ARIHANT RESIDENCY

by ARIHANT INFRASTRUCTURE COMPANY · Chunabhatti, MumbaiAlso near Chembur, Nehru Nagar, Sion

Possession date of ARIHANT RESIDENCY: 31 March 2026, moved from 30 September 2019 (78 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800008281. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (March 2026) has passed.

What do you want to know about ARIHANT RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ARIHANT RESIDENCY has moved

  1. 30 September 2019

    Completion date given when the project was registered

  2. 29 September 2020

    Extended at the builder's request (MahaRERA application EXT51800002468)

    Reason the builder gave MahaRERA:
    “• High Court Stay in PIL 86/2014 ~ The Directorate General of Civil Aviation (DGCA) is the Indian governmental regulatory body for civil aviation under the Ministry of Civil Aviation. As a result of the Stay imposed in the PIL 86/2014 on 01…” Read the full reason“• High Court Stay in PIL 86/2014 ~ The Directorate General of Civil Aviation (DGCA) is the Indian governmental regulatory body for civil aviation under the Ministry of Civil Aviation. As a result of the Stay imposed in the PIL 86/2014 on 01.09.16, the DGCA authority was restricted in issuing any NOC for Additional Height Clearance . • Final Order in PIL 86/2014. In the final order dated 5 & 6th April 2018, the stay was lifted and the process for Aeronautical Study could be conducted. • Height Approval of 78.75 ASML for our project was finally approved by AAI and sanctioned on 04.07.18. • DC…”
  3. 29 December 2021

    Extended at the builder's request (MahaRERA application EXT51800009434)

    Reason the builder gave MahaRERA:
    “We, M/s. Arihant Infrastructure Company, hereby request you to grant extension of registration for project ‘Arihant Residency’ situated at Kurla, Mumbai Suburban, PIN 400022. Registered with the regulatory authority vide project registratio…” Read the full reason“We, M/s. Arihant Infrastructure Company, hereby request you to grant extension of registration for project ‘Arihant Residency’ situated at Kurla, Mumbai Suburban, PIN 400022. Registered with the regulatory authority vide project registration certificate bearing no. P51800008281 for a further period of 9 Months from 30.03.2021 to 29.12.2021. The under-construction project got delayed due to various reasons such as stay order received form High court, Solid Waste Management prohibited by Supreme Court and change in approving authority. Please find detailed reasoning of delay in project comple…”
  4. 30 March 2023

    Extended at the builder's request (MahaRERA application EXT51800012244)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 51.35% allottees for purpose of extension of RERA registration period of the said project. The under-construction project got delayed due to various reasons such as stay order received form High court, Solid Waste Management prohibited by Supreme Court and change in approving authority.”
  5. 30 March 2024

    Extended at the builder's request (MahaRERA application EXT51800015375)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.31% allottees for purpose of extension of RERA registration period of the said project.”
  6. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51800019468)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.92% allottees for purpose of extension of RERA registration period of the said project.”
  7. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51800028339)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Ce…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-03-2026 to complete the project and f…”

Source: ARIHANT RESIDENCY’s extension records on MahaRERA (P51800008281), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ARIHANT RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the March 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008281
Status
Lapsed (registration period ended)
Builder
ARIHANT INFRASTRUCTURE COMPANY
Location
Chunabhatti, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
18 Aug 2017
Completion date at registration
September 2019
Latest completion date
March 2026
Delay so far
78 months
Homes
100
Sold or booked
43%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of ARIHANT RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A, B100%100%100%97%

Commencement certificate (CC), as filed on MahaRERA

  • WING A, B: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT RESIDENCY every month.

ARIHANT RESIDENCY: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK414 – 41759
2 BHK602 – 67041
Shops55 – 1,0204

The builder’s record and reviews

Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects.

Read Google reviews of ARIHANT RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ARIHANT RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ARIHANT RESIDENCY

What is the possession date of ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT RESIDENCY in Chunabhatti, Mumbai is 31 March 2026 — 78 months later than 30 September 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for ARIHANT RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT RESIDENCY's builder has filed on MahaRERA, the official one, is 31 March 2026, already 78 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ARIHANT RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY's builder applied to MahaRERA to extend the completion date 6 times: to 29 September 2020, giving the reason "• High Court Stay in PIL 86/2014 ~ The Directorate General of Civil Aviation (DGCA) is the Indian governmental regulatory body for civil aviation under the Ministry of Civil Aviation. As a result of the Stay imposed in the PIL 86/2014 on 01.09.16, the DGCA authority was restricted in issuing any NOC for Additional Height Clearance . • Final Order in PIL 86/2014. In the final order dated 5 & 6th April 2018, the stay was lifted and the process for Aeronautical Study could be conducted. • Height Approval of 78.75 ASML for our project was finally approved by AAI and sanctioned on 04.07.18. • DC…"; to 29 December 2021, giving the reason "We, M/s. Arihant Infrastructure Company, hereby request you to grant extension of registration for project ‘Arihant Residency’ situated at Kurla, Mumbai Suburban, PIN 400022. Registered with the regulatory authority vide project registration certificate bearing no. P51800008281 for a further period of 9 Months from 30.03.2021 to 29.12.2021. The under-construction project got delayed due to various reasons such as stay order received form High court, Solid Waste Management prohibited by Supreme Court and change in approving authority. Please find detailed reasoning of delay in project comple…"; to 30 March 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 51.35% allottees for purpose of extension of RERA registration period of the said project. The under-construction project got delayed due to various reasons such as stay order received form High court, Solid Waste Management prohibited by Supreme Court and change in approving authority."; to 30 March 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 51.31% allottees for purpose of extension of RERA registration period of the said project."; to 31 March 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.92% allottees for purpose of extension of RERA registration period of the said project."; to 31 March 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-03-2026 to complete the project and f…".

What is the RERA number of ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT RESIDENCY in Chunabhatti, Mumbai is P51800008281.

Is ARIHANT RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY is registered as P51800008281 and its status is "Lapsed (registration period ended)".

What is the construction status of ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on WING A, B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does ARIHANT RESIDENCY have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ARIHANT RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY is registered on MahaRERA as P51800008281, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 78 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ARIHANT RESIDENCY's possession date changes?

The latest dates are on ARIHANT RESIDENCY's MahaRERA page (P51800008281). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ARIHANT RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY has one building filed: WING A, B with 21 floors and 104 units.

What are the flat sizes (carpet area) in ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ARIHANT RESIDENCY: 1 BHK: 414 to 417 sq ft carpet (59 homes); 2 BHK: 602 to 670 sq ft carpet (41 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY stands on 1,408 sq m of land (about 0.3 acres), with 8,264 sq m of sanctioned built-up area.

What is the track record of ARIHANT RESIDENCY's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ARIHANT RESIDENCY?

Google Maps has reviews of ARIHANT RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ARIHANT RESIDENCY?

ARIHANT RESIDENCY by ARIHANT INFRASTRUCTURE COMPANY is in Chunabhatti, Mumbai (pincode 400022), near Chembur, Nehru Nagar, Sion, Maharashtra, and is registered on MahaRERA as P51800008281, per GharKundli's check of MahaRERA records.

How many homes are in ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY has 100 homes in 1 tower registered on MahaRERA, and 43% of them are sold or booked.

When was ARIHANT RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT RESIDENCY was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ARIHANT RESIDENCY?

No court cases are listed for ARIHANT RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ARIHANT RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT INFRASTRUCTURE COMPANY, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai City →

Other projects in pincode 400022

All 98 projects in Sion (400022) →

Other projects by ARIHANT INFRASTRUCTURE COMPANY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.