NAMAN PREMIER
by SHREE NAMAN DEVELOPERS PVT LTD · Andheri East, MumbaiAlso near Marol, Powai, Chandivali
Possession date of NAMAN PREMIER: 31 December 2025, moved from 31 March 2020 (69 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800008002. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about NAMAN PREMIER?
How the possession date of NAMAN PREMIER has moved
31 March 2020
Completion date given when the project was registered
30 March 2021
Extended at the builder's request (MahaRERA application EXT51800002453)
Reason the builder gave MahaRERA: “The project has been delayed for reasons beyond the control of the Promoters”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800011647)
Reason the builder gave MahaRERA: “The Project is delayed due to reasons beyond the control of the Promoter.”
Source: NAMAN PREMIER’s extension records on MahaRERA (P51800008002), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NAMAN PREMIER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008002
- Status
- Lapsed (registration period ended)
- Builder
- SHREE NAMAN DEVELOPERS PVT LTD
- Location
- Andheri East, Mumbai · 400059
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- March 2020
- Latest completion date
- December 2025
- Delay so far
- 69 months
- Homes
- 436
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of NAMAN PREMIER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NAMAN PREMIER | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- NAMAN PREMIER: covers 16th
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAMAN PREMIER every month.
NAMAN PREMIER: buildings, flats and land, as filed on MahaRERA
- Buildings: NAMAN PREMIER (23 floors, 436 units)
- Land: 6,694 sq m (about 1.7 acres) · sanctioned built-up 18,094 sq m · recreational space 1,339 sq m
- Boundaries filed include: Raj Industrial Complex, Greenfield Mapkhan Nagar
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shree Naman Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 72 months); 3 still being built, 1 past the promised date (typically 68 months late). 11 complaints on MahaRERA across 2 projects.
Read Google reviews of NAMAN PREMIER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NAMAN PREMIER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NAMAN PREMIER
What is the possession date of NAMAN PREMIER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NAMAN PREMIER in Andheri East, Mumbai is 31 December 2025 — 69 months later than 31 March 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for NAMAN PREMIER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NAMAN PREMIER's builder has filed on MahaRERA, the official one, is 31 December 2025, already 69 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NAMAN PREMIER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER's builder applied to MahaRERA to extend the completion date 2 times: to 30 March 2021, giving the reason "The project has been delayed for reasons beyond the control of the Promoters"; to 31 December 2025, giving the reason "The Project is delayed due to reasons beyond the control of the Promoter.".
What is the RERA number of NAMAN PREMIER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NAMAN PREMIER in Andheri East, Mumbai is P51800008002.
Is NAMAN PREMIER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER is registered as P51800008002 and its status is "Lapsed (registration period ended)".
What is the construction status of NAMAN PREMIER?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NAMAN PREMIER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does NAMAN PREMIER have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is NAMAN PREMIER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER is registered on MahaRERA as P51800008002, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 69 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NAMAN PREMIER's possession date changes?
The latest dates are on NAMAN PREMIER's MahaRERA page (P51800008002). GharKundli's Kundli Watch sends a free WhatsApp update on NAMAN PREMIER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NAMAN PREMIER have?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER has one building filed: NAMAN PREMIER with 23 floors and 436 units.
How big is the land of NAMAN PREMIER?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER stands on 6,694 sq m of land (about 1.7 acres), with 18,094 sq m of sanctioned built-up area and 1,339 sq m of recreational open space.
What is the track record of NAMAN PREMIER's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Naman Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 72 months); 3 still being built, 1 past the promised date (typically 68 months late). 11 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of NAMAN PREMIER?
Google Maps has reviews of NAMAN PREMIER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NAMAN PREMIER?
NAMAN PREMIER by SHREE NAMAN DEVELOPERS PVT LTD is in Andheri East, Mumbai (pincode 400059), near Marol, Powai, Chandivali, Maharashtra, and is registered on MahaRERA as P51800008002, per GharKundli's check of MahaRERA records. Its boundaries filed there include Raj Industrial Complex, Greenfield Mapkhan Nagar.
How many homes are in NAMAN PREMIER?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER has 436 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was NAMAN PREMIER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NAMAN PREMIER was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on NAMAN PREMIER?
No court cases are listed for NAMAN PREMIER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NAMAN PREMIER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE NAMAN DEVELOPERS PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NAMAN PREMIER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Andheri East
- Privilon
- AQUINA
- Trade Square 4th to 7th Floor
- I Wing Samarth Enclave Andheri Chhaya CHS
- Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
- Swapna Sudha CHS LTD
- Pratap Vista
- TRILIVE MAROL TOWER B