Tivon Park Wing E and F

by D S Developers (Vinayak) · Ghatkopar- West, MumbaiAlso near Barve Nagar, Rajawadi

Possession date of Tivon Park Wing E and F: 30 April 2027, moved from 31 December 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800003235, and currently active. Its completion date has moved from December 2018 to April 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Tivon Park Wing E and F?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Tivon Park Wing E and F has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT51800001035)

    Reason the builder gave MahaRERA: “As the Naval Department is not issuing NOC BMC is not issuing Occupation Certificate”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51800006127)

    Reason the builder gave MahaRERA:
    “Pursuant to the IOD dated 08/08/2013 as revised from time to time and as per the last amendment dated 25/08/2015 issued by Municipal Corporation of Greater Mumbai (MCGM) we commenced the construction of Wings E&F after obtaining all due app…” Read the full reason“Pursuant to the IOD dated 08/08/2013 as revised from time to time and as per the last amendment dated 25/08/2015 issued by Municipal Corporation of Greater Mumbai (MCGM) we commenced the construction of Wings E&F after obtaining all due approvals and the same was nearing completion. In the midst thereof MCGM insisted Naval NOC in terms of circular under reference bearing no. F11026/2/2011/D(Lands) dated 17.11.2015. Accordingly, we made an application dated 14.11.2017 for obtaining NOC from Navy Department. The same has not been considered by the concerned Naval authorities stating that “the…”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800016949)

    Reason the builder gave MahaRERA:
    “Due to the guideline issued by the Defence Ministry to have mandatory buffer zone of minimum 500 meters of radius from the Naval establishment, the building proposal and/or other competent authority/department is not granting the required a…” Read the full reason“Due to the guideline issued by the Defence Ministry to have mandatory buffer zone of minimum 500 meters of radius from the Naval establishment, the building proposal and/or other competent authority/department is not granting the required approvals/permission as required for completing the project.”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Tivon Park Wing E and F’s extension records on MahaRERA (P51800003235), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tivon Park Wing E and F

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800003235
Status
Registered and active
Builder
D S Developers
Location
Ghatkopar- West, Mumbai · 400086
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
December 2018
Latest completion date
April 2027
Delay so far
96 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
54
Sold or booked
100%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Tivon Park Wing E and F, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tivon Park - Wing E and F100%100%100%97%

Commencement certificate (CC), as filed on MahaRERA

  • Tivon Park - Wing E and F: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tivon Park Wing E and F every month.

Tivon Park Wing E and F: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK591 – 73854

The builder’s record and reviews

Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects.

Read Google reviews of Tivon Park Wing E and F →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tivon Park Wing E and F: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Tivon Park Wing E and F

What is the possession date of Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tivon Park Wing E and F in Ghatkopar- West, Mumbai is 30 April 2027 — 96 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Tivon Park Wing E and F?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tivon Park Wing E and F's builder has filed on MahaRERA, the official one, is 30 April 2027, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Tivon Park Wing E and F extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2019, giving the reason "As the Naval Department is not issuing NOC BMC is not issuing Occupation Certificate"; to 31 December 2022, giving the reason "Pursuant to the IOD dated 08/08/2013 as revised from time to time and as per the last amendment dated 25/08/2015 issued by Municipal Corporation of Greater Mumbai (MCGM) we commenced the construction of Wings E&F after obtaining all due approvals and the same was nearing completion. In the midst thereof MCGM insisted Naval NOC in terms of circular under reference bearing no. F11026/2/2011/D(Lands) dated 17.11.2015. Accordingly, we made an application dated 14.11.2017 for obtaining NOC from Navy Department. The same has not been considered by the concerned Naval authorities stating that “the…"; to 31 December 2026, giving the reason "Due to the guideline issued by the Defence Ministry to have mandatory buffer zone of minimum 500 meters of radius from the Naval establishment, the building proposal and/or other competent authority/department is not granting the required approvals/permission as required for completing the project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tivon Park Wing E and F in Ghatkopar- West, Mumbai is P51800003235.

Is Tivon Park Wing E and F registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F is registered as P51800003235 and its status is "Registered and active".

What is the construction status of Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tivon Park - Wing E and F is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Tivon Park Wing E and F have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Tivon Park Wing E and F safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F is registered on MahaRERA as P51800003235, its completion date has moved 96 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Tivon Park Wing E and F have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Tivon Park Wing G and H (P51800009120, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Tivon Park Wing E and F's possession date changes?

The latest dates are on Tivon Park Wing E and F's MahaRERA page (P51800003235). GharKundli's Kundli Watch sends a free WhatsApp update on Tivon Park Wing E and F every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tivon Park Wing E and F have?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F has one building filed: Tivon Park - Wing E and F with 11 floors and 54 units.

What are the flat sizes (carpet area) in Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Tivon Park Wing E and F: 2 BHK: 591 to 738 sq ft carpet (54 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F stands on 511 sq m of land (about 0.1 acres), with 4,017 sq m of sanctioned built-up area.

What is the track record of Tivon Park Wing E and F's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Tivon Park Wing E and F?

Google Maps has reviews of Tivon Park Wing E and F written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Tivon Park Wing E and F?

Tivon Park Wing E and F by D S Developers (Vinayak) is in Ghatkopar- West, Mumbai (pincode 400086), near Barve Nagar, Rajawadi, Maharashtra, and is registered on MahaRERA as P51800003235, per GharKundli's check of MahaRERA records.

How many homes are in Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F has 54 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Tivon Park Wing E and F registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tivon Park Wing E and F was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Tivon Park Wing E and F?

No court cases are listed for Tivon Park Wing E and F on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Tivon Park Wing E and F?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is D S Developers, the company Vinayak files this project under, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400086

All 83 projects in Ghatkopar West (400086) →

Other projects by D S Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.