HARI KRISHNA PHASE IV
by KBC GLOBAL LIMITED · Deolali, Nashik
Possession date of HARI KRISHNA PHASE IV: 31 December 2025, moved from 28 November 2023 (25 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51600020324. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about HARI KRISHNA PHASE IV?
How the possession date of HARI KRISHNA PHASE IV has moved
28 November 2023
Completion date given when the project was registered
27 November 2024
Extended at the builder's request (MahaRERA application EXT51600017970)
Reason the builder gave MahaRERA: “Due to some unavoidable reasons construction is being delayed”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51600027545)
Reason the builder gave MahaRERA: “The construction work is delayed due to unavoidable reason”
Source: HARI KRISHNA PHASE IV’s extension records on MahaRERA (P51600020324), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HARI KRISHNA PHASE IV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600020324
- Status
- Lapsed (registration period ended)
- Builder
- KBC GLOBAL LIMITED
- Location
- Deolali, Nashik · 422101
- Project type
- Others
- Registered on
- 5 Apr 2019
- Completion date at registration
- November 2023
- Latest completion date
- December 2025
- Delay so far
- 25 months
- Homes
- 63
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 19
HARI KRISHNA PHASE IV: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A (9 floors)
- Land: 2,600 sq m (about 0.6 acres) · sanctioned built-up 2,465 sq m · recreational space 250 sq m
The builder’s record and reviews
KBC Global has 20 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 60 months); 6 lapsed. 16 complaints on MahaRERA across 6 projects.
Read Google reviews of HARI KRISHNA PHASE IV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HARI KRISHNA PHASE IV: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HARI KRISHNA PHASE IV
What is the possession date of HARI KRISHNA PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HARI KRISHNA PHASE IV in Deolali, Nashik is 31 December 2025 — 25 months later than 28 November 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for HARI KRISHNA PHASE IV?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HARI KRISHNA PHASE IV's builder has filed on MahaRERA, the official one, is 31 December 2025, already 25 months later than the 28 November 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HARI KRISHNA PHASE IV extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV's builder applied to MahaRERA to extend the completion date 2 times: to 27 November 2024, giving the reason "Due to some unavoidable reasons construction is being delayed"; to 31 December 2025, giving the reason "The construction work is delayed due to unavoidable reason".
What is the RERA number of HARI KRISHNA PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HARI KRISHNA PHASE IV in Deolali, Nashik is P51600020324.
Is HARI KRISHNA PHASE IV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV is registered as P51600020324 and its status is "Lapsed (registration period ended)".
What is the construction status of HARI KRISHNA PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.
Does HARI KRISHNA PHASE IV have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HARI KRISHNA PHASE IV safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV is registered on MahaRERA as P51600020324, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 25 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HARI KRISHNA PHASE IV's possession date changes?
The latest dates are on HARI KRISHNA PHASE IV's MahaRERA page (P51600020324). GharKundli