Siddhivinayak Angan
by Siddhivinayak Developers · Yavat, Pune
Possession date of Siddhivinayak Angan: 31 July 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100046054. Status: Lapsed (registration period ended). Its completion date is now July 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Siddhivinayak Angan?
How the possession date of Siddhivinayak Angan has moved
31 March 2026
Completion date given when the project was registered
31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Siddhivinayak Angan’s extension records on MahaRERA (P52100046054), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Siddhivinayak Angan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100046054
- Status
- Lapsed (registration period ended)
- Builder
- Siddhivinayak Developers
- Location
- Yavat, Pune · 412214
- Project type
- Residential / Group Housing
- Registered on
- 15 Jun 2022
- Completion date at registration
- March 2026
- Latest completion date
- July 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 36
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 46
Construction progress of Siddhivinayak Angan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Siddhivinayak Angan Wing A | 100% | 100% | 0% | 0% |
| Siddhivinayak Angan Wing B | 100% | 100% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Siddhivinayak Angan every month.
Siddhivinayak Angan: buildings, flats and land, as filed on MahaRERA
- Buildings: Siddhivinayak Angan Wing A (5 floors) · Siddhivinayak Angan Wing B (5 floors)
- Land: 2,728 sq m (about 0.7 acres) · sanctioned built-up 3,252 sq m · recreational space 400 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Siddhivinayak Angan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Siddhivinayak Angan: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Siddhivinayak Angan
What is the possession date of Siddhivinayak Angan?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Siddhivinayak Angan in Yavat, Pune is 31 July 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Siddhivinayak Angan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Siddhivinayak Angan's builder has filed on MahaRERA, the official one, is 31 July 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Siddhivinayak Angan?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Siddhivinayak Angan in Yavat, Pune is P52100046054.
Is Siddhivinayak Angan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan is registered as P52100046054 and its status is "Lapsed (registration period ended)".
What is the construction status of Siddhivinayak Angan?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Siddhivinayak Angan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Siddhivinayak Angan safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan is registered on MahaRERA as P52100046054, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Siddhivinayak Angan's possession date changes?
The latest dates are on Siddhivinayak Angan's MahaRERA page (P52100046054). GharKundli's Kundli Watch sends a free WhatsApp update on Siddhivinayak Angan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Siddhivinayak Angan have?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan has 2 buildings filed: Siddhivinayak Angan Wing A with 5 floors; Siddhivinayak Angan Wing B with 5 floors.
How big is the land of Siddhivinayak Angan?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan stands on 2,728 sq m of land (about 0.7 acres), with 3,252 sq m of sanctioned built-up area and 400 sq m of recreational open space.
Where can I read reviews of Siddhivinayak Angan?
Google Maps has reviews of Siddhivinayak Angan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Siddhivinayak Angan?
Siddhivinayak Angan by Siddhivinayak Developers is in Yavat, Pune (pincode 412214), Maharashtra, and is registered on MahaRERA as P52100046054, per GharKundli's check of MahaRERA records.
How many homes are in Siddhivinayak Angan?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan has 36 homes in 2 towers registered on MahaRERA.
When was Siddhivinayak Angan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Siddhivinayak Angan was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Siddhivinayak Angan?
No court cases are listed for Siddhivinayak Angan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Siddhivinayak Angan?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Siddhivinayak Developers, which has 46 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Siddhivinayak Angan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in Daund
All 5 projects in Yavat (412214) →Other projects by Siddhivinayak Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.