Sethia Grandeur
by K MANIAR (Sethia) · Bandra East, MumbaiAlso near Nirmal Nagar, Khar Delivery, Santacruz East
Possession date of Sethia Grandeur: 30 June 2022, moved from 30 December 2020 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800009020. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2022) has passed.
What do you want to know about Sethia Grandeur?
GharKundli’s full report on Sethia Grandeur
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009020
- Status
- Lapsed (registration period ended)
- Builder
- K MANIAR
- Location
- Bandra East, Mumbai · 400051
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- June 2022
- Delay so far
- 18 months
- Homes
- 95
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of Sethia Grandeur, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sethia Grandeur | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Sethia Grandeur: covers 20TH FLOOR
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sethia Grandeur every month.
Sethia Grandeur: buildings, flats and land, as filed on MahaRERA
- Buildings: Sethia Grandeur (22 floors, 99 units)
- Land: 896 sq m (about 0.2 acres) · sanctioned built-up 5,789 sq m · recreational space 46 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sethia Infrastructure (a group of 7 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late); 1 lapsed. 40 complaints on MahaRERA across 5 projects.
Read Google reviews of Sethia Grandeur →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sethia Grandeur: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sethia Grandeur
What is the possession date of Sethia Grandeur?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sethia Grandeur in Bandra East, Mumbai is 30 June 2022 — 18 months later than 30 December 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Sethia Grandeur?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sethia Grandeur's builder has filed on MahaRERA, the official one, is 30 June 2022, already 18 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sethia Grandeur?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sethia Grandeur in Bandra East, Mumbai is P51800009020.
Is Sethia Grandeur registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur is registered as P51800009020 and its status is "Lapsed (registration period ended)".
What is the construction status of Sethia Grandeur?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Sethia Grandeur is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sethia Grandeur have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sethia Grandeur safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur is registered on MahaRERA as P51800009020, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sethia Grandeur's possession date changes?
The latest dates are on Sethia Grandeur's MahaRERA page (P51800009020). GharKundli's Kundli Watch sends a free WhatsApp update on Sethia Grandeur every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sethia Grandeur have?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur has one building filed: Sethia Grandeur with 22 floors and 99 units.
How big is the land of Sethia Grandeur?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur stands on 896 sq m of land (about 0.2 acres), with 5,789 sq m of sanctioned built-up area and 46 sq m of recreational open space.
What is the track record of Sethia Grandeur's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Infrastructure (a group of 7 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late); 1 lapsed. 40 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sethia Grandeur?
Google Maps has reviews of Sethia Grandeur written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sethia Grandeur?
Sethia Grandeur by K MANIAR (Sethia) is in Bandra East, Mumbai (pincode 400051), near Nirmal Nagar, Khar Delivery, Santacruz East, Maharashtra, and is registered on MahaRERA as P51800009020, per GharKundli's check of MahaRERA records.
How many homes are in Sethia Grandeur?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur has 95 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was Sethia Grandeur registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sethia Grandeur was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Sethia Grandeur?
No court cases are listed for Sethia Grandeur on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Sethia Grandeur?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is K MANIAR, the company Sethia files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Sethia Grandeur
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400051
- Nero
- BKC 28
- K.K.GARMENT HUB
- KHERNAGAR SHRIRAM
- LEO EMINENCE
- Rustomjee Prive
- Vaibhavlaxmi Rhythm 51
- VAKRATUNDA ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.