EKTA PARKSVILLE PHASE II

by EKTA PARKSVILLE HOMES PVT. LTD. · Linking Road, Palghar

Possession date of EKTA PARKSVILLE PHASE II: 30 April 2027, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000000115, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 44 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about EKTA PARKSVILLE PHASE II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of EKTA PARKSVILLE PHASE II has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 29 June 2022

    Extended at the builder's request (MahaRERA application EXT99000006139)

    Reason the builder gave MahaRERA: “due to scarcity of availability of the resources and also some technical reasons.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT99000013283)

    Reason the builder gave MahaRERA:
    “We hereby apply for extension u/s 7(3) for the wings [ A to H ] of the registered project Ekta Parksville Phase III bearing MahaRERA registration No. P99000000115. Wings A,B, E TO H of the said project have already received OC on 15th May,…” Read the full reason“We hereby apply for extension u/s 7(3) for the wings [ A to H ] of the registered project Ekta Parksville Phase III bearing MahaRERA registration No. P99000000115. Wings A,B, E TO H of the said project have already received OC on 15th May, 2019. The structure of the Wings D is already completed and construction of the Wing C structure is ongoing. Further, Consent to Operate has been delayed for a long time for the entire larger HDIL Layout. Therefore, application for Occupation Certificate, will be applied shortly. Although, procurement of all the permissions including Consent to Operate in…”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA12092401795)

    Reason the builder gave MahaRERA: “Non compliance on the part of HDIL”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: EKTA PARKSVILLE PHASE II’s extension records on MahaRERA (P99000000115), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on EKTA PARKSVILLE PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 44 complaints and 4 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000000115
Status
Registered and active
Builder
EKTA PARKSVILLE HOMES PVT. LTD.
Location
Linking Road, Palghar · 401103
Project type
Residential / Group Housing
Registered on
4 Jul 2017
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
591
Towers
8
Complaints on MahaRERA
44
Court cases listed
4
Appeals at the tribunal
5
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of EKTA PARKSVILLE PHASE II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LINCOLN PARK A WING100%100%100%100%
LINCOLN PARK B WING100%100%100%100%
LINCOLN PARK C WING100%25%0%0%
LINCOLN PARK D WING100%100%100%90%
LINCOLN PARK E WING100%100%100%100%
LINCOLN PARK F WING100%100%100%100%
LINCOLN PARK G WING100%100%100%100%
LINCOLN PARK H WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on EKTA PARKSVILLE PHASE II every month.

EKTA PARKSVILLE PHASE II: buildings, flats and land, as filed on MahaRERA

  • Buildings: LINCOLN PARK A WING (17 floors) · LINCOLN PARK B WING (17 floors) · LINCOLN PARK C WING (17 floors) · LINCOLN PARK D WING (17 floors) · LINCOLN PARK E WING (17 floors) · LINCOLN PARK F WING (17 floors) · LINCOLN PARK G WING (17 floors) · LINCOLN PARK H WING (17 floors)
  • Land: 2,321 sq m (about 0.6 acres) · sanctioned built-up 23,198 sq m · recreational space 991 sq m

The builder’s record and reviews

Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 181 complaints on MahaRERA across 6 projects.

Read Google reviews of EKTA PARKSVILLE PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

EKTA PARKSVILLE PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about EKTA PARKSVILLE PHASE II

What is the possession date of EKTA PARKSVILLE PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EKTA PARKSVILLE PHASE II in Linking Road, Palghar is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for EKTA PARKSVILLE PHASE II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date EKTA PARKSVILLE PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of EKTA PARKSVILLE PHASE II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2022, giving the reason "due to scarcity of availability of the resources and also some technical reasons."; to 31 December 2024, giving the reason "We hereby apply for extension u/s 7(3) for the wings [ A to H ] of the registered project Ekta Parksville Phase III bearing MahaRERA registration No. P99000000115. Wings A,B, E TO H of the said project have already received OC on 15th May, 2019. The structure of the Wings D is already completed and construction of the Wing C structure is ongoing. Further, Consent to Operate has been delayed for a long time for the entire larger HDIL Layout. Therefore, application for Occupation Certificate, will be applied shortly. Although, procurement of all the permissions including Consent to Operate in…"; to 31 December 2026, giving the reason "Non compliance on the part of HDIL". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of EKTA PARKSVILLE PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EKTA PARKSVILLE PHASE II in Linking Road, Palghar is P99000000115.

Is EKTA PARKSVILLE PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II is registered as P99000000115 and its status is "Registered and active".

What is the construction status of EKTA PARKSVILLE PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 25% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does EKTA PARKSVILLE PHASE II have complaints on MahaRERA?

44 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is EKTA PARKSVILLE PHASE II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II is registered on MahaRERA as P99000000115, its completion date has moved 66 months since registration and 44 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if EKTA PARKSVILLE PHASE II's possession date changes?

The latest dates are on EKTA PARKSVILLE PHASE II's MahaRERA page (P99000000115). GharKundli's Kundli Watch sends a free WhatsApp update on EKTA PARKSVILLE PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does EKTA PARKSVILLE PHASE II have?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II has 8 buildings filed: LINCOLN PARK A WING with 17 floors; LINCOLN PARK B WING with 17 floors; LINCOLN PARK C WING with 17 floors; LINCOLN PARK D WING with 17 floors; LINCOLN PARK E WING with 17 floors; LINCOLN PARK F WING with 17 floors; and 2 more.

How big is the land of EKTA PARKSVILLE PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II stands on 2,321 sq m of land (about 0.6 acres), with 23,198 sq m of sanctioned built-up area and 991 sq m of recreational open space.

What is the track record of EKTA PARKSVILLE PHASE II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 181 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of EKTA PARKSVILLE PHASE II?

Google Maps has reviews of EKTA PARKSVILLE PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 44 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is EKTA PARKSVILLE PHASE II?

EKTA PARKSVILLE PHASE II by EKTA PARKSVILLE HOMES PVT. LTD. is in Linking Road, Palghar (pincode 401103), Maharashtra, and is registered on MahaRERA as P99000000115, per GharKundli's check of MahaRERA records.

How many homes are in EKTA PARKSVILLE PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II has 591 homes in 8 towers registered on MahaRERA.

When was EKTA PARKSVILLE PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA PARKSVILLE PHASE II was registered on MahaRERA on 4 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on EKTA PARKSVILLE PHASE II?

4 court cases are listed for EKTA PARKSVILLE PHASE II on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of EKTA PARKSVILLE PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EKTA PARKSVILLE HOMES PVT. LTD., which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Vasai

All 9 projects in Vangaon (401103) →

Other projects by EKTA PARKSVILLE HOMES PVT. LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.