Skip to content
GharKundli

The Sacred Basil Phase III

by Ashapuri Kapase Ventures · Pirangut, Pune

Possession: The Sacred Basil Phase III is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100021606. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about The Sacred Basil Phase III?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of The Sacred Basil Phase III has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52100012338)

    Reason the builder gave MahaRERA: “Occupancy certificate not received”

Source: The Sacred Basil Phase III’s extension records on MahaRERA (P52100021606), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Sacred Basil Phase III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100021606
Status
Completed
Builder
Ashapuri Kapase Ventures
Location
Pirangut, Pune · 412115
Project type
Residential / Group Housing
Registered on
15 Jul 2019
Completion date at registration
June 2022
Latest completion date
December 2022
Delay so far
6 months
Homes
48
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of The Sacred Basil Phase III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
D wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Sacred Basil Phase III every month.

The Sacred Basil Phase III: buildings, flats and land, as filed on MahaRERA

  • Buildings: D wing (7 floors)
  • Land: 800 sq m (about 0.2 acres) · sanctioned built-up 1,770 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of The Sacred Basil Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Sacred Basil Phase III: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about The Sacred Basil Phase III

What is the possession date of The Sacred Basil Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Sacred Basil Phase III in Pirangut, Pune is 31 December 2022 — 6 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for The Sacred Basil Phase III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Sacred Basil Phase III's builder has filed on MahaRERA, the official one, is 31 December 2022, already 6 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Sacred Basil Phase III extended?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "Occupancy certificate not received".

What is the RERA number of The Sacred Basil Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Sacred Basil Phase III in Pirangut, Pune is P52100021606.

Is The Sacred Basil Phase III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III is registered as P52100021606 and its status is "Completed".

What is the construction status of The Sacred Basil Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III's status on MahaRERA is "Completed". As filed by the builder, slab work on D wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does The Sacred Basil Phase III have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is The Sacred Basil Phase III safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III is registered on MahaRERA as P52100021606, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does The Sacred Basil Phase III have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: The Sacred Basil Phase II (P52100001486). Check that your agreement names the registration of your own wing.

How can I get updates if The Sacred Basil Phase III's possession date changes?

The latest dates are on The Sacred Basil Phase III's MahaRERA page (P52100021606). GharKundli's Kundli Watch sends a free WhatsApp update on The Sacred Basil Phase III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Sacred Basil Phase III have?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III has one building filed: D wing with 7 floors.

How big is the land of The Sacred Basil Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III stands on 800 sq m of land (about 0.2 acres), with 1,770 sq m of sanctioned built-up area.

Where can I read reviews of The Sacred Basil Phase III?

Google Maps has reviews of The Sacred Basil Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is The Sacred Basil Phase III?

The Sacred Basil Phase III by Ashapuri Kapase Ventures is in Pirangut, Pune (pincode 412115), Maharashtra, and is registered on MahaRERA as P52100021606, per GharKundli's check of MahaRERA records.

How many homes are in The Sacred Basil Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III has 48 homes in 1 tower registered on MahaRERA.

When was The Sacred Basil Phase III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Sacred Basil Phase III was registered on MahaRERA on 15 July 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on The Sacred Basil Phase III?

No court cases are listed for The Sacred Basil Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of The Sacred Basil Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ashapuri Kapase Ventures.

Other projects in pincode 412115

All 198 projects in Bhugaon (412115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.