Ekta Parksville Phase IV

by EKTA PARKSVILLE HOMES PVT. LTD. · Virar, Palghar

Possession date of Ekta Parksville Phase IV: 30 April 2029, moved from 30 June 2022 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000015239, and currently active. Its completion date has moved from June 2022 to April 2029: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Ekta Parksville Phase IV?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ekta Parksville Phase IV has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 29 June 2023

    Extended at the builder's request (MahaRERA application EXT99000005652)

    Reason the builder gave MahaRERA: “Due to scarcity of the resources & also some technical reasons.”
  3. 31 December 2028

    Extended at the builder's request (MahaRERA application EA12092401797)

    Reason the builder gave MahaRERA: “Delay in grant of CC by VVCMC and non compliance on part of HDIL”
  4. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ekta Parksville Phase IV’s extension records on MahaRERA (P99000015239), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ekta Parksville Phase IV

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000015239
Status
Registered and active
Builder
EKTA PARKSVILLE HOMES PVT. LTD.
Location
Virar, Palghar · 401303
Project type
Residential / Group Housing
Registered on
8 Feb 2018
Completion date at registration
June 2022
Latest completion date
April 2029
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
292
Sold or booked
17%
Towers
4
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Ekta Parksville Phase IV, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%0%0%0%
Wing B100%0%0%0%
Wing C100%0%0%0%
Wing D100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ekta Parksville Phase IV every month.

Ekta Parksville Phase IV: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (17 floors) · Wing B (17 floors) · Wing C (17 floors) · Wing D (17 floors)
  • Land: 1,283 sq m (about 0.3 acres) · sanctioned built-up 13,131 sq m

The builder’s record and reviews

Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 181 complaints on MahaRERA across 6 projects.

Read Google reviews of Ekta Parksville Phase IV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ekta Parksville Phase IV: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ekta Parksville Phase IV

What is the possession date of Ekta Parksville Phase IV?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ekta Parksville Phase IV in Virar, Palghar is 30 April 2029 — 78 months later than 30 June 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ekta Parksville Phase IV?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ekta Parksville Phase IV's builder has filed on MahaRERA, the official one, is 30 April 2029, already 78 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ekta Parksville Phase IV extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2023, giving the reason "Due to scarcity of the resources & also some technical reasons."; to 31 December 2028, giving the reason "Delay in grant of CC by VVCMC and non compliance on part of HDIL". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ekta Parksville Phase IV?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ekta Parksville Phase IV in Virar, Palghar is P99000015239.

Is Ekta Parksville Phase IV registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV is registered as P99000015239 and its status is "Registered and active".

What is the construction status of Ekta Parksville Phase IV?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Ekta Parksville Phase IV have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Ekta Parksville Phase IV safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV is registered on MahaRERA as P99000015239, its completion date has moved 78 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Ekta Parksville Phase IV have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: EKTA PARKSVILLE PHASE I (P99000000116, possession 27 Jul 2023); EKTA PARKSVILLE PHASE III (P99000000109, possession 30 Dec 2023). Check that your agreement names the registration of your own wing.

How can I get updates if Ekta Parksville Phase IV's possession date changes?

The latest dates are on Ekta Parksville Phase IV's MahaRERA page (P99000015239). GharKundli's Kundli Watch sends a free WhatsApp update on Ekta Parksville Phase IV every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ekta Parksville Phase IV have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV has 4 buildings filed: Wing A with 17 floors; Wing B with 17 floors; Wing C with 17 floors; Wing D with 17 floors.

How big is the land of Ekta Parksville Phase IV?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV stands on 1,283 sq m of land (about 0.3 acres), with 13,131 sq m of sanctioned built-up area.

What is the track record of Ekta Parksville Phase IV's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Homes has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 41 months); 2 still being built, 2 past the promised date (typically 42 months late). 181 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ekta Parksville Phase IV?

Google Maps has reviews of Ekta Parksville Phase IV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ekta Parksville Phase IV?

Ekta Parksville Phase IV by EKTA PARKSVILLE HOMES PVT. LTD. is in Virar, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000015239, per GharKundli's check of MahaRERA records.

How many homes are in Ekta Parksville Phase IV?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV has 292 homes in 4 towers registered on MahaRERA, and 17% of them are sold or booked.

When was Ekta Parksville Phase IV registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Parksville Phase IV was registered on MahaRERA on 8 February 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Ekta Parksville Phase IV?

No court cases are listed for Ekta Parksville Phase IV on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Ekta Parksville Phase IV?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EKTA PARKSVILLE HOMES PVT. LTD., which has 6 other projects registered on MahaRERA.

All projects with possession due in 2029 in Palghar →

Other projects in pincode 401303

All 210 projects in Virar West (401303) →

Other projects by EKTA PARKSVILLE HOMES PVT. LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.