BROOKLYN PARK PHASE III
by EKTA PARKSVILLE HOMES PVT. LTD. · Linking Road, Palghar
Possession: BROOKLYN PARK PHASE III is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000000148. Status: Completed. 13 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BROOKLYN PARK PHASE III?
How the possession date of BROOKLYN PARK PHASE III has moved
28 February 2020
Completion date given when the project was registered
27 February 2021
Extended at the builder's request (MahaRERA application EXT99000005765)
Reason the builder gave MahaRERA: “due to scarcity of the resources & also some technical reasons.”
30 April 2023
Extended at the builder's request (MahaRERA application EXT99000012337)
Reason the builder gave MahaRERA: “we have almost completed the project but are pending for the environment Clearance Certificate, Once will get applied for the OC.”
27 July 2023
Extended at the builder's request (MahaRERA application EXT99000016883)
Reason the builder gave MahaRERA: “Reply attached herewith.”
Source: BROOKLYN PARK PHASE III’s extension records on MahaRERA (P99000000148), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BROOKLYN PARK PHASE III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 13 complaints and 3 court cases, and how it ended
- Construction pace against the July 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- BROOKLYN PARK PHASE IP99000000134
- BROOKLYN PARK PHASE IIP99000000110 · possession 30 Sep 2023
- BROOKLYN PARK PHASE IVP99000000417 · possession 31 Dec 2024
- MahaRERA registration
- P99000000148
- Status
- Completed
- Builder
- EKTA PARKSVILLE HOMES PVT. LTD.
- Location
- Linking Road, Palghar · 401303
- Project type
- Residential / Group Housing
- Registered on
- 5 Jul 2017
- Completion date at registration
- February 2020
- Latest completion date
- July 2023
- Delay so far
- 41 months
- Homes
- 195
- Towers
- 3
- Complaints on MahaRERA
- 13
- Court cases listed
- 3
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of BROOKLYN PARK PHASE III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SEC III BUILDING NO 9 WING A | 100% | 100% | 100% | 100% |
| SEC III BUILDING NO 9 WING B | 100% | 100% | 100% | 100% |
| SEC III BUILDING NO 9 WING C | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BROOKLYN PARK PHASE III every month.
BROOKLYN PARK PHASE III: buildings, flats and land, as filed on MahaRERA
- Buildings: SEC III BUILDING NO 9 WING A (14 floors) · SEC III BUILDING NO 9 WING B (14 floors) · SEC III BUILDING NO 9 WING C (14 floors)
- Land: 919 sq m (about 0.2 acres) · sanctioned built-up 7,982 sq m · recreational space 785 sq m
The builder’s record and reviews
Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 87 complaints on MahaRERA across 4 projects.
Read Google reviews of BROOKLYN PARK PHASE III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BROOKLYN PARK PHASE III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BROOKLYN PARK PHASE III
What is the possession date of BROOKLYN PARK PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BROOKLYN PARK PHASE III in Linking Road, Palghar is 27 July 2023 — 41 months later than 28 February 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for BROOKLYN PARK PHASE III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BROOKLYN PARK PHASE III's builder has filed on MahaRERA, the official one, is 27 July 2023, already 41 months later than the 28 February 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BROOKLYN PARK PHASE III extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III's builder applied to MahaRERA to extend the completion date 3 times: to 27 February 2021, giving the reason "due to scarcity of the resources & also some technical reasons."; to 30 April 2023, giving the reason "we have almost completed the project but are pending for the environment Clearance Certificate, Once will get applied for the OC."; to 27 July 2023, giving the reason "Reply attached herewith.".
What is the RERA number of BROOKLYN PARK PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BROOKLYN PARK PHASE III in Linking Road, Palghar is P99000000148.
Is BROOKLYN PARK PHASE III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III is registered as P99000000148 and its status is "Completed".
What is the construction status of BROOKLYN PARK PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does BROOKLYN PARK PHASE III have complaints on MahaRERA?
13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BROOKLYN PARK PHASE III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III is registered on MahaRERA as P99000000148, its MahaRERA status is "Completed", its completion date has moved 41 months since registration and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does BROOKLYN PARK PHASE III have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: BROOKLYN PARK PHASE I (P99000000134); BROOKLYN PARK PHASE II (P99000000110, possession 30 Sep 2023); BROOKLYN PARK PHASE IV (P99000000417, possession 31 Dec 2024). Check that your agreement names the registration of your own wing.
How can I get updates if BROOKLYN PARK PHASE III's possession date changes?
The latest dates are on BROOKLYN PARK PHASE III's MahaRERA page (P99000000148). GharKundli's Kundli Watch sends a free WhatsApp update on BROOKLYN PARK PHASE III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BROOKLYN PARK PHASE III have?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III has 3 buildings filed: SEC III BUILDING NO 9 WING A with 14 floors; SEC III BUILDING NO 9 WING B with 14 floors; SEC III BUILDING NO 9 WING C with 14 floors.
How big is the land of BROOKLYN PARK PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III stands on 919 sq m of land (about 0.2 acres), with 7,982 sq m of sanctioned built-up area and 785 sq m of recreational open space.
What is the track record of BROOKLYN PARK PHASE III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 87 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BROOKLYN PARK PHASE III?
Google Maps has reviews of BROOKLYN PARK PHASE III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BROOKLYN PARK PHASE III?
BROOKLYN PARK PHASE III by EKTA PARKSVILLE HOMES PVT. LTD. is in Linking Road, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000000148, per GharKundli's check of MahaRERA records.
How many homes are in BROOKLYN PARK PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III has 195 homes in 3 towers registered on MahaRERA.
When was BROOKLYN PARK PHASE III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BROOKLYN PARK PHASE III was registered on MahaRERA on 5 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on BROOKLYN PARK PHASE III?
3 court cases are listed for BROOKLYN PARK PHASE III on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of BROOKLYN PARK PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EKTA PARKSVILLE HOMES PVT. LTD., which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of BROOKLYN PARK PHASE III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vasai
- EKTA PARKSVILLE PHASE II
- BROOKLYN PARK PHASE II
- EKTA PARKSVILLE PHASE III
- STAR LEGACY
- VIMALNATH Building no-2
- Acciano Bianca
- REALTECH VALENCIA
- DHANANJAY ICON
Other projects by EKTA PARKSVILLE HOMES PVT. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.