Skip to content
GharKundli

ARIHANT HEIGHTS

by ARIHANT INFRASTRUCTURE COMPANY · Ghatkopar West, MumbaiAlso near Ghatkopar East, Pant Nagar, Vile Parle West

Possession date of ARIHANT HEIGHTS: 31 December 2026, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800015068, and currently active. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ARIHANT HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ARIHANT HEIGHTS has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009104)

    Reason the builder gave MahaRERA:
    “The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013642)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.56% allottees for purpose of extension of RERA registration period of the said project.”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019062)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 52.5% allottees for purpose of extension of RERA registration period of the said project.”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025556)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Ce…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements.”
  6. 31 December 2026

    Extended at the builder's request (MahaRERA application EA14012619438)

    Reason the builder gave MahaRERA:
    “The delay in obtaining the OC is solely due to procedural requirements and administrative processing by the authority, which is beyond the control of the promoter. To ensure full regulatory compliance and to avoid any technical lapse in RER…” Read the full reason“The delay in obtaining the OC is solely due to procedural requirements and administrative processing by the authority, which is beyond the control of the promoter. To ensure full regulatory compliance and to avoid any technical lapse in RERA validity during this period, we are applying for an extension of the project registration. No further construction activity is pending, and the extension is required only until the OC is formally issued.”

Source: ARIHANT HEIGHTS’s extension records on MahaRERA (P51800015068), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ARIHANT HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800015068
Status
Registered and active
Builder
ARIHANT INFRASTRUCTURE COMPANY
Location
Ghatkopar West, Mumbai · 400086
Project type
Residential / Group Housing
Registered on
23 Jan 2018
Completion date at registration
June 2021
Latest completion date
December 2026
Delay so far
66 months
Homes
100
Sold or booked
45%
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of ARIHANT HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ARIHANT HEIGHTS100%100%85%50%

Commencement certificate (CC), as filed on MahaRERA

  • ARIHANT HEIGHTS: covers 13 (2 Basements + Ground + 10 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT HEIGHTS every month.

ARIHANT HEIGHTS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK414 – 41759
2 BHK602 – 67041
Shops55 – 1,0204

The builder’s record and reviews

Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects.

Read Google reviews of ARIHANT HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ARIHANT HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ARIHANT HEIGHTS

What is the possession date of ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT HEIGHTS in Ghatkopar West, Mumbai is 31 December 2026 — 66 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ARIHANT HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2026, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ARIHANT HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS's builder applied to MahaRERA to extend the completion date 5 times: to 30 June 2022, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry."; to 31 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.56% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 52.5% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements."; to 31 December 2026, giving the reason "The delay in obtaining the OC is solely due to procedural requirements and administrative processing by the authority, which is beyond the control of the promoter. To ensure full regulatory compliance and to avoid any technical lapse in RERA validity during this period, we are applying for an extension of the project registration. No further construction activity is pending, and the extension is required only until the OC is formally issued.".

What is the RERA number of ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT HEIGHTS in Ghatkopar West, Mumbai is P51800015068.

Is ARIHANT HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS is registered as P51800015068 and its status is "Registered and active".

What is the construction status of ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ARIHANT HEIGHTS is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does ARIHANT HEIGHTS have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ARIHANT HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS is registered on MahaRERA as P51800015068, its completion date has moved 66 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ARIHANT HEIGHTS's possession date changes?

The latest dates are on ARIHANT HEIGHTS's MahaRERA page (P51800015068). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ARIHANT HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS has one building filed: ARIHANT HEIGHTS with 13 floors and 104 units.

What are the flat sizes (carpet area) in ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ARIHANT HEIGHTS: 1 BHK: 414 to 417 sq ft carpet (59 homes); 2 BHK: 602 to 670 sq ft carpet (41 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS stands on 1,673 sq m of land (about 0.4 acres), with 5,325 sq m of sanctioned built-up area.

What is the track record of ARIHANT HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ARIHANT HEIGHTS?

Google Maps has reviews of ARIHANT HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ARIHANT HEIGHTS?

ARIHANT HEIGHTS by ARIHANT INFRASTRUCTURE COMPANY is in Ghatkopar West, Mumbai (pincode 400086), near Ghatkopar East, Pant Nagar, Vile Parle West, Maharashtra, and is registered on MahaRERA as P51800015068, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPAL SCHOOL.

How many homes are in ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS has 100 homes in 1 tower registered on MahaRERA, and 45% of them are sold or booked.

When was ARIHANT HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT HEIGHTS was registered on MahaRERA on 23 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on ARIHANT HEIGHTS?

No court cases are listed for ARIHANT HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ARIHANT HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT INFRASTRUCTURE COMPANY, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400086

All 83 projects in Ghatkopar West (400086) →

Other projects by ARIHANT INFRASTRUCTURE COMPANY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.