SAFAL GOLF RESIDENCES
by MANGALNATH DEVELOPERS PVT LTD · Chembur Mumbai, MumbaiAlso near Fci, Nehru Nagar
Possession date of SAFAL GOLF RESIDENCES: 30 October 2027, moved from 31 December 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800029994, and currently active. Its completion date has moved from December 2024 to October 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAFAL GOLF RESIDENCES?
How the possession date of SAFAL GOLF RESIDENCES has moved
31 December 2024
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EXT51800027186)
Reason the builder gave MahaRERA:
“We started this project after covid-19, due to effect of covid-19 old developer was removed by SRA through regulation 13/2, further due all these process and pending matters of old developers, change of NOC and documentation took time so we…” Read the full reason
“We started this project after covid-19, due to effect of covid-19 old developer was removed by SRA through regulation 13/2, further due all these process and pending matters of old developers, change of NOC and documentation took time so we were unable to start the project on time . Now construction is started and plinth of the building is completed. therefore request you to give extension upto 30th June 2027.”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAFAL GOLF RESIDENCES’s extension records on MahaRERA (P51800029994), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAFAL GOLF RESIDENCES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800029994
- Status
- Registered and active
- Builder
- MANGALNATH DEVELOPERS PVT LTD
- Location
- Chembur Mumbai, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 20 Jul 2021
- Completion date at registration
- December 2024
- Latest completion date
- October 2027
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 218
- Sold or booked
- 43%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAFAL GOLF RESIDENCES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAFAL GOLF RESIDENCES | 65% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAFAL GOLF RESIDENCES: covers PLINTH
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAFAL GOLF RESIDENCES every month.
SAFAL GOLF RESIDENCES: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 545 – 1,023 | 139 |
| 1 BHK | 379 – 569 | 79 |
- Buildings: SAFAL GOLF RESIDENCES (23 floors, 218 units)
- Land: 3,718 sq m (about 0.9 acres) · sanctioned built-up 9,012 sq m · recreational space 361 sq m
The builder’s record and reviews
Nav Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects.
Read Google reviews of SAFAL GOLF RESIDENCES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAFAL GOLF RESIDENCES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAFAL GOLF RESIDENCES
What is the possession date of SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAFAL GOLF RESIDENCES in Chembur Mumbai, Mumbai is 30 October 2027 — 30 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAFAL GOLF RESIDENCES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAFAL GOLF RESIDENCES's builder has filed on MahaRERA, the official one, is 30 October 2027, already 30 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAFAL GOLF RESIDENCES extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "We started this project after covid-19, due to effect of covid-19 old developer was removed by SRA through regulation 13/2, further due all these process and pending matters of old developers, change of NOC and documentation took time so we were unable to start the project on time . Now construction is started and plinth of the building is completed. therefore request you to give extension upto 30th June 2027.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAFAL GOLF RESIDENCES in Chembur Mumbai, Mumbai is P51800029994.
Is SAFAL GOLF RESIDENCES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES is registered as P51800029994 and its status is "Registered and active".
What is the construction status of SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAFAL GOLF RESIDENCES is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SAFAL GOLF RESIDENCES have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAFAL GOLF RESIDENCES safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES is registered on MahaRERA as P51800029994, its completion date has moved 30 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAFAL GOLF RESIDENCES's possession date changes?
The latest dates are on SAFAL GOLF RESIDENCES's MahaRERA page (P51800029994). GharKundli's Kundli Watch sends a free WhatsApp update on SAFAL GOLF RESIDENCES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAFAL GOLF RESIDENCES have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES has one building filed: SAFAL GOLF RESIDENCES with 23 floors and 218 units.
What are the flat sizes (carpet area) in SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAFAL GOLF RESIDENCES: 2 BHK: 545 to 1023 sq ft carpet (139 homes); 1 BHK: 379 to 569 sq ft carpet (79 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES stands on 3,718 sq m of land (about 0.9 acres), with 9,012 sq m of sanctioned built-up area and 361 sq m of recreational open space.
What is the track record of SAFAL GOLF RESIDENCES's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Nav Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAFAL GOLF RESIDENCES?
Google Maps has reviews of SAFAL GOLF RESIDENCES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAFAL GOLF RESIDENCES?
SAFAL GOLF RESIDENCES by MANGALNATH DEVELOPERS PVT LTD is in Chembur Mumbai, Mumbai (pincode 400071), near Fci, Nehru Nagar, Maharashtra, and is registered on MahaRERA as P51800029994, per GharKundli's check of MahaRERA records.
How many homes are in SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES has 218 homes in 1 tower registered on MahaRERA, and 43% of them are sold or booked.
When was SAFAL GOLF RESIDENCES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAFAL GOLF RESIDENCES was registered on MahaRERA on 20 July 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SAFAL GOLF RESIDENCES?
No court cases are listed for SAFAL GOLF RESIDENCES on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SAFAL GOLF RESIDENCES?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANGALNATH DEVELOPERS PVT LTD, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAFAL GOLF RESIDENCES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Other projects by MANGALNATH DEVELOPERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.