Skip to content
GharKundli

ZEAL REGENCY

by BLUE BARON REALTORS · Vasai, Palghar

Possession: ZEAL REGENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000003182. Status: Completed. 10 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ZEAL REGENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ZEAL REGENCY has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 December 2019

    Extended at the builder's request (MahaRERA application EXT99000001264)

    Reason the builder gave MahaRERA: “HAVE ATTACHED APPLICATION HEREWITH....”
  3. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT99000009403)

    Reason the builder gave MahaRERA: “The delay is on account of pending approval of Fire NOC, Water supply from corporation and Electricity meters from MSEB.”
  4. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT99000011669)

    Reason the builder gave MahaRERA: “The delay is on account of pending approval of Fire NOC, Water supply from corporation and Electricity meters from MSEB.”
  5. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT99000015065)

    Reason the builder gave MahaRERA: “They delay is on account of Non issuance of OC”

Source: ZEAL REGENCY’s extension records on MahaRERA (P99000003182), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ZEAL REGENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 10 complaints, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000003182
Status
Completed
Builder
BLUE BARON REALTORS
Location
Vasai, Palghar · 401303
Project type
Others
Registered on
4 Aug 2017
Completion date at registration
December 2018
Latest completion date
March 2024
Delay so far
63 months
Homes
215
Towers
1
Complaints on MahaRERA
10
Court cases listed
0
Title report on file
Not found

Construction progress of ZEAL REGENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ZEAL REGENCY100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ZEAL REGENCY every month.

ZEAL REGENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: ZEAL REGENCY (17 floors)
  • Land: 2,158 sq m (about 0.5 acres) · sanctioned built-up 12,994 sq m · recreational space 1,154 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ZEAL REGENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ZEAL REGENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ZEAL REGENCY

What is the possession date of ZEAL REGENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ZEAL REGENCY in Vasai, Palghar is 31 March 2024 — 63 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ZEAL REGENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ZEAL REGENCY's builder has filed on MahaRERA, the official one, is 31 March 2024, already 63 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ZEAL REGENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2019, giving the reason "HAVE ATTACHED APPLICATION HEREWITH...."; to 30 September 2021, giving the reason "The delay is on account of pending approval of Fire NOC, Water supply from corporation and Electricity meters from MSEB."; to 31 March 2023, giving the reason "The delay is on account of pending approval of Fire NOC, Water supply from corporation and Electricity meters from MSEB."; to 31 March 2024, giving the reason "They delay is on account of Non issuance of OC".

What is the RERA number of ZEAL REGENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ZEAL REGENCY in Vasai, Palghar is P99000003182.

Is ZEAL REGENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY is registered as P99000003182 and its status is "Completed".

What is the construction status of ZEAL REGENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on ZEAL REGENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does ZEAL REGENCY have complaints on MahaRERA?

10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ZEAL REGENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY is registered on MahaRERA as P99000003182, its MahaRERA status is "Completed", its completion date has moved 63 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ZEAL REGENCY's possession date changes?

The latest dates are on ZEAL REGENCY's MahaRERA page (P99000003182). GharKundli's Kundli Watch sends a free WhatsApp update on ZEAL REGENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ZEAL REGENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY has one building filed: ZEAL REGENCY with 17 floors.

How big is the land of ZEAL REGENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY stands on 2,158 sq m of land (about 0.5 acres), with 12,994 sq m of sanctioned built-up area and 1,154 sq m of recreational open space.

Where can I read reviews of ZEAL REGENCY?

Google Maps has reviews of ZEAL REGENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ZEAL REGENCY?

ZEAL REGENCY by BLUE BARON REALTORS is in Vasai, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000003182, per GharKundli's check of MahaRERA records.

How many homes are in ZEAL REGENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY has 215 homes in 1 tower registered on MahaRERA.

When was ZEAL REGENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ZEAL REGENCY was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ZEAL REGENCY?

No court cases are listed for ZEAL REGENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ZEAL REGENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BLUE BARON REALTORS.

Other projects in Vasai

All 187 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.