Skip to content
GharKundli

GIRDHARI HEIGHTS

by SHREE KRISHNA DEVELOPERS · Virar East, PalgharAlso near Virar West

Possession: GIRDHARI HEIGHTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000029298. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GIRDHARI HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GIRDHARI HEIGHTS has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT99000025978)

    Reason the builder gave MahaRERA:
    “We would like to inform you that the period 2021-2022 was not favourable for real-estate sectors due to the Covid-19 pandemic, frequent lockdown, shortage of building materials and shortage of skilled workers and construction project work w…” Read the full reason“We would like to inform you that the period 2021-2022 was not favourable for real-estate sectors due to the Covid-19 pandemic, frequent lockdown, shortage of building materials and shortage of skilled workers and construction project work were largely affected and project was not ale to complete in time. And we expect some more delay in getting occupancy certificate(OC) from VVCMC. So we request you to extend the Therefore, we request you extend the project completion date up to 30/12/2025”
  3. 30 April 2026

    Extended at the builder's request (MahaRERA application EA20022619930)

    Reason the builder gave MahaRERA: “We have availed Occupancy certificate from VVCMC dated 13/01/2026. Since OC dated is beyond project completion date (30/12/2025) we are Appling for the extension project.”

Source: GIRDHARI HEIGHTS’s extension records on MahaRERA (P99000029298), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GIRDHARI HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000029298
Status
Completed
Builder
SHREE KRISHNA DEVELOPERS
Location
Virar East, Palghar · 401305
Project type
Residential / Group Housing
Registered on
18 May 2021
Completion date at registration
December 2024
Latest completion date
April 2026
Delay so far
16 months
Homes
67
Sold or booked
66%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Construction progress of GIRDHARI HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GIRDHARI HEIGHTS, BUILDING NO 5100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • GIRDHARI HEIGHTS, BUILDING NO 5: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GIRDHARI HEIGHTS every month.

GIRDHARI HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: GIRDHARI HEIGHTS, BUILDING NO 5 (9 floors, 67 units)
  • Car parking: 1 covered, 16 open
  • Land: 1,339 sq m (about 0.3 acres) · sanctioned built-up 4,322 sq m
  • Boundaries filed include: Exiting Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Shree Krishna Developers has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 8 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of GIRDHARI HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GIRDHARI HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GIRDHARI HEIGHTS

What is the possession date of GIRDHARI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GIRDHARI HEIGHTS in Virar East, Palghar is 30 April 2026 — 16 months later than 31 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GIRDHARI HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GIRDHARI HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2026, already 16 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GIRDHARI HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "We would like to inform you that the period 2021-2022 was not favourable for real-estate sectors due to the Covid-19 pandemic, frequent lockdown, shortage of building materials and shortage of skilled workers and construction project work were largely affected and project was not ale to complete in time. And we expect some more delay in getting occupancy certificate(OC) from VVCMC. So we request you to extend the Therefore, we request you extend the project completion date up to 30/12/2025"; to 30 April 2026, giving the reason "We have availed Occupancy certificate from VVCMC dated 13/01/2026. Since OC dated is beyond project completion date (30/12/2025) we are Appling for the extension project.".

What is the RERA number of GIRDHARI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GIRDHARI HEIGHTS in Virar East, Palghar is P99000029298.

Is GIRDHARI HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS is registered as P99000029298 and its status is "Completed".

What is the construction status of GIRDHARI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on GIRDHARI HEIGHTS, BUILDING NO 5 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GIRDHARI HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GIRDHARI HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS is registered on MahaRERA as P99000029298, its MahaRERA status is "Completed", its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GIRDHARI HEIGHTS's possession date changes?

The latest dates are on GIRDHARI HEIGHTS's MahaRERA page (P99000029298). GharKundli's Kundli Watch sends a free WhatsApp update on GIRDHARI HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GIRDHARI HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS has one building filed: GIRDHARI HEIGHTS, BUILDING NO 5 with 9 floors and 67 units.

How much parking does GIRDHARI HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 16 open car parking spaces for GIRDHARI HEIGHTS.

How big is the land of GIRDHARI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS stands on 1,339 sq m of land (about 0.3 acres), with 4,322 sq m of sanctioned built-up area.

What is the track record of GIRDHARI HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krishna Developers has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 8 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GIRDHARI HEIGHTS?

Google Maps has reviews of GIRDHARI HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GIRDHARI HEIGHTS?

GIRDHARI HEIGHTS by SHREE KRISHNA DEVELOPERS is in Virar East, Palghar (pincode 401305), near Virar West, Maharashtra, and is registered on MahaRERA as P99000029298, per GharKundli's check of MahaRERA records. Its boundaries filed there include Exiting Road.

How many homes are in GIRDHARI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS has 67 homes in 1 tower registered on MahaRERA, and 66% of them are sold or booked.

When was GIRDHARI HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GIRDHARI HEIGHTS was registered on MahaRERA on 18 May 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on GIRDHARI HEIGHTS?

No court cases are listed for GIRDHARI HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GIRDHARI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE KRISHNA DEVELOPERS, which has 11 other projects registered on MahaRERA.

Other projects in pincode 401305

All 88 projects in Virar East (401305) →

Other projects by SHREE KRISHNA DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.