ADIRAJ BLISS
by S K DEVELOPERS · Bhugaon, Pune
Possession: ADIRAJ BLISS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100015487. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ADIRAJ BLISS?
How the possession date of ADIRAJ BLISS has moved
30 March 2022
Completion date given when the project was registered
29 March 2023
Extended at the builder's request (MahaRERA application EXT52100012230)
Reason the builder gave MahaRERA: “DUE TO COVID-19 WORK IS DELAYED .....NEED SOME TIME TO COMPLETE THE REMAINING WORK ..........”
Source: ADIRAJ BLISS’s extension records on MahaRERA (P52100015487), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ADIRAJ BLISS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100015487
- Status
- Completed
- Builder
- S K DEVELOPERS
- Location
- Bhugaon, Pune · 412115
- Project type
- Residential / Group Housing
- Registered on
- 1 Mar 2018
- Completion date at registration
- March 2022
- Latest completion date
- March 2023
- Delay so far
- 12 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 20
Construction progress of ADIRAJ BLISS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ADIRAJ BLISS | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ADIRAJ BLISS every month.
ADIRAJ BLISS: buildings, flats and land, as filed on MahaRERA
- Buildings: ADIRAJ BLISS (6 floors)
- Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 870 sq m · recreational space 250 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ADIRAJ BLISS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ADIRAJ BLISS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ADIRAJ BLISS
What is the possession date of ADIRAJ BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ADIRAJ BLISS in Bhugaon, Pune is 29 March 2023 — 12 months later than 30 March 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ADIRAJ BLISS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ADIRAJ BLISS's builder has filed on MahaRERA, the official one, is 29 March 2023, already 12 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ADIRAJ BLISS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS's builder applied to MahaRERA to extend the completion date once: to 29 March 2023, giving the reason "DUE TO COVID-19 WORK IS DELAYED .....NEED SOME TIME TO COMPLETE THE REMAINING WORK ..........".
What is the RERA number of ADIRAJ BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ADIRAJ BLISS in Bhugaon, Pune is P52100015487.
Is ADIRAJ BLISS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS is registered as P52100015487 and its status is "Completed".
What is the construction status of ADIRAJ BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS's status on MahaRERA is "Completed". As filed by the builder, slab work on ADIRAJ BLISS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ADIRAJ BLISS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ADIRAJ BLISS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS is registered on MahaRERA as P52100015487, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ADIRAJ BLISS's possession date changes?
The latest dates are on ADIRAJ BLISS's MahaRERA page (P52100015487). GharKundli's Kundli Watch sends a free WhatsApp update on ADIRAJ BLISS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ADIRAJ BLISS have?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS has one building filed: ADIRAJ BLISS with 6 floors.
How big is the land of ADIRAJ BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS stands on 1,000 sq m of land (about 0.2 acres), with 870 sq m of sanctioned built-up area and 250 sq m of recreational open space.
Where can I read reviews of ADIRAJ BLISS?
Google Maps has reviews of ADIRAJ BLISS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ADIRAJ BLISS?
ADIRAJ BLISS by S K DEVELOPERS is in Bhugaon, Pune (pincode 412115), Maharashtra, and is registered on MahaRERA as P52100015487, per GharKundli's check of MahaRERA records.
How many homes are in ADIRAJ BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS has 24 homes in 1 tower registered on MahaRERA.
When was ADIRAJ BLISS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ADIRAJ BLISS was registered on MahaRERA on 1 March 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on ADIRAJ BLISS?
No court cases are listed for ADIRAJ BLISS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ADIRAJ BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S K DEVELOPERS, which has 20 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ADIRAJ BLISS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 412115
- The Green Hill
- NAKSHATRA ANGAN C BUILDING
- Mahindra Rivenza Phase 2
- Mahindra Rivenza Phase 1
- LOTUS CREST
- THE WINDS PHASE-1, SECTOR 1B AT AVIAN VALLEY
- NANDANVAN PARK
- Pre Eminence
Other projects by S K DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.