OM SATYAM NIWAS CHS LTD
by Greenfield Developers & Realtors LLP · borivali, MumbaiAlso near Shimpoli, Kandivali West, Magathane
Possession date of OM SATYAM NIWAS CHS LTD: 31 July 2022, moved from 31 July 2020 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800002293. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (July 2022) has passed.
What do you want to know about OM SATYAM NIWAS CHS LTD?
How the possession date of OM SATYAM NIWAS CHS LTD has moved
31 July 2020
Completion date given when the project was registered
31 July 2021
Extended at the builder's request (MahaRERA application EXT51800003680)
Reason the builder gave MahaRERA:
“The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they had delayed the implementation date to 1st September, 2018 as stated in Corrigendum to Notice No. TPB-4317/…” Read the full reason
“The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they had delayed the implementation date to 1st September, 2018 as stated in Corrigendum to Notice No. TPB-4317/629/CR-118/2017/EP/UD-11, dt. 22/06/2018.The said DCPR-2034 was implemented on 01/09/2018 without EP’s (Excluded Part) only on 13/11/2018 was the DCPR fully implemented including all EP’s The Regulations 33(7) B allows for incentive FSI in lieu of TDR Use.The same Which is now Clarified vide transition policy No.4 of MCGM dated 9/7/2019.This delay in impl…”31 July 2022
Revised completion date on MahaRERA
Source: OM SATYAM NIWAS CHS LTD’s extension records on MahaRERA (P51800002293), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OM SATYAM NIWAS CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002293
- Status
- Lapsed (registration period ended)
- Builder
- Greenfield Developers & Realtors LLP
- Location
- borivali, Mumbai · 400092
- Project type
- Others
- Registered on
- 31 Jul 2017
- Completion date at registration
- July 2020
- Latest completion date
- July 2022
- Delay so far
- 24 months
- Homes
- 66
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of OM SATYAM NIWAS CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM SATYAM NIWAS CHS LTD | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OM SATYAM NIWAS CHS LTD every month.
OM SATYAM NIWAS CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: OM SATYAM NIWAS CHS LTD (18 floors)
- Land: 1,662 sq m (about 0.4 acres) · sanctioned built-up 4,405 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of OM SATYAM NIWAS CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OM SATYAM NIWAS CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OM SATYAM NIWAS CHS LTD
What is the possession date of OM SATYAM NIWAS CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OM SATYAM NIWAS CHS LTD in borivali, Mumbai is 31 July 2022 — 24 months later than 31 July 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for OM SATYAM NIWAS CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OM SATYAM NIWAS CHS LTD's builder has filed on MahaRERA, the official one, is 31 July 2022, already 24 months later than the 31 July 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OM SATYAM NIWAS CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD's builder applied to MahaRERA to extend the completion date once: to 31 July 2021, giving the reason "The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they had delayed the implementation date to 1st September, 2018 as stated in Corrigendum to Notice No. TPB-4317/629/CR-118/2017/EP/UD-11, dt. 22/06/2018.The said DCPR-2034 was implemented on 01/09/2018 without EP’s (Excluded Part) only on 13/11/2018 was the DCPR fully implemented including all EP’s The Regulations 33(7) B allows for incentive FSI in lieu of TDR Use.The same Which is now Clarified vide transition policy No.4 of MCGM dated 9/7/2019.This delay in impl…".
What is the RERA number of OM SATYAM NIWAS CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OM SATYAM NIWAS CHS LTD in borivali, Mumbai is P51800002293.
Is OM SATYAM NIWAS CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD is registered as P51800002293 and its status is "Lapsed (registration period ended)".
What is the construction status of OM SATYAM NIWAS CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on OM SATYAM NIWAS CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does OM SATYAM NIWAS CHS LTD have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is OM SATYAM NIWAS CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD is registered on MahaRERA as P51800002293, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if OM SATYAM NIWAS CHS LTD's possession date changes?
The latest dates are on OM SATYAM NIWAS CHS LTD's MahaRERA page (P51800002293). GharKundli's Kundli Watch sends a free WhatsApp update on OM SATYAM NIWAS CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OM SATYAM NIWAS CHS LTD have?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD has one building filed: OM SATYAM NIWAS CHS LTD with 18 floors.
How big is the land of OM SATYAM NIWAS CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD stands on 1,662 sq m of land (about 0.4 acres), with 4,405 sq m of sanctioned built-up area.
Where can I read reviews of OM SATYAM NIWAS CHS LTD?
Google Maps has reviews of OM SATYAM NIWAS CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OM SATYAM NIWAS CHS LTD?
OM SATYAM NIWAS CHS LTD by Greenfield Developers & Realtors LLP is in borivali, Mumbai (pincode 400092), near Shimpoli, Kandivali West, Magathane, Maharashtra, and is registered on MahaRERA as P51800002293, per GharKundli's check of MahaRERA records.
How many homes are in OM SATYAM NIWAS CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD has 66 homes in 1 tower registered on MahaRERA.
When was OM SATYAM NIWAS CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SATYAM NIWAS CHS LTD was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OM SATYAM NIWAS CHS LTD?
No court cases are listed for OM SATYAM NIWAS CHS LTD on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of OM SATYAM NIWAS CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Greenfield Developers & Realtors LLP.
Check it yourself on MahaRERA
- How to check the possession date of OM SATYAM NIWAS CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400092
- FORTUNE AVIRAHI WING A
- SONI ARCADE, BUILDING NO 2
- Sparkle Umadarshan
- SHRADDHA SKYLINE
- I SPACE URBAN VISTA
- GAURAV GALAXY
- SKYLARK HEIGHTS
- Hiranandani Bluecrest
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.