ASHOK ODYSSEY - A WING

by SANYAM REALTORS PRIVATE LIMITED · Ghatkopar West, MumbaiAlso near Barve Nagar, Vikhroli, Pant Nagar

Possession date of ASHOK ODYSSEY - A WING: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005268, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ASHOK ODYSSEY - A WING?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ASHOK ODYSSEY - A WING has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800013870)

    Reason the builder gave MahaRERA:
    “Project is likely to get delayed in obtaining Occupation due to ongoing realignment of boundaries with the adjoining plot that is being developed under SRA. The realignment of boundaries however shall have no impact on total FSI but the pro…” Read the full reason“Project is likely to get delayed in obtaining Occupation due to ongoing realignment of boundaries with the adjoining plot that is being developed under SRA. The realignment of boundaries however shall have no impact on total FSI but the procedure of realignment involved various government agencies and it is likely that the Occupation may not be obtained within the prescribed time. Thus to avoid misrepresentation to the public at large, this Applicant seeks to seek extension of the proposed date of completion.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025822)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. We kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements.”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA20122518865)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.The completion of the project and the submission of this request have been delayed due to several unforeseen circumstances encountered during the execution phase. These circumstances included procurement-related challenges such as delays in the sourcing and deliver…”
  5. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ASHOK ODYSSEY - A WING’s extension records on MahaRERA (P51800005268), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ASHOK ODYSSEY - A WING

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 10 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005268
Status
Registered and active
Builder
SANYAM REALTORS PRIVATE LIMITED
Location
Ghatkopar West, Mumbai · 400086
Project type
Residential / Group Housing
Registered on
11 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
59
Sold or booked
78%
Towers
1
Complaints on MahaRERA
1
Court cases listed
10
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of ASHOK ODYSSEY - A WING, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Ashok Odyssey - A Wing100%84%84%84%

Commencement certificate (CC), as filed on MahaRERA

  • Ashok Odyssey - A Wing: covers Ground+1 Lower First Floor+1 Upper First Floor+10 Upper Floors

Latest CC order on MahaRERA: dated 14/05/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ASHOK ODYSSEY - A WING every month.

ASHOK ODYSSEY - A WING: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK394 – 49459
  • Buildings: Ashok Odyssey - A Wing (13 floors, 59 units)
  • Car parking: 15 covered
  • Land: 2,878 sq m (about 0.7 acres) · sanctioned built-up 2,470 sq m

The builder’s record and reviews

Sanyam Realtors has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 12 months late). 12 complaints on MahaRERA across 3 projects.

Read Google reviews of ASHOK ODYSSEY - A WING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ASHOK ODYSSEY - A WING: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ASHOK ODYSSEY - A WING

What is the possession date of ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ASHOK ODYSSEY - A WING in Ghatkopar West, Mumbai is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ASHOK ODYSSEY - A WING?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ASHOK ODYSSEY - A WING's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ASHOK ODYSSEY - A WING extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "Project is likely to get delayed in obtaining Occupation due to ongoing realignment of boundaries with the adjoining plot that is being developed under SRA. The realignment of boundaries however shall have no impact on total FSI but the procedure of realignment involved various government agencies and it is likely that the Occupation may not be obtained within the prescribed time. Thus to avoid misrepresentation to the public at large, this Applicant seeks to seek extension of the proposed date of completion."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. We kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements."; to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.The completion of the project and the submission of this request have been delayed due to several unforeseen circumstances encountered during the execution phase. These circumstances included procurement-related challenges such as delays in the sourcing and deliver…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ASHOK ODYSSEY - A WING in Ghatkopar West, Mumbai is P51800005268.

Is ASHOK ODYSSEY - A WING registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING is registered as P51800005268 and its status is "Registered and active".

What is the construction status of ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ashok Odyssey - A Wing is 84% done and internal work 84%. GharKundli's full report compares construction progress with the deadline.

Does ASHOK ODYSSEY - A WING have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ASHOK ODYSSEY - A WING safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING is registered on MahaRERA as P51800005268, its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ASHOK ODYSSEY - A WING's possession date changes?

The latest dates are on ASHOK ODYSSEY - A WING's MahaRERA page (P51800005268). GharKundli's Kundli Watch sends a free WhatsApp update on ASHOK ODYSSEY - A WING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ASHOK ODYSSEY - A WING have?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING has one building filed: Ashok Odyssey - A Wing with 13 floors and 59 units.

What are the flat sizes (carpet area) in ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ASHOK ODYSSEY - A WING: 1 BHK: 394 to 494 sq ft carpet (59 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does ASHOK ODYSSEY - A WING have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for ASHOK ODYSSEY - A WING.

How big is the land of ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING stands on 2,878 sq m of land (about 0.7 acres), with 2,470 sq m of sanctioned built-up area.

What is the track record of ASHOK ODYSSEY - A WING's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sanyam Realtors has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 12 months late). 12 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ASHOK ODYSSEY - A WING?

Google Maps has reviews of ASHOK ODYSSEY - A WING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ASHOK ODYSSEY - A WING?

ASHOK ODYSSEY - A WING by SANYAM REALTORS PRIVATE LIMITED is in Ghatkopar West, Mumbai (pincode 400086), near Barve Nagar, Vikhroli, Pant Nagar, Maharashtra, and is registered on MahaRERA as P51800005268, per GharKundli's check of MahaRERA records.

How many homes are in ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING has 59 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.

When was ASHOK ODYSSEY - A WING registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ASHOK ODYSSEY - A WING was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ASHOK ODYSSEY - A WING?

10 court cases are listed for ASHOK ODYSSEY - A WING on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ASHOK ODYSSEY - A WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANYAM REALTORS PRIVATE LIMITED, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in pincode 400086

All 83 projects in Ghatkopar West (400086) →

Other projects by SANYAM REALTORS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.