EKTA PARKSVILLE PHASE I
by EKTA PARKSVILLE HOMES PVT. LTD. · Virar, Palghar
Possession: EKTA PARKSVILLE PHASE I is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000000116. Status: Completed. 27 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about EKTA PARKSVILLE PHASE I?
How the possession date of EKTA PARKSVILLE PHASE I has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT99000001904)
Reason the builder gave MahaRERA: “Due to Scarcity of availability of the resources and also some technical reasons.”
31 March 2023
Extended at the builder's request (MahaRERA application EXT99000011390)
Reason the builder gave MahaRERA:
“Due to following force majeure conditions project got delayed:- 1. Non availability of Building Material 2. Stop Work notices issued time to time by VVCMC 3. Delay in getting permissions from the Environments and Pollution Department 4. Loc…” Read the full reason
“Due to following force majeure conditions project got delayed:- 1. Non availability of Building Material 2. Stop Work notices issued time to time by VVCMC 3. Delay in getting permissions from the Environments and Pollution Department 4. Lockdown Due to Novel Corona Virus Pandemic. 5. Non Availability of Labor due to Covid”27 July 2023
Extended at the builder's request (MahaRERA application EXT99000016860)
Reason the builder gave MahaRERA: “Reason as per attached herewith.”
Source: EKTA PARKSVILLE PHASE I’s extension records on MahaRERA (P99000000116), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EKTA PARKSVILLE PHASE I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 27 complaints and 4 court cases, and how it ended
- Construction pace against the July 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- EKTA PARKSVILLE PHASE IIIP99000000109 · possession 30 Dec 2023
- Ekta Parksville Phase IVP99000015239 · possession 30 Apr 2029
- MahaRERA registration
- P99000000116
- Status
- Completed
- Builder
- EKTA PARKSVILLE HOMES PVT. LTD.
- Location
- Virar, Palghar · 401303
- Project type
- Residential / Group Housing
- Registered on
- 4 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- July 2023
- Delay so far
- 43 months
- Homes
- 646
- Towers
- 9
- Complaints on MahaRERA
- 27
- Court cases listed
- 4
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of EKTA PARKSVILLE PHASE I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CENTRAL PARK A WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK B WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK C WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK D WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK E WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK F WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK G WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK H WING | 100% | 100% | 100% | 100% |
| CENTRAL PARK K WING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EKTA PARKSVILLE PHASE I every month.
EKTA PARKSVILLE PHASE I: buildings, flats and land, as filed on MahaRERA
- Buildings: CENTRAL PARK A WING (17 floors) · CENTRAL PARK B WING (17 floors) · CENTRAL PARK C WING (17 floors) · CENTRAL PARK D WING (17 floors) · CENTRAL PARK E WING (17 floors) · CENTRAL PARK F WING (17 floors) · CENTRAL PARK G WING (17 floors) · CENTRAL PARK H WING (17 floors) · and 1 more
- Land: 2,843 sq m (about 0.7 acres) · sanctioned built-up 26,079 sq m · recreational space 1,043 sq m
The builder’s record and reviews
Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 181 complaints on MahaRERA across 6 projects.
Read Google reviews of EKTA PARKSVILLE PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EKTA PARKSVILLE PHASE I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EKTA PARKSVILLE PHASE I
What is the possession date of EKTA PARKSVILLE PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EKTA PARKSVILLE PHASE I in Virar, Palghar is 27 July 2023 — 43 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EKTA PARKSVILLE PHASE I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EKTA PARKSVILLE PHASE I's builder has filed on MahaRERA, the official one, is 27 July 2023, already 43 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EKTA PARKSVILLE PHASE I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "Due to Scarcity of availability of the resources and also some technical reasons."; to 31 March 2023, giving the reason "Due to following force majeure conditions project got delayed:- 1. Non availability of Building Material 2. Stop Work notices issued time to time by VVCMC 3. Delay in getting permissions from the Environments and Pollution Department 4. Lockdown Due to Novel Corona Virus Pandemic. 5. Non Availability of Labor due to Covid"; to 27 July 2023, giving the reason "Reason as per attached herewith.".
What is the RERA number of EKTA PARKSVILLE PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EKTA PARKSVILLE PHASE I in Virar, Palghar is P99000000116.
Is EKTA PARKSVILLE PHASE I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I is registered as P99000000116 and its status is "Completed".
What is the construction status of EKTA PARKSVILLE PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 9 towers. GharKundli's full report compares construction progress with the deadline.
Does EKTA PARKSVILLE PHASE I have complaints on MahaRERA?
27 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is EKTA PARKSVILLE PHASE I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I is registered on MahaRERA as P99000000116, its MahaRERA status is "Completed", its completion date has moved 43 months since registration and 27 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does EKTA PARKSVILLE PHASE I have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: EKTA PARKSVILLE PHASE III (P99000000109, possession 30 Dec 2023); Ekta Parksville Phase IV (P99000015239, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.
How can I get updates if EKTA PARKSVILLE PHASE I's possession date changes?
The latest dates are on EKTA PARKSVILLE PHASE I's MahaRERA page (P99000000116). GharKundli's Kundli Watch sends a free WhatsApp update on EKTA PARKSVILLE PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EKTA PARKSVILLE PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I has 9 buildings filed: CENTRAL PARK A WING with 17 floors; CENTRAL PARK B WING with 17 floors; CENTRAL PARK C WING with 17 floors; CENTRAL PARK D WING with 17 floors; CENTRAL PARK E WING with 17 floors; CENTRAL PARK F WING with 17 floors; and 3 more.
How big is the land of EKTA PARKSVILLE PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I stands on 2,843 sq m of land (about 0.7 acres), with 26,079 sq m of sanctioned built-up area and 1,043 sq m of recreational open space.
What is the track record of EKTA PARKSVILLE PHASE I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 181 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of EKTA PARKSVILLE PHASE I?
Google Maps has reviews of EKTA PARKSVILLE PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 27 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EKTA PARKSVILLE PHASE I?
EKTA PARKSVILLE PHASE I by EKTA PARKSVILLE HOMES PVT. LTD. is in Virar, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000000116, per GharKundli's check of MahaRERA records.
How many homes are in EKTA PARKSVILLE PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I has 646 homes in 9 towers registered on MahaRERA.
When was EKTA PARKSVILLE PHASE I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE I was registered on MahaRERA on 4 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EKTA PARKSVILLE PHASE I?
4 court cases are listed for EKTA PARKSVILLE PHASE I on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of EKTA PARKSVILLE PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EKTA PARKSVILLE HOMES PVT. LTD., which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of EKTA PARKSVILLE PHASE I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401303
- VIVA CITY - A5
- Bhakti Greens
- S M TOWER
- VIMALNATH Building no-2
- UNIQUE APARTMENT
- VALENCIA CHS
- Belle Vue 9
- SUPER HOMEZ-HARMONY PHASE III
Other projects by EKTA PARKSVILLE HOMES PVT. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.