Skip to content
GharKundli

Paranjape Azure Aster G and H

by PARANJAPE SCHEMES (CONSTRUCTION) LTD · Tathawade, Pune 411033Also near ChinchwadgaonRegistered on MahaRERA as “Azure Aster G and H”

What’s in the report? →

Possession date of Paranjape Azure Aster G and H (MahaRERA P52100024186): 28 June 2026, and it has already passed. It has 178 homes, 1% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100024186. Status: Lapsed (registration period ended). Its completion date is now June 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P52100024186, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Paranjape Azure Aster G and H?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Paranjape Azure Aster G and H has moved

  1. 28 February 2026

    Completion date given when the project was registered

  2. 28 June 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Paranjape Azure Aster G and H’s extension records on MahaRERA (P52100024186), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Paranjape Azure Aster G and H

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100024186
Status
Lapsed (registration period ended)
Builder
PARANJAPE SCHEMES (CONSTRUCTION) LTD
Location
Tathawade, Pune · 411033
Project type
Residential / Group Housing
Registered on
24 Jan 2020
Completion date at registration
February 2026
Latest completion date
June 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
178
Sold or booked
1%
Towers
2
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
25

Construction progress of Paranjape Azure Aster G and H, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Azure Aster G0%0%0%0%
Azure Aster H0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Azure Aster G: covers 15 floors
  • Azure Aster H: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Paranjape Azure Aster G and H every 1–2 months.

Paranjape Azure Aster G and H: buildings, flats and land, as filed on MahaRERA

  • Buildings: Azure Aster G (15 floors, 89 units) · Azure Aster H (15 floors, 89 units)
  • Land: 7,621 sq m (about 1.9 acres) · sanctioned built-up 557 sq m · recreational space 2,268 sq m
  • Land, as filed: 84/1B, 84/2B, 84/3B Part 84/4 Part
  • Map: Get directions

The builder’s record and reviews

Paranjape Schemes Construction (a group of 3 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 33 GharKundli has checked: 18 finished, 10 within the promised date and 8 needed more time (typically 24 months); 10 still being built, 5 past the promised date (typically 6 months late); 5 lapsed. 92 complaints on MahaRERA across 14 projects.

Read Google reviews of Paranjape Azure Aster G and H →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Paranjape Azure Aster G and H: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Paranjape Azure Aster G and H

What is the possession date of Paranjape Azure Aster G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Paranjape Azure Aster G and H in Tathawade, Pune is 28 June 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Paranjape Azure Aster G and H?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Paranjape Azure Aster G and H's builder has filed on MahaRERA, the official one, is 28 June 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Paranjape Azure Aster G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Paranjape Azure Aster G and H in Tathawade, Pune is P52100024186.

Is Paranjape Azure Aster G and H registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H is registered as P52100024186 and its status is "Lapsed (registration period ended)".

What is the current construction status of Paranjape Azure Aster G and H? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Paranjape Azure Aster G and H have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Paranjape Azure Aster G and H safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H is registered on MahaRERA as P52100024186, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Paranjape Azure Aster G and H?

Paranjape Azure Aster G and H isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Paranjape Azure Aster G and H?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Paranjape Azure Aster G and H: gharkundli.com/tools/property-cost-calculator

Has Paranjape Azure Aster G and H received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 28 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Paranjape Azure Aster G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (28 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Paranjape Azure Aster G and H uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Paranjape Azure Aster G and H was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Paranjape Azure Aster G and H's possession date changes?

The latest dates are on Paranjape Azure Aster G and H's MahaRERA page (P52100024186). GharKundli's Kundli Watch sends a free WhatsApp update on Paranjape Azure Aster G and H every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Paranjape Azure Aster G and H have?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H has 2 buildings filed: Azure Aster G with 15 floors and 89 units; Azure Aster H with 15 floors and 89 units.

How big is the land of Paranjape Azure Aster G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H stands on 7,621 sq m of land (about 1.9 acres), with 557 sq m of sanctioned built-up area and 2,268 sq m of recreational open space.

What is the track record of Paranjape Azure Aster G and H's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Schemes Construction (a group of 3 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 33 GharKundli has checked: 18 finished, 10 within the promised date and 8 needed more time (typically 24 months); 10 still being built, 5 past the promised date (typically 6 months late); 5 lapsed. 92 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Paranjape Azure Aster G and H?

Google Maps has reviews of Paranjape Azure Aster G and H written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Paranjape Azure Aster G and H?

Paranjape Azure Aster G and H by PARANJAPE SCHEMES (CONSTRUCTION) LTD is in Tathawade, Pune, pincode 411033 (near Chinchwadgaon), Maharashtra, and is registered on MahaRERA as P52100024186, per GharKundli's check of MahaRERA records. Its land is filed as 84/1B, 84/2B, 84/3B Part 84/4 Part. GharKundli lists all 613 MahaRERA projects in Chinchwadgaon (411033).

How many flats are in Paranjape Azure Aster G and H, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H has 178 homes in 2 towers registered on MahaRERA, and 1% of them are sold or booked.

When was Paranjape Azure Aster G and H registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Azure Aster G and H was registered on MahaRERA on 24 January 2020. GharKundli did not find a title report on the land on file there.

Does Paranjape Azure Aster G and H have any legal issues or court cases?

2 court cases are listed for Paranjape Azure Aster G and H on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Paranjape Azure Aster G and H?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARANJAPE SCHEMES (CONSTRUCTION) LTD, which has 25 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Chinchwadgaon (411033)

All 613 projects in Chinchwadgaon (411033) →

Other projects by PARANJAPE SCHEMES (CONSTRUCTION) LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.