BHUVNESHWAR VINTAGE
by S P INFRA (Arihant) · Ghatkopar West, MumbaiAlso near Ghatkopar East, Pant Nagar, Vile Parle West
Possession date of BHUVNESHWAR VINTAGE: 30 December 2026, moved from 30 March 2023 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800022717, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BHUVNESHWAR VINTAGE?
How the possession date of BHUVNESHWAR VINTAGE has moved
30 March 2023
Completion date given when the project was registered
29 March 2024
Extended at the builder's request (MahaRERA application EXT51800015239)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800024918)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-06-2026. to complete the project and fulfil all regulatory requirements.”30 June 2026
Extended at the builder's request (MahaRERA application EA06012619322)
Reason the builder gave MahaRERA:
“We wish to state that the project is nearly completed, with all major construction and finishing works already executed. The only pending requirement is the issuance of the Occupation Certificate (OC) from the local authority. Despite timel…” Read the full reason
“We wish to state that the project is nearly completed, with all major construction and finishing works already executed. The only pending requirement is the issuance of the Occupation Certificate (OC) from the local authority. Despite timely submission of all necessary documents and compliance with statutory norms, the approval process is taking longer than expected due to administrative procedures. Hence, we request a RERA extension to cover the period until the OC is received and completion formalities are finalized.”30 December 2026
Extended at the builder's request (MahaRERA application EA16072621774)
Reason the builder gave MahaRERA:
“The above-mentioned project was duly registered with MahaRERA. However, due to certain unforeseen and unavoidable circumstances, the project could not be completed within the originally stipulated timeline. Reasons for Seeking Extension The…” Read the full reason
“The above-mentioned project was duly registered with MahaRERA. However, due to certain unforeseen and unavoidable circumstances, the project could not be completed within the originally stipulated timeline. Reasons for Seeking Extension The progress of the project was adversely affected due to procurement-related issues, unforeseen site conditions, coordination challenges among contractors and consultants, and temporary financial constraints, which impacted the pace of construction and execution of the remaining work. Further, although substantial construction work has been completed, the p…”
Source: BHUVNESHWAR VINTAGE’s extension records on MahaRERA (P51800022717), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BHUVNESHWAR VINTAGE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800022717
- Status
- Registered and active
- Builder
- S P INFRA
- Location
- Ghatkopar West, Mumbai · 400086
- Project type
- Residential / Group Housing
- Registered on
- 12 Oct 2019
- Completion date at registration
- March 2023
- Latest completion date
- December 2026
- Delay so far
- 45 months
- Homes
- 21
- Sold or booked
- 38%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of BHUVNESHWAR VINTAGE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BHUVNESHWAR VINTAGE | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BHUVNESHWAR VINTAGE: covers 9 (Ground + 1 Mezzanine Floor + 7 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHUVNESHWAR VINTAGE every month.
BHUVNESHWAR VINTAGE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 538 – 596 | 14 |
| 3 BHK | 813 | 7 |
- Buildings: BHUVNESHWAR VINTAGE (9 floors, 21 units)
- Land: 540 sq m (about 0.1 acres) · sanctioned built-up 1,009 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects.
Read Google reviews of BHUVNESHWAR VINTAGE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BHUVNESHWAR VINTAGE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BHUVNESHWAR VINTAGE
What is the possession date of BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BHUVNESHWAR VINTAGE in Ghatkopar West, Mumbai is 30 December 2026 — 45 months later than 30 March 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for BHUVNESHWAR VINTAGE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BHUVNESHWAR VINTAGE's builder has filed on MahaRERA, the official one, is 30 December 2026, already 45 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BHUVNESHWAR VINTAGE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE's builder applied to MahaRERA to extend the completion date 4 times: to 29 March 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 June 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-06-2026. to complete the project and fulfil all regulatory requirements."; to 30 June 2026, giving the reason "We wish to state that the project is nearly completed, with all major construction and finishing works already executed. The only pending requirement is the issuance of the Occupation Certificate (OC) from the local authority. Despite timely submission of all necessary documents and compliance with statutory norms, the approval process is taking longer than expected due to administrative procedures. Hence, we request a RERA extension to cover the period until the OC is received and completion formalities are finalized."; to 30 December 2026, giving the reason "The above-mentioned project was duly registered with MahaRERA. However, due to certain unforeseen and unavoidable circumstances, the project could not be completed within the originally stipulated timeline. Reasons for Seeking Extension The progress of the project was adversely affected due to procurement-related issues, unforeseen site conditions, coordination challenges among contractors and consultants, and temporary financial constraints, which impacted the pace of construction and execution of the remaining work. Further, although substantial construction work has been completed, the p…".
What is the RERA number of BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BHUVNESHWAR VINTAGE in Ghatkopar West, Mumbai is P51800022717.
Is BHUVNESHWAR VINTAGE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE is registered as P51800022717 and its status is "Registered and active".
What is the construction status of BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BHUVNESHWAR VINTAGE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does BHUVNESHWAR VINTAGE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is BHUVNESHWAR VINTAGE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE is registered on MahaRERA as P51800022717, its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BHUVNESHWAR VINTAGE's possession date changes?
The latest dates are on BHUVNESHWAR VINTAGE's MahaRERA page (P51800022717). GharKundli's Kundli Watch sends a free WhatsApp update on BHUVNESHWAR VINTAGE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BHUVNESHWAR VINTAGE have?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE has one building filed: BHUVNESHWAR VINTAGE with 9 floors and 21 units.
What are the flat sizes (carpet area) in BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for BHUVNESHWAR VINTAGE: 2 BHK: 538 to 596 sq ft carpet (14 homes); 3 BHK: 813 sq ft carpet (7 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE stands on 540 sq m of land (about 0.1 acres), with 1,009 sq m of sanctioned built-up area.
What is the track record of BHUVNESHWAR VINTAGE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BHUVNESHWAR VINTAGE?
Google Maps has reviews of BHUVNESHWAR VINTAGE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BHUVNESHWAR VINTAGE?
BHUVNESHWAR VINTAGE by S P INFRA (Arihant) is in Ghatkopar West, Mumbai (pincode 400086), near Ghatkopar East, Pant Nagar, Vile Parle West, Maharashtra, and is registered on MahaRERA as P51800022717, per GharKundli's check of MahaRERA records.
How many homes are in BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE has 21 homes in 1 tower registered on MahaRERA, and 38% of them are sold or booked.
When was BHUVNESHWAR VINTAGE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BHUVNESHWAR VINTAGE was registered on MahaRERA on 12 October 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on BHUVNESHWAR VINTAGE?
No court cases are listed for BHUVNESHWAR VINTAGE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of BHUVNESHWAR VINTAGE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S P INFRA, the company Arihant files this project under.
Check it yourself on MahaRERA
- How to check the possession date of BHUVNESHWAR VINTAGE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400086
- ASHOK ODYSSEY - A WING
- Elanza Commercial
- Tivon Park Wing E and F
- Kadri Residency
- Crystal Palladian 207
- 72 WEST
- Neelyog Regent
- Redevlopement of SBI Madhur Milan CHSL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.