KDR PLATINUM
by KDR BUILDER · Nari, NagpurAlso near Uppalwadi, Dr.Ambedkar Marg
Possession date of KDR PLATINUM: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1190002500725, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KDR PLATINUM?
How the possession date of KDR PLATINUM has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KDR PLATINUM’s extension records on MahaRERA (PR1190002500725), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KDR PLATINUM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1190002500725
- Status
- Registered and active
- Builder
- KDR BUILDER
- Location
- Nari, Nagpur · 440026
- Project type
- Residential / Group Housing
- Registered on
- 9 Sep 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 33
- Sold or booked
- 12%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KDR PLATINUM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| R-4,CTS No 415,KH No 53,Sheet No 920/55,Mouza Nari | 100% | 35% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- R-4,CTS No 415,KH No 53,Sheet No 920/55,Mouza Nari: covers 7 floors
Latest CC order on MahaRERA: dated 23/06/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KDR PLATINUM every month.
KDR PLATINUM: buildings, flats and land, as filed on MahaRERA
- Buildings: R-4,CTS No 415,KH No 53,Sheet No 920/55,Mouza Nari (8 floors, 33 units)
- Car parking: 16 covered
- Land: 853 sq m (about 0.2 acres) · sanctioned built-up 2,726 sq m
- Boundaries filed include: ROAD APPROACH
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KDR PLATINUM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KDR PLATINUM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KDR PLATINUM
What is the possession date of KDR PLATINUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KDR PLATINUM in Nari, Nagpur is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KDR PLATINUM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KDR PLATINUM's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of KDR PLATINUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KDR PLATINUM in Nari, Nagpur is PR1190002500725.
Is KDR PLATINUM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM is registered as PR1190002500725 and its status is "Registered and active".
What is the construction status of KDR PLATINUM?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM's status on MahaRERA is "Registered and active". As filed by the builder, slab work on R-4,CTS No 415,KH No 53,Sheet No 920/55,Mouza Nari is 35% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does KDR PLATINUM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is KDR PLATINUM safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM is registered on MahaRERA as PR1190002500725, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KDR PLATINUM's possession date changes?
The latest dates are on KDR PLATINUM's MahaRERA page (PR1190002500725). GharKundli's Kundli Watch sends a free WhatsApp update on KDR PLATINUM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KDR PLATINUM have?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM has one building filed: R-4,CTS No 415,KH No 53,Sheet No 920/55,Mouza Nari with 8 floors and 33 units.
How much parking does KDR PLATINUM have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered car parking spaces for KDR PLATINUM.
How big is the land of KDR PLATINUM?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM stands on 853 sq m of land (about 0.2 acres), with 2,726 sq m of sanctioned built-up area.
Where can I read reviews of KDR PLATINUM?
Google Maps has reviews of KDR PLATINUM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KDR PLATINUM?
KDR PLATINUM by KDR BUILDER is in Nari, Nagpur (pincode 440026), near Uppalwadi, Dr.Ambedkar Marg, Maharashtra, and is registered on MahaRERA as PR1190002500725, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROAD APPROACH.
How many homes are in KDR PLATINUM?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM has 33 homes in 1 tower registered on MahaRERA, and 12% of them are sold or booked.
When was KDR PLATINUM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KDR PLATINUM was registered on MahaRERA on 9 September 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on KDR PLATINUM?
No court cases are listed for KDR PLATINUM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KDR PLATINUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KDR BUILDER.
Check it yourself on MahaRERA
- How to check the possession date of KDR PLATINUM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Nagpur →
Other projects in Nagpur (Urban)
- RAI CREST
- KDR ROYALE
- ROYAL PARK
- GLOCAL SQUARE 3 RD FLOOR
- SHREE APARTMENTS
- Mithila Apartment
- EMPRESS ROYAL EFGH
- ROYAL PRIDE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.