addressOne - Phase 6
by Peninsula Land Limited · Near MCA Stadium Gahunje, Pune 412101Also near Mamurdi, Fort, Near Address One
What’s in the report? →Possession date of addressOne - Phase 6 (MahaRERA P52100018788): 30 June 2026, moved from 30 June 2024 (24 months later), and it has already passed. It has 200 homes, 100% sold or booked. 34 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100018788. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100018788, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about addressOne - Phase 6?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of addressOne - Phase 6 has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT52100024078)
Reason the builder gave MahaRERA:
“a) The said Project is a part of the larger layout/phase-wise development having phases 1-6. The original amended Environmental Clearance for larger layout including the Phase 6 was obtained on 10/01/2019. However, due to the impact of the…” Read the full reason
“a) The said Project is a part of the larger layout/phase-wise development having phases 1-6. The original amended Environmental Clearance for larger layout including the Phase 6 was obtained on 10/01/2019. However, due to the impact of the COVID-19 pandemic, subsequent permissions for all the phases were significantly delayed. As a result, the revalidation of consent to operate permission could only be obtained in May 2022 for phase 1 to 4. Therefore, the consent to operate for the remaining phases i.e. Phase 5 and phase 6 experienced a delay. b) The Vendor- M/s Tricon Infra Buidtech Pvt. L…”30 June 2026
Extended at the builder's request (MahaRERA application EA10112518294)
Reason the builder gave MahaRERA:
“In Project Certificate No. P52100018788 and Extension Application No. EA10112518294 , application is filed under Section 7(3) of the MahaRERA Act, read with Order No. 40 of 2022. Please find attached herewith the Order passed by the Hon. Ch…” Read the full reason
“In Project Certificate No. P52100018788 and Extension Application No. EA10112518294 , application is filed under Section 7(3) of the MahaRERA Act, read with Order No. 40 of 2022. Please find attached herewith the Order passed by the Hon. Chairperson, MahaRERA, granting extension from 01.07.2025 to 30.06.2026, vide Order Regulatory Case No. 432 of 2025, in respect of addressOne Phase 6. The same is enclosed at Sr. No. 10 for your reference. we have uploaded the QPR upto December 2025 in the system.”
Source: addressOne - Phase 6’s extension records on MahaRERA (P52100018788), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on addressOne - Phase 6
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 34 complaints, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- addressOne - Phase 1P52100015756 · possession 30 Dec 2022
- addressOne - Phase 2P52100015747 · possession 30 Apr 2023
- addressOne - Phase 3P52100015779 · possession 30 May 2023
- addressOne - Phase 4P52100015803 · possession 28 Aug 2023
- addressOne - Phase 5P52100018855 · possession 29 Dec 2024
- MahaRERA registration
- P52100018788
- Status
- Lapsed (registration period ended)
- Builder
- Peninsula Land Limited
- Location
- Near MCA Stadium Gahunje, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 5 Dec 2018
- Completion date at registration
- June 2024
- Latest completion date
- June 2026
- Delay so far
- 24 months
- Homes
- 200
- Sold or booked
- 100%
- Towers
- 10
- Complaints on MahaRERA
- 34
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 16
Construction progress of addressOne - Phase 6, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building 66 | 100% | 100% | 100% | 100% |
| Building 67 | 100% | 100% | 100% | 100% |
| Building 68 | 100% | 100% | 100% | 100% |
| Building 69 | 100% | 100% | 100% | 100% |
| Building 70 | 100% | 100% | 100% | 100% |
| Building 71 | 100% | 100% | 100% | 100% |
| Building 72 | 100% | 100% | 100% | 100% |
| Building 73 | 100% | 100% | 100% | 100% |
| Building 77 | 100% | 100% | 100% | 100% |
| Building 78 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Building 66: covers 5 floors
- Building 67: covers 5 floors
- Building 68: covers 5 floors
- Building 69: covers 5 floors
- Building 70: covers 5 floors
- Building 71: covers 5 floors
- Building 72: covers 5 floors
- Building 73: covers 5 floors
- Building 77: covers 5 floors
- Building 78: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on addressOne - Phase 6 every 1–2 months.
addressOne - Phase 6: buildings, flats and land, as filed on MahaRERA
- Buildings: Building 66 (5 floors, 20 units) · Building 67 (5 floors, 20 units) · Building 68 (5 floors, 20 units) · Building 69 (5 floors, 20 units) · Building 70 (5 floors, 20 units) · Building 71 (5 floors, 20 units) · Building 72 (5 floors, 20 units) · Building 73 (5 floors, 20 units) · and 2 more
- Car parking: 86 open
- Land: 3,812 sq m (about 0.9 acres) · sanctioned built-up 8,052 sq m
- Land, as filed: Being portion of approved layout of Gat nos 195 222 223 and 224 of Village Gahunje Taluka Maval Pune
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Peninsula Land (a group of 3 linked companies) has 20 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 10 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 3 months late); 2 lapsed. 94 complaints on MahaRERA across 9 projects.
Read Google reviews of addressOne - Phase 6 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
addressOne - Phase 6: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about addressOne - Phase 6
What is the possession date of addressOne - Phase 6?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for addressOne - Phase 6 in Near MCA Stadium Gahunje, Pune is 30 June 2026 — 24 months later than 30 June 2024, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for addressOne - Phase 6?
