SAFAL SAI AND SAFAL SAINATH

by MANGALNATH DEVELOPERS PVT LTD · Kelkarwadi, MumbaiAlso near Chembur, Kurla, Govandi

Possession date of SAFAL SAI AND SAFAL SAINATH: 31 October 2026, moved from 30 December 2023 (34 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009799, and currently active. 11 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about SAFAL SAI AND SAFAL SAINATH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAFAL SAI AND SAFAL SAINATH has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT51800018316)

    Reason the builder gave MahaRERA:
    “THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN W…” Read the full reason“THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW WE HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS.”
  3. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51800024699)

    Reason the builder gave MahaRERA: “DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS STILL NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UPTO 31ST MARCH 2025.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800028420)

    Reason the builder gave MahaRERA: “Due to unresolved financial issues that have impacted the progress of the project. Despite of our best efforts, the required financial resources are not yet fully secured. we therefore request for an extension up to December 2025”
  5. 31 May 2026

    Extended at the builder's request (MahaRERA application EA28042620761)

    Reason the builder gave MahaRERA:
    “Due to financial issues project was slow now all financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progr…” Read the full reason“Due to financial issues project was slow now all financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progress and the revised construction schedule, we requires an additional 5 months (up to May 2026) to complete the project in all respects. We assures the Hon’ble Authority that the interests of allottees are fully safeguarded, and the project shall be completed within the extended period.”
  6. 31 October 2026

    Extended at the builder's request (MahaRERA application EA27062621575)

    Reason the builder gave MahaRERA:
    “The structural construction of the project is fully completed. However, we require additional time of approximately five months to complete the remaining finishing works, testing, common area development, and rectification of minor pending…” Read the full reason“The structural construction of the project is fully completed. However, we require additional time of approximately five months to complete the remaining finishing works, testing, common area development, and rectification of minor pending items and statutory inspections, compliance procedures, and obtaining the Occupancy Certificate from the competent authority. You are therefore requested to kindly consider application and grant us extension upto 31st October 2026”

Source: SAFAL SAI AND SAFAL SAINATH’s extension records on MahaRERA (P51800009799), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAFAL SAI AND SAFAL SAINATH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 11 complaints, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009799
Status
Registered and active
Builder
MANGALNATH DEVELOPERS PVT LTD
Location
Kelkarwadi, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2023
Latest completion date
October 2026
Delay so far
34 months
Homes
195
Sold or booked
75%
Towers
2
Complaints on MahaRERA
11
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SAFAL SAI AND SAFAL SAINATH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAFAL SAI WING A WING B AND WING C100%100%100%100%
SAFAL SAINATH100%25%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • SAFAL SAI WING A WING B AND WING C: covers 12 floors
  • SAFAL SAINATH: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAFAL SAI AND SAFAL SAINATH every month.

SAFAL SAI AND SAFAL SAINATH: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAFAL SAI WING A WING B AND WING C (14 floors, 137 units) · SAFAL SAINATH (21 floors, 61 units)
  • Land: 4,686 sq m (about 1.2 acres) · sanctioned built-up 9,367 sq m · recreational space 151 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects.

Read Google reviews of SAFAL SAI AND SAFAL SAINATH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAFAL SAI AND SAFAL SAINATH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAFAL SAI AND SAFAL SAINATH

What is the possession date of SAFAL SAI AND SAFAL SAINATH?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAFAL SAI AND SAFAL SAINATH in Kelkarwadi, Mumbai is 31 October 2026 — 34 months later than 30 December 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAFAL SAI AND SAFAL SAINATH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAFAL SAI AND SAFAL SAINATH's builder has filed on MahaRERA, the official one, is 31 October 2026, already 34 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAFAL SAI AND SAFAL SAINATH extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH's builder applied to MahaRERA to extend the completion date 5 times: to 31 August 2024, giving the reason "THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW WE HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS."; to 31 March 2025, giving the reason "DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS STILL NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UPTO 31ST MARCH 2025."; to 31 December 2025, giving the reason "Due to unresolved financial issues that have impacted the progress of the project. Despite of our best efforts, the required financial resources are not yet fully secured. we therefore request for an extension up to December 2025"; to 31 May 2026, giving the reason "Due to financial issues project was slow now all financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progress and the revised construction schedule, we requires an additional 5 months (up to May 2026) to complete the project in all respects. We assures the Hon’ble Authority that the interests of allottees are fully safeguarded, and the project shall be completed within the extended period."; to 31 October 2026, giving the reason "The structural construction of the project is fully completed. However, we require additional time of approximately five months to complete the remaining finishing works, testing, common area development, and rectification of minor pending items and statutory inspections, compliance procedures, and obtaining the Occupancy Certificate from the competent authority. You are therefore requested to kindly consider application and grant us extension upto 31st October 2026".

What is the RERA number of SAFAL SAI AND SAFAL SAINATH?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAFAL SAI AND SAFAL SAINATH in Kelkarwadi, Mumbai is P51800009799.

Is SAFAL SAI AND SAFAL SAINATH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH is registered as P51800009799 and its status is "Registered and active".

What is the construction status of SAFAL SAI AND SAFAL SAINATH?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 25% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SAFAL SAI AND SAFAL SAINATH have complaints on MahaRERA?

11 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAFAL SAI AND SAFAL SAINATH safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH is registered on MahaRERA as P51800009799, its completion date has moved 34 months since registration and 11 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAFAL SAI AND SAFAL SAINATH's possession date changes?

The latest dates are on SAFAL SAI AND SAFAL SAINATH's MahaRERA page (P51800009799). GharKundli's Kundli Watch sends a free WhatsApp update on SAFAL SAI AND SAFAL SAINATH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAFAL SAI AND SAFAL SAINATH have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH has 2 buildings filed: SAFAL SAI WING A WING B AND WING C with 14 floors and 137 units; SAFAL SAINATH with 21 floors and 61 units.

How big is the land of SAFAL SAI AND SAFAL SAINATH?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH stands on 4,686 sq m of land (about 1.2 acres), with 9,367 sq m of sanctioned built-up area and 151 sq m of recreational open space.

What is the track record of SAFAL SAI AND SAFAL SAINATH's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAFAL SAI AND SAFAL SAINATH?

Google Maps has reviews of SAFAL SAI AND SAFAL SAINATH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 11 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAFAL SAI AND SAFAL SAINATH?

SAFAL SAI AND SAFAL SAINATH by MANGALNATH DEVELOPERS PVT LTD is in Kelkarwadi, Mumbai (pincode 400071), near Chembur, Kurla, Govandi, Maharashtra, and is registered on MahaRERA as P51800009799, per GharKundli's check of MahaRERA records.

How many homes are in SAFAL SAI AND SAFAL SAINATH?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH has 195 homes in 2 towers registered on MahaRERA, and 75% of them are sold or booked.

When was SAFAL SAI AND SAFAL SAINATH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL SAI AND SAFAL SAINATH was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAFAL SAI AND SAFAL SAINATH?

No court cases are listed for SAFAL SAI AND SAFAL SAINATH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAFAL SAI AND SAFAL SAINATH?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANGALNATH DEVELOPERS PVT LTD, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Kurla

All 318 projects in Chembur (400071) →

Other projects by MANGALNATH DEVELOPERS PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.