SUNFLOWER
by Shree Krishna Developers · Hariniwas, MumbaiAlso near Mulund East, Mulund West, Vile Parle East
Possession: SUNFLOWER is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800006422. Status: Completed. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SUNFLOWER?
How the possession date of SUNFLOWER has moved
31 December 2018
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51800008645)
Reason the builder gave MahaRERA:
“WE HEREBY SAY THAT THIS IS A SRA PROJECT. THE SLUM TENANTS ARE REHABILITATED IN THE NEW BUILDING. AS PER THE APPROVALS THE SALE BUILDING IS OF ABOUT 14 FLOORS, TILL 12TH FLOOR OF THE SAID BUILDING PART O.C HAS BEEN OBTAINED ON 19.01.2019, H…” Read the full reason
“WE HEREBY SAY THAT THIS IS A SRA PROJECT. THE SLUM TENANTS ARE REHABILITATED IN THE NEW BUILDING. AS PER THE APPROVALS THE SALE BUILDING IS OF ABOUT 14 FLOORS, TILL 12TH FLOOR OF THE SAID BUILDING PART O.C HAS BEEN OBTAINED ON 19.01.2019, HOWEVER 13TH AND 14TH FLOOR IS COMPLETED AS PER THE FORM -4 DATED 06.02.2020 ISSUED BY THE ARCHITECT S.S.ASSOCIATES THE SAID STRUCTURE IS FIT FOR OCCUPANCY . THE ALLOTTEES HAVE TAKEN THE POSSESSION OF THEIR RESPECTIVE FLATS AND FURTHER EVEN THE CO-OPERTIVE SOCIETY HAS BEEN FORMED BY THE ALLOTTEES IN 2019. I SAY THAT AS PER THE CONDITIONS OF THE IOA/ CC, TH…”30 June 2022
Revised completion date on MahaRERA
Source: SUNFLOWER’s extension records on MahaRERA (P51800006422), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SUNFLOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006422
- Status
- Completed
- Builder
- Shree Krishna Developers
- Location
- Hariniwas, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- June 2022
- Delay so far
- 42 months
- Homes
- 123
- Towers
- 2
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of SUNFLOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SUNFLOWER | 100% | 100% | 100% | 100% |
| SHRAMIK NAGAR | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUNFLOWER every month.
SUNFLOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: SUNFLOWER (16 floors) · SHRAMIK NAGAR (9 floors)
- Land: 1,789 sq m (about 0.4 acres) · sanctioned built-up 4,557 sq m · recreational space 102 sq m
- Boundaries filed include: SETH RESIDENCY PARK, VASUDEV BALWANT PHADKE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SUNFLOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SUNFLOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SUNFLOWER
What is the possession date of SUNFLOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SUNFLOWER in Hariniwas, Mumbai is 30 June 2022 — 42 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SUNFLOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SUNFLOWER's builder has filed on MahaRERA, the official one, is 30 June 2022, already 42 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SUNFLOWER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER's builder applied to MahaRERA to extend the completion date once: to 31 December 2021, giving the reason "WE HEREBY SAY THAT THIS IS A SRA PROJECT. THE SLUM TENANTS ARE REHABILITATED IN THE NEW BUILDING. AS PER THE APPROVALS THE SALE BUILDING IS OF ABOUT 14 FLOORS, TILL 12TH FLOOR OF THE SAID BUILDING PART O.C HAS BEEN OBTAINED ON 19.01.2019, HOWEVER 13TH AND 14TH FLOOR IS COMPLETED AS PER THE FORM -4 DATED 06.02.2020 ISSUED BY THE ARCHITECT S.S.ASSOCIATES THE SAID STRUCTURE IS FIT FOR OCCUPANCY . THE ALLOTTEES HAVE TAKEN THE POSSESSION OF THEIR RESPECTIVE FLATS AND FURTHER EVEN THE CO-OPERTIVE SOCIETY HAS BEEN FORMED BY THE ALLOTTEES IN 2019. I SAY THAT AS PER THE CONDITIONS OF THE IOA/ CC, TH…".
What is the RERA number of SUNFLOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SUNFLOWER in Hariniwas, Mumbai is P51800006422.
Is SUNFLOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER is registered as P51800006422 and its status is "Completed".
What is the construction status of SUNFLOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SUNFLOWER have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SUNFLOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER is registered on MahaRERA as P51800006422, its MahaRERA status is "Completed", its completion date has moved 42 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SUNFLOWER's possession date changes?
The latest dates are on SUNFLOWER's MahaRERA page (P51800006422). GharKundli's Kundli Watch sends a free WhatsApp update on SUNFLOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SUNFLOWER have?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER has 2 buildings filed: SUNFLOWER with 16 floors; SHRAMIK NAGAR with 9 floors.
How big is the land of SUNFLOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER stands on 1,789 sq m of land (about 0.4 acres), with 4,557 sq m of sanctioned built-up area and 102 sq m of recreational open space.
Where can I read reviews of SUNFLOWER?
Google Maps has reviews of SUNFLOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SUNFLOWER?
SUNFLOWER by Shree Krishna Developers is in Hariniwas, Mumbai (pincode 400081), near Mulund East, Mulund West, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800006422, per GharKundli's check of MahaRERA records. Its boundaries filed there include SETH RESIDENCY PARK, VASUDEV BALWANT PHADKE ROAD.
How many homes are in SUNFLOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER has 123 homes in 2 towers registered on MahaRERA.
When was SUNFLOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SUNFLOWER was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SUNFLOWER?
No court cases are listed for SUNFLOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SUNFLOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Krishna Developers, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SUNFLOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla
- SUDHANSHU HEIGHTS
- Saptashringi
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- Kanakdhara
- Privilon
- Valentina CHS
Other projects by Shree Krishna Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.