Builders and listing sites often quote an earlier "target" date for handover. The completion date addressOne - Phase 6's builder has filed on MahaRERA, the official one, is 30 June 2026, already 24 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of addressOne - Phase 6 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "a) The said Project is a part of the larger layout/phase-wise development having phases 1-6. The original amended Environmental Clearance for larger layout including the Phase 6 was obtained on 10/01/2019. However, due to the impact of the COVID-19 pandemic, subsequent permissions for all the phases were significantly delayed. As a result, the revalidation of consent to operate permission could only be obtained in May 2022 for phase 1 to 4. Therefore, the consent to operate for the remaining phases i.e. Phase 5 and phase 6 experienced a delay. b) The Vendor- M/s Tricon Infra Buidtech Pvt. L…"; to 30 June 2026, giving the reason "In Project Certificate No. P52100018788 and Extension Application No. EA10112518294 , application is filed under Section 7(3) of the MahaRERA Act, read with Order No. 40 of 2022. Please find attached herewith the Order passed by the Hon. Chairperson, MahaRERA, granting extension from 01.07.2025 to 30.06.2026, vide Order Regulatory Case No. 432 of 2025, in respect of addressOne Phase 6. The same is enclosed at Sr. No. 10 for your reference. we have uploaded the QPR upto December 2025 in the system.".
What is the RERA number of addressOne - Phase 6?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of addressOne - Phase 6 in Near MCA Stadium Gahunje, Pune is P52100018788.
Is addressOne - Phase 6 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 is registered as P52100018788 and its status is "Lapsed (registration period ended)".
What is the current construction status of addressOne - Phase 6? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 10 towers. GharKundli's full report compares construction progress with the deadline.
Does addressOne - Phase 6 have complaints on MahaRERA?
34 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
34 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is addressOne - Phase 6 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 is registered on MahaRERA as P52100018788, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 34 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in addressOne - Phase 6?
addressOne - Phase 6 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in addressOne - Phase 6?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in addressOne - Phase 6: gharkundli.com/tools/property-cost-calculator
Has addressOne - Phase 6 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for addressOne - Phase 6?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has addressOne - Phase 6 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for addressOne - Phase 6 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does addressOne - Phase 6 have other wings or phases?
Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: addressOne - Phase 1 (P52100015756, possession 30 Dec 2022); addressOne - Phase 2 (P52100015747, possession 30 Apr 2023); addressOne - Phase 3 (P52100015779, possession 30 May 2023); addressOne - Phase 4 (P52100015803, possession 28 Aug 2023); addressOne - Phase 5 (P52100018855, possession 29 Dec 2024). Check that your agreement names the registration of your own wing.
How can I get updates if addressOne - Phase 6's possession date changes?
The latest dates are on addressOne - Phase 6's MahaRERA page (P52100018788). GharKundli's Kundli Watch sends a free WhatsApp update on addressOne - Phase 6 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does addressOne - Phase 6 have?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 has 10 buildings filed: Building 66 with 5 floors and 20 units; Building 67 with 5 floors and 20 units; Building 68 with 5 floors and 20 units; Building 69 with 5 floors and 20 units; Building 70 with 5 floors and 20 units; Building 71 with 5 floors and 20 units; and 4 more.
How much parking does addressOne - Phase 6 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 86 open car parking spaces for addressOne - Phase 6.
How big is the land of addressOne - Phase 6?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 stands on 3,812 sq m of land (about 0.9 acres), with 8,052 sq m of sanctioned built-up area.
What is the track record of addressOne - Phase 6's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Peninsula Land (a group of 3 linked companies) has 20 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 10 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 3 months late); 2 lapsed. 94 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of addressOne - Phase 6?
Google Maps has reviews of addressOne - Phase 6 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 34 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of addressOne - Phase 6?
addressOne - Phase 6 by Peninsula Land Limited is in Near MCA Stadium Gahunje, Pune, pincode 412101 (near Mamurdi, Fort, Near Address One), Maharashtra, and is registered on MahaRERA as P52100018788, per GharKundli's check of MahaRERA records. Its land is filed as Being portion of approved layout of Gat nos 195 222 223 and 224 of Village Gahunje Taluka Maval Pune. GharKundli lists all 606 MahaRERA projects in Ravet (412101).
How many flats are in addressOne - Phase 6, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 has 200 homes in 10 towers registered on MahaRERA, and 100% of them are sold or booked.
When was addressOne - Phase 6 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), addressOne - Phase 6 was registered on MahaRERA on 5 December 2018. GharKundli did not find a title report on the land on file there.
Does addressOne - Phase 6 have any legal issues or court cases?
No court cases are listed for addressOne - Phase 6 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of addressOne - Phase 6?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Peninsula Land Limited, which has 16 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of addressOne - Phase 6
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in Mawal
- addressOne - Phase 5
- Paloma Azure
- Kakade Swapanashilp
- Nakshatraban
- Mann Natura
- Shree Ramkunj
- Abhimaan Homes Phase 3
- Om Capital.
Other projects by Peninsula Land Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.