by Rite Developers Pvt. Ltd. · Opp. Usha Nagar, MumbaiAlso near Bhandup West, Bhandup East, Nahur East

Possession date of Rite Advent: 30 March 2022, moved from 31 December 2018 (39 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009491. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2022) has passed.

What do you want to know about Rite Advent?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Rite Advent has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 September 2020

    Extended at the builder's request (MahaRERA application EXT51800001353)

    Reason the builder gave MahaRERA:
    “As per approved amended plan we had obtained full Commencement Certificate as per Architect certificate dated 8th October, 2018 from Ravi N. Gohil Architect, the current status of the project that internal and external development work in r…” Read the full reason“As per approved amended plan we had obtained full Commencement Certificate as per Architect certificate dated 8th October, 2018 from Ravi N. Gohil Architect, the current status of the project that internal and external development work in respect of project is 100% competed 100% as per approved plans. We state that due to delay in implementation of DCR 2034, we are waiting for getting approval on additional FSI in the project, further additional floors will be constructed on the said Property for utilising additional FSI on getting approval.”
  3. 30 September 2020

    Extended at the builder's request (MahaRERA application EXT51800005356)

    Reason the builder gave MahaRERA:
    “The current status of the project i.e. internal and external development work in respect of project is 100% competed, all members i.e. 64 Society original members and 77 new flat purchasers i.e. 141 members have taken possession of their re…” Read the full reason“The current status of the project i.e. internal and external development work in respect of project is 100% competed, all members i.e. 64 Society original members and 77 new flat purchasers i.e. 141 members have taken possession of their respective flats in the said project Now only additional 5 flats to be approved and constructed due to delay in implementation of DCR 2034, there was delay in approval of plans further as per the process we are compiling various procedure and as soon as on receipt of commencement Certificate we will start the construction work and complete the same within t…”
  4. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT51800009439)

    Reason the builder gave MahaRERA:
    “As per approved amended plan we had obtained full Commencement Certificate as per Architect certificate dated 31st December, 2019 from Ravi N. Gohil Architect, the current status of the project that internal and external development work in…” Read the full reason“As per approved amended plan we had obtained full Commencement Certificate as per Architect certificate dated 31st December, 2019 from Ravi N. Gohil Architect, the current status of the project that internal and external development work in respect of project is 100% competed 100% as per approved plans, also all members i.e., 64 Society original members and 77 new flat purchasers i.e. 141 members have taken possession of their respective flats in the said project. Now only additional 5 flats are approved but to be constructed.We state that due to delay in implementation of DCR 2034, there w…”
  5. 30 March 2022

    Revised completion date on MahaRERA

Source: Rite Advent’s extension records on MahaRERA (P51800009491), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rite Advent

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the March 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009491
Status
Lapsed (registration period ended)
Builder
Rite Developers Pvt. Ltd.
Location
Opp. Usha Nagar, Mumbai · 400078
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2018
Latest completion date
March 2022
Delay so far
39 months
Homes
82
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Rite Advent, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Rite Advent100%99%97%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rite Advent every month.

Rite Advent: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Rite Developers has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 5 lapsed. 16 complaints on MahaRERA across 4 projects.

Read Google reviews of Rite Advent →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rite Advent: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Rite Advent

What is the possession date of Rite Advent?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rite Advent in Opp. Usha Nagar, Mumbai is 30 March 2022 — 39 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Rite Advent?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rite Advent's builder has filed on MahaRERA, the official one, is 30 March 2022, already 39 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Rite Advent extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent's builder applied to MahaRERA to extend the completion date 3 times: to 30 September 2020, giving the reason "As per approved amended plan we had obtained full Commencement Certificate as per Architect certificate dated 8th October, 2018 from Ravi N. Gohil Architect, the current status of the project that internal and external development work in respect of project is 100% competed 100% as per approved plans. We state that due to delay in implementation of DCR 2034, we are waiting for getting approval on additional FSI in the project, further additional floors will be constructed on the said Property for utilising additional FSI on getting approval."; to 30 September 2020, giving the reason "The current status of the project i.e. internal and external development work in respect of project is 100% competed, all members i.e. 64 Society original members and 77 new flat purchasers i.e. 141 members have taken possession of their respective flats in the said project Now only additional 5 flats to be approved and constructed due to delay in implementation of DCR 2034, there was delay in approval of plans further as per the process we are compiling various procedure and as soon as on receipt of commencement Certificate we will start the construction work and complete the same within t…"; to 30 September 2021, giving the reason "As per approved amended plan we had obtained full Commencement Certificate as per Architect certificate dated 31st December, 2019 from Ravi N. Gohil Architect, the current status of the project that internal and external development work in respect of project is 100% competed 100% as per approved plans, also all members i.e., 64 Society original members and 77 new flat purchasers i.e. 141 members have taken possession of their respective flats in the said project. Now only additional 5 flats are approved but to be constructed.We state that due to delay in implementation of DCR 2034, there w…".

What is the RERA number of Rite Advent?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rite Advent in Opp. Usha Nagar, Mumbai is P51800009491.

Is Rite Advent registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent is registered as P51800009491 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Rite Advent?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Rite Advent is 99% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.

Does Rite Advent have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Rite Advent safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent is registered on MahaRERA as P51800009491, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 39 months since registration, 2 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Rite Advent's possession date changes?

The latest dates are on Rite Advent's MahaRERA page (P51800009491). GharKundli's Kundli Watch sends a free WhatsApp update on Rite Advent every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rite Advent have?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent has one building filed: Rite Advent with 16 floors.

How big is the land of Rite Advent?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent stands on 3,182 sq m of land (about 0.8 acres), with 7,670 sq m of sanctioned built-up area and 615 sq m of recreational open space.

What is the track record of Rite Advent's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Developers has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 5 lapsed. 16 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Rite Advent?

Google Maps has reviews of Rite Advent written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Rite Advent?

Rite Advent by Rite Developers Pvt. Ltd. is in Opp. Usha Nagar, Mumbai (pincode 400078), near Bhandup West, Bhandup East, Nahur East, Maharashtra, and is registered on MahaRERA as P51800009491, per GharKundli's check of MahaRERA records.

How many homes are in Rite Advent?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent has 82 homes in 1 tower registered on MahaRERA.

When was Rite Advent registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Advent was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Rite Advent?

No court cases are listed for Rite Advent on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Rite Advent?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Rite Developers Pvt. Ltd., which has 9 other projects registered on MahaRERA.

Other projects in Kurla

All 176 projects in Bhandup West (400078) →

Other projects by Rite Developers Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.