Rite Skyluxe

by Rite Developers Pvt. Ltd. · Chembur, MumbaiAlso near Govandi, Ghatkopar East, Subhash Nagar

Possession date of Rite Skyluxe: 30 December 2021, moved from 31 December 2018 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800006893. Status: Lapsed (registration period ended). 11 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about Rite Skyluxe?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Rite Skyluxe has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51800001110)

    Reason the builder gave MahaRERA:
    “(1) Due to change in Government policies initially there were difference of opinion occurred between two government authorities (i.e. MHADA and MCGM) due to which process to give sanctions were kept on hold by both the authorities; (2) furt…” Read the full reason“(1) Due to change in Government policies initially there were difference of opinion occurred between two government authorities (i.e. MHADA and MCGM) due to which process to give sanctions were kept on hold by both the authorities; (2) further on 16th June, 2017 we got full concessions approved for “B” wing with condition that Subhash Nagar layout to be approved from Municipal commissioner for full FSI and Subhash Nagar Layout got approved by MHADA on 1st February, 2018. (3) Vide notification issued by Urban Department, Department of Govt. of Maharashtra, wherein MHADA has been appointed as…”
  3. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT51800005423)

    Reason the builder gave MahaRERA:
    “The current status of the project i.e. internal and external development work in respect of project is 85% competed as per approved plans further due to change in goverment policy, change in approving authority i.e. from MCGM to MHADA due t…” Read the full reason“The current status of the project i.e. internal and external development work in respect of project is 85% competed as per approved plans further due to change in goverment policy, change in approving authority i.e. from MCGM to MHADA due to which got delayed in completion of project within time line. We also obtain consent from the Allottees for extension of the date mentioned in RERA, and Allottees have no objection in extension of possession date in RERA i.e. date of Completion of project be extended from 31st December, 2019 to 31st December, 2020.”
  4. 30 December 2021

    Revised completion date on MahaRERA

Source: Rite Skyluxe’s extension records on MahaRERA (P51800006893), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rite Skyluxe

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 11 complaints and 1 court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006893
Status
Lapsed (registration period ended)
Builder
Rite Developers Pvt. Ltd.
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2021
Delay so far
36 months
Homes
85
Towers
1
Complaints on MahaRERA
11
Court cases listed
1
Appeals at the tribunal
3
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Rite Skyluxe, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Rite Skyluxe100%94%94%94%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rite Skyluxe every month.

Rite Skyluxe: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Rite Developers has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 5 lapsed. 16 complaints on MahaRERA across 4 projects.

Read Google reviews of Rite Skyluxe →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rite Skyluxe: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Rite Skyluxe

What is the possession date of Rite Skyluxe?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rite Skyluxe in Chembur, Mumbai is 30 December 2021 — 36 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Rite Skyluxe?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rite Skyluxe's builder has filed on MahaRERA, the official one, is 30 December 2021, already 36 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Rite Skyluxe extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "(1) Due to change in Government policies initially there were difference of opinion occurred between two government authorities (i.e. MHADA and MCGM) due to which process to give sanctions were kept on hold by both the authorities; (2) further on 16th June, 2017 we got full concessions approved for “B” wing with condition that Subhash Nagar layout to be approved from Municipal commissioner for full FSI and Subhash Nagar Layout got approved by MHADA on 1st February, 2018. (3) Vide notification issued by Urban Department, Department of Govt. of Maharashtra, wherein MHADA has been appointed as…"; to 31 December 2020, giving the reason "The current status of the project i.e. internal and external development work in respect of project is 85% competed as per approved plans further due to change in goverment policy, change in approving authority i.e. from MCGM to MHADA due to which got delayed in completion of project within time line. We also obtain consent from the Allottees for extension of the date mentioned in RERA, and Allottees have no objection in extension of possession date in RERA i.e. date of Completion of project be extended from 31st December, 2019 to 31st December, 2020.".

What is the RERA number of Rite Skyluxe?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rite Skyluxe in Chembur, Mumbai is P51800006893.

Is Rite Skyluxe registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe is registered as P51800006893 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Rite Skyluxe?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Rite Skyluxe is 94% done and internal work 94%. GharKundli's full report compares construction progress with the deadline.

Does Rite Skyluxe have complaints on MahaRERA?

11 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Rite Skyluxe safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe is registered on MahaRERA as P51800006893, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration, 11 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Rite Skyluxe's possession date changes?

The latest dates are on Rite Skyluxe's MahaRERA page (P51800006893). GharKundli's Kundli Watch sends a free WhatsApp update on Rite Skyluxe every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rite Skyluxe have?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe has one building filed: Rite Skyluxe with 18 floors.

How big is the land of Rite Skyluxe?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe stands on 1,447 sq m of land (about 0.4 acres), with 6,831 sq m of sanctioned built-up area.

What is the track record of Rite Skyluxe's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Developers has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 5 lapsed. 16 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Rite Skyluxe?

Google Maps has reviews of Rite Skyluxe written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 11 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Rite Skyluxe?

Rite Skyluxe by Rite Developers Pvt. Ltd. is in Chembur, Mumbai (pincode 400071), near Govandi, Ghatkopar East, Subhash Nagar, Maharashtra, and is registered on MahaRERA as P51800006893, per GharKundli's check of MahaRERA records.

How many homes are in Rite Skyluxe?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe has 85 homes in 1 tower registered on MahaRERA.

When was Rite Skyluxe registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rite Skyluxe was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Rite Skyluxe?

1 court case is listed for Rite Skyluxe on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Rite Skyluxe?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Rite Developers Pvt. Ltd., which has 9 other projects registered on MahaRERA.

Other projects in pincode 400071

All 318 projects in Chembur (400071) →

Other projects by Rite Developers Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.