by HUGES REAL ESTATES DEVELOPERS LLP · Ghatkopar West, MumbaiAlso near Chembur, Bhandup West, Tilak Nagar

Possession date of 49 ELINA: 30 December 2021, moved from 31 December 2019 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009485. Status: Lapsed (registration period ended). 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about 49 ELINA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 49 ELINA has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800005370)

    Reason the builder gave MahaRERA:
    “We have completed the building in all aspects. Certain internal work is pending. Basic essentials like water connection / electricity connection / drainage work / lift work etc. is pending post which we will need to get the requisite NOC’s…” Read the full reason“We have completed the building in all aspects. Certain internal work is pending. Basic essentials like water connection / electricity connection / drainage work / lift work etc. is pending post which we will need to get the requisite NOC’s to apply for occupation. Now we are preparing our file as per requirement to submit as early as possible and hope it will be cleared as early as possible. So, we request the RERA authority to grant Extension for 12 months from the expiration of certificate granted that is 30.12.2020 and obliged.”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: 49 ELINA’s extension records on MahaRERA (P51800009485), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 49 ELINA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009485
Status
Lapsed (registration period ended)
Builder
HUGES REAL ESTATES DEVELOPERS LLP
Location
Ghatkopar West, Mumbai · 400089
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
63
Towers
1
Complaints on MahaRERA
7
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found

Construction progress of 49 ELINA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
49 ELINA100%100%75%20%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 49 ELINA every month.

49 ELINA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Anchor SKY Scrapers (a group of 6 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 9 months); 5 still being built, 2 past the promised date (typically 58 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects.

Read Google reviews of 49 ELINA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

49 ELINA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 49 ELINA

What is the possession date of 49 ELINA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 49 ELINA in Ghatkopar West, Mumbai is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for 49 ELINA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 49 ELINA's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 49 ELINA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "We have completed the building in all aspects. Certain internal work is pending. Basic essentials like water connection / electricity connection / drainage work / lift work etc. is pending post which we will need to get the requisite NOC’s to apply for occupation. Now we are preparing our file as per requirement to submit as early as possible and hope it will be cleared as early as possible. So, we request the RERA authority to grant Extension for 12 months from the expiration of certificate granted that is 30.12.2020 and obliged.".

What is the RERA number of 49 ELINA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 49 ELINA in Ghatkopar West, Mumbai is P51800009485.

Is 49 ELINA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA is registered as P51800009485 and its status is "Lapsed (registration period ended)".

What is the construction status of 49 ELINA?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on 49 ELINA is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does 49 ELINA have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 49 ELINA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA is registered on MahaRERA as P51800009485, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 49 ELINA's possession date changes?

The latest dates are on 49 ELINA's MahaRERA page (P51800009485). GharKundli's Kundli Watch sends a free WhatsApp update on 49 ELINA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 49 ELINA have?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA has one building filed: 49 ELINA with 16 floors.

How big is the land of 49 ELINA?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA stands on 1,452 sq m of land (about 0.4 acres), with 6,911 sq m of sanctioned built-up area.

What is the track record of 49 ELINA's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Anchor SKY Scrapers (a group of 6 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 9 months); 5 still being built, 2 past the promised date (typically 58 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 49 ELINA?

Google Maps has reviews of 49 ELINA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 49 ELINA?

49 ELINA by HUGES REAL ESTATES DEVELOPERS LLP is in Ghatkopar West, Mumbai (pincode 400089), near Chembur, Bhandup West, Tilak Nagar, Maharashtra, and is registered on MahaRERA as P51800009485, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAYOUT ROAD.

How many homes are in 49 ELINA?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA has 63 homes in 1 tower registered on MahaRERA.

When was 49 ELINA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 49 ELINA was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 49 ELINA?

No court cases are listed for 49 ELINA on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of 49 ELINA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HUGES REAL ESTATES DEVELOPERS LLP.