Kadri Residency
by Yaqub AbbasAli Khan · Ghatkopar West, MumbaiAlso near Rajawadi, Pant Nagar, Barve Nagar
Possession: Kadri Residency is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800024376. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Kadri Residency?
How the possession date of Kadri Residency has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800024999)
Reason the builder gave MahaRERA:
“Project was delayed due to Flamingo Thane Creek Sanctuary, Private Fire Consultant barred from issuing NOC for building under 32 meters perhaps work of the building is completed (1) Final Fire NOC for Occupation has been obtained from fire…” Read the full reason
“Project was delayed due to Flamingo Thane Creek Sanctuary, Private Fire Consultant barred from issuing NOC for building under 32 meters perhaps work of the building is completed (1) Final Fire NOC for Occupation has been obtained from fire department and (2) 270A - Adequate Water Supply Certificate has been obtained from Water department and the the file has been forwarded of Occupation Certificate”31 December 2026
Extended at the builder's request (MahaRERA application EA10062621299)
Reason the builder gave MahaRERA:
“The said Project is Completed, Occupation Certificate has been obtained and Possession of the sold Flats has been handed over. Previously we had submitted for Completion however a query was raised wherein it was advised to submitted for Cor…” Read the full reason
“The said Project is Completed, Occupation Certificate has been obtained and Possession of the sold Flats has been handed over. Previously we had submitted for Completion however a query was raised wherein it was advised to submitted for Correction Application since the last inserted details are not matching with the Last Approved Plan.”
Source: Kadri Residency’s extension records on MahaRERA (P51800024376), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kadri Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800024376
- Status
- Completed
- Builder
- Yaqub AbbasAli Khan
- Location
- Ghatkopar West, Mumbai · 400086
- Project type
- Residential / Group Housing
- Registered on
- 10 Feb 2020
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 40
- Sold or booked
- 41%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Kadri Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kadri Residency | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Kadri Residency: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kadri Residency every month.
Kadri Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 379 – 484 | 34 |
| 2 BHK | 635 – 643 | 3 |
| 1 Room Kitchen | 270 | 3 |
| Multi Purpose Room | 139 | 1 |
- Buildings: Kadri Residency (11 floors, 41 units)
- Car parking: 9 covered, 1 open
- Land: 923 sq m (about 0.2 acres) · sanctioned built-up 1,834 sq m
The builder’s record and reviews
Kadri Construction has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Kadri Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kadri Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kadri Residency
What is the possession date of Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kadri Residency in Ghatkopar West, Mumbai is 31 December 2026 — 24 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Kadri Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kadri Residency's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kadri Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "Project was delayed due to Flamingo Thane Creek Sanctuary, Private Fire Consultant barred from issuing NOC for building under 32 meters perhaps work of the building is completed (1) Final Fire NOC for Occupation has been obtained from fire department and (2) 270A - Adequate Water Supply Certificate has been obtained from Water department and the the file has been forwarded of Occupation Certificate"; to 31 December 2026, giving the reason "The said Project is Completed, Occupation Certificate has been obtained and Possession of the sold Flats has been handed over. Previously we had submitted for Completion however a query was raised wherein it was advised to submitted for Correction Application since the last inserted details are not matching with the Last Approved Plan.".
What is the RERA number of Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kadri Residency in Ghatkopar West, Mumbai is P51800024376.
Is Kadri Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency is registered as P51800024376 and its status is "Completed".
What is the construction status of Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency's status on MahaRERA is "Completed". As filed by the builder, slab work on Kadri Residency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Kadri Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kadri Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency is registered on MahaRERA as P51800024376, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Kadri Residency's possession date changes?
The latest dates are on Kadri Residency's MahaRERA page (P51800024376). GharKundli's Kundli Watch sends a free WhatsApp update on Kadri Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kadri Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency has one building filed: Kadri Residency with 11 floors and 41 units.
What are the flat sizes (carpet area) in Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kadri Residency: 1 BHK: 379 to 484 sq ft carpet (34 homes); 2 BHK: 635 to 643 sq ft carpet (3 homes); 1 Room Kitchen: 270 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Kadri Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered and 1 open car parking spaces for Kadri Residency.
How big is the land of Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency stands on 923 sq m of land (about 0.2 acres), with 1,834 sq m of sanctioned built-up area.
What is the track record of Kadri Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Construction has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kadri Residency?
Google Maps has reviews of Kadri Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kadri Residency?
Kadri Residency by Yaqub AbbasAli Khan is in Ghatkopar West, Mumbai (pincode 400086), near Rajawadi, Pant Nagar, Barve Nagar, Maharashtra, and is registered on MahaRERA as P51800024376, per GharKundli's check of MahaRERA records.
How many homes are in Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency has 40 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.
When was Kadri Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kadri Residency was registered on MahaRERA on 10 February 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on Kadri Residency?
No court cases are listed for Kadri Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Kadri Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Yaqub AbbasAli Khan.
Check it yourself on MahaRERA
- How to check the possession date of Kadri Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400086
- ASHOK ODYSSEY - A WING
- Elanza Commercial
- Tivon Park Wing E and F
- BHUVNESHWAR VINTAGE
- Crystal Palladian 207
- 72 WEST
- Neelyog Regent
- Redevlopement of SBI Madhur Milan CHSL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.