NANA HEIGHTS
by SHREE SWAMI SAMARTH DEVELOPERS · Kopari, Virar East, PalgharAlso near Virar West
Possession date of NANA HEIGHTS: 31 July 2028, moved from 31 May 2026 (22 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000049128, and currently active. Its completion date has moved from May 2026 to July 2028: 22 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about NANA HEIGHTS?
How the possession date of NANA HEIGHTS has moved
31 May 2026
Completion date given when the project was registered
31 March 2028
Extended at the builder's request (MahaRERA application EA29052621145)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…”31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: NANA HEIGHTS’s extension records on MahaRERA (P99000049128), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NANA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000049128
- Status
- Registered and active
- Builder
- SHREE SWAMI SAMARTH DEVELOPERS
- Location
- Kopari, Virar East, Palghar · 401305
- Project type
- Residential / Group Housing
- Registered on
- 1 Feb 2023
- Completion date at registration
- May 2026
- Latest completion date
- July 2028
- Delay so far
- 22 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 104
- Sold or booked
- 52%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of NANA HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NANA HEIGHTS | 100% | 100% | 30% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- NANA HEIGHTS: covers 8 floors
Latest CC order on MahaRERA: dated 15/07/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NANA HEIGHTS every month.
NANA HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: NANA HEIGHTS (8 floors, 104 units)
- Car parking: 17 covered
- Land: 2,100 sq m (about 0.5 acres) · sanctioned built-up 5,014 sq m
- Boundaries filed include: KOPARI GAON ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NANA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NANA HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NANA HEIGHTS
What is the possession date of NANA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NANA HEIGHTS in Kopari, Virar East, Palghar is 31 July 2028 — 22 months later than 31 May 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for NANA HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NANA HEIGHTS's builder has filed on MahaRERA, the official one, is 31 July 2028, already 22 months later than the 31 May 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NANA HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 March 2028, giving the reason "Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of NANA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NANA HEIGHTS in Kopari, Virar East, Palghar is P99000049128.
Is NANA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS is registered as P99000049128 and its status is "Registered and active".
What is the construction status of NANA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NANA HEIGHTS is 100% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does NANA HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is NANA HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS is registered on MahaRERA as P99000049128, its completion date has moved 22 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NANA HEIGHTS's possession date changes?
The latest dates are on NANA HEIGHTS's MahaRERA page (P99000049128). GharKundli's Kundli Watch sends a free WhatsApp update on NANA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NANA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS has one building filed: NANA HEIGHTS with 8 floors and 104 units.
How much parking does NANA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 17 covered car parking spaces for NANA HEIGHTS.
How big is the land of NANA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS stands on 2,100 sq m of land (about 0.5 acres), with 5,014 sq m of sanctioned built-up area.
Where can I read reviews of NANA HEIGHTS?
Google Maps has reviews of NANA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NANA HEIGHTS?
NANA HEIGHTS by SHREE SWAMI SAMARTH DEVELOPERS is in Kopari, Virar East, Palghar (pincode 401305), near Virar West, Maharashtra, and is registered on MahaRERA as P99000049128, per GharKundli's check of MahaRERA records. Its boundaries filed there include KOPARI GAON ROAD.
How many homes are in NANA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS has 104 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.
When was NANA HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NANA HEIGHTS was registered on MahaRERA on 1 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on NANA HEIGHTS?
No court cases are listed for NANA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of NANA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SWAMI SAMARTH DEVELOPERS, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NANA HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in pincode 401305
- Swastik Epitome Building 2 Phase I Ground to 7 floors
- Swastik Epitome Building 2 Phase II 8 to 14 floors
- SIDDHIVINAYAK CROWN
- GIRDHARI HEIGHTS
- VIRAT CO-OP HOUSING SOCIETY
- MJV CORPORATION
- SHREE SWAMI SAMARTH NX
- SHIVNERI
Other projects by SHREE SWAMI SAMARTH DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.