRERA.The mitigating circumstances that were beyond the contro…”
Source: Manhattan Residency (A4) - 19th Floor’s extension records on MahaRERA (P51800001035), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Manhattan Residency (A4) - 19th Floor
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800001035
- Status
- Completed
- Builder
- Rare Township Private Limited
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 25 Jul 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 4
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Manhattan Residency (A4) - 19th Floor, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Rising City - Manhattan Residency - Above 19 Floor | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Rising City - Manhattan Residency - Above 19 Floor: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Manhattan Residency (A4) - 19th Floor every month.
Manhattan Residency (A4) - 19th Floor: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 634 | 4 |
- Buildings: Rising City - Manhattan Residency - Above 19 Floor (4 floors, 4 units)
- Land: 1,980 sq m (about 0.5 acres) · sanctioned built-up 275 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Rare Townships (a group of 2 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 15 finished, 4 within the promised date and 11 needed more time (typically 6 months); 8 still being built, none past the promised date yet. 219 complaints on MahaRERA across 18 projects.
Read Google reviews of Manhattan Residency (A4) - 19th Floor →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Manhattan Residency (A4) - 19th Floor: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Manhattan Residency (A4) - 19th Floor
What is the possession date of Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Manhattan Residency (A4) - 19th Floor in Ghatkopar East, Mumbai is 30 December 2025 — 12 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Manhattan Residency (A4) - 19th Floor?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Manhattan Residency (A4) - 19th Floor's builder has filed on MahaRERA, the official one, is 30 December 2025, already 12 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Manhattan Residency (A4) - 19th Floor extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor's builder applied to MahaRERA to extend the completion date once: to 30 December 2025, giving the reason "The project completion date in the aforementioned projects needs to be extended on the MAHARERA PORTAL as the aforementioned Projects have faced several circumstances that were beyond the control of the Promoter and which the Promoter could not have reasonably anticipated. The circumstances that arose in the aforesaid projects have led to a extension in the timeline for completion of the aforesaid projects, which is presently necessitating the Promoter to seek an Extension of the completion date of the aforesaid projects from MahaRERA.The mitigating circumstances that were beyond the contro…".
What is the RERA number of Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Manhattan Residency (A4) - 19th Floor in Ghatkopar East, Mumbai is P51800001035.
Is Manhattan Residency (A4) - 19th Floor registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor is registered as P51800001035 and its status is "Completed".
What is the construction status of Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor's status on MahaRERA is "Completed". As filed by the builder, slab work on Rising City - Manhattan Residency - Above 19 Floor is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Manhattan Residency (A4) - 19th Floor have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Manhattan Residency (A4) - 19th Floor safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor is registered on MahaRERA as P51800001035, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Manhattan Residency (A4) - 19th Floor's possession date changes?
The latest dates are on Manhattan Residency (A4) - 19th Floor's MahaRERA page (P51800001035). GharKundli's Kundli Watch sends a free WhatsApp update on Manhattan Residency (A4) - 19th Floor every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Manhattan Residency (A4) - 19th Floor have?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor has one building filed: Rising City - Manhattan Residency - Above 19 Floor with 4 floors and 4 units.
What are the flat sizes (carpet area) in Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Manhattan Residency (A4) - 19th Floor: 2 BHK: 634 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor stands on 1,980 sq m of land (about 0.5 acres), with 275 sq m of sanctioned built-up area.
What is the track record of Manhattan Residency (A4) - 19th Floor's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rare Townships (a group of 2 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 15 finished, 4 within the promised date and 11 needed more time (typically 6 months); 8 still being built, none past the promised date yet. 219 complaints on MahaRERA across 18 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Manhattan Residency (A4) - 19th Floor?
Google Maps has reviews of Manhattan Residency (A4) - 19th Floor written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Manhattan Residency (A4) - 19th Floor?
Manhattan Residency (A4) - 19th Floor by Rare Township Private Limited is in Ghatkopar East, Mumbai (pincode 400077), near Gowandi, Santacruz East, Pant Nagar, Maharashtra, and is registered on MahaRERA as P51800001035, per GharKundli's check of MahaRERA records.
How many homes are in Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor has 4 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Manhattan Residency (A4) - 19th Floor registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Residency (A4) - 19th Floor was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Manhattan Residency (A4) - 19th Floor?
No court cases are listed for Manhattan Residency (A4) - 19th Floor on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Manhattan Residency (A4) - 19th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rare Township Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Manhattan Residency (A4) - 19th Floor
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ghatkopar East
- Jai Arihant
- Terraform Dwarka - Wing D
- Avis Residency
- Omkaar Pride
- PALATINA
- North Sea Heights (A1) - upto 14th floor
- Damji Shamji Corporate Square - Wing C
- Manhattan Residency (A4) - upto 14th Floor
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.