Navkar Girija Sadan
by Navkar Groups Private Limited · Borivali West, MumbaiAlso near Babhai Naka
Possession date of Navkar Girija Sadan: 30 April 2028, moved from 31 December 2018 (108 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800006112, and currently active. Its completion date has moved from December 2018 to April 2028: 108 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Navkar Girija Sadan?
How the possession date of Navkar Girija Sadan has moved
31 December 2018
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT51800009747)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 63.16 % allottees for purpose of extension of RERA registration period of the said project..”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Navkar Girija Sadan’s extension records on MahaRERA (P51800006112), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Navkar Girija Sadan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006112
- Status
- Registered and active
- Builder
- Navkar Groups Private Limited
- Location
- Borivali West, Mumbai · 400092
- Project type
- Others
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- April 2028
- Delay so far
- 108 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Navkar Girija Sadan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Navkar Girija Sadan | 100% | 83% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Navkar Girija Sadan every month.
Navkar Girija Sadan: buildings, flats and land, as filed on MahaRERA
- Buildings: Navkar Girija Sadan (8 floors)
- Land: 344 sq m (about 0.1 acres) · sanctioned built-up 806 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Navkar Groups has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects.
Read Google reviews of Navkar Girija Sadan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Navkar Girija Sadan: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Navkar Girija Sadan
What is the possession date of Navkar Girija Sadan?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Navkar Girija Sadan in Borivali West, Mumbai is 30 April 2028 — 108 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Navkar Girija Sadan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Navkar Girija Sadan's builder has filed on MahaRERA, the official one, is 30 April 2028, already 108 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Navkar Girija Sadan extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 63.16 % allottees for purpose of extension of RERA registration period of the said project..". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Navkar Girija Sadan?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Navkar Girija Sadan in Borivali West, Mumbai is P51800006112.
Is Navkar Girija Sadan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan is registered as P51800006112 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of Navkar Girija Sadan?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Navkar Girija Sadan is 83% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Navkar Girija Sadan have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Navkar Girija Sadan safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan is registered on MahaRERA as P51800006112, its completion date has moved 108 months since registration, 4 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Navkar Girija Sadan's possession date changes?
The latest dates are on Navkar Girija Sadan's MahaRERA page (P51800006112). GharKundli's Kundli Watch sends a free WhatsApp update on Navkar Girija Sadan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Navkar Girija Sadan have?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan has one building filed: Navkar Girija Sadan with 8 floors.
How big is the land of Navkar Girija Sadan?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan stands on 344 sq m of land (about 0.1 acres), with 806 sq m of sanctioned built-up area.
What is the track record of Navkar Girija Sadan's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Groups has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Navkar Girija Sadan?
Google Maps has reviews of Navkar Girija Sadan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Navkar Girija Sadan?
Navkar Girija Sadan by Navkar Groups Private Limited is in Borivali West, Mumbai (pincode 400092), near Babhai Naka, Maharashtra, and is registered on MahaRERA as P51800006112, per GharKundli's check of MahaRERA records.
How many homes are in Navkar Girija Sadan?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan has 21 homes in 1 tower registered on MahaRERA.
When was Navkar Girija Sadan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Navkar Girija Sadan was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Navkar Girija Sadan?
No court cases are listed for Navkar Girija Sadan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Navkar Girija Sadan?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Navkar Groups Private Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Navkar Girija Sadan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400092
- FORTUNE AVIRAHI WING A
- SONI ARCADE, BUILDING NO 2
- Sparkle Umadarshan
- SHRADDHA SKYLINE
- I SPACE URBAN VISTA
- GAURAV GALAXY
- SKYLARK HEIGHTS
- Hiranandani Bluecrest
Other projects by Navkar Groups Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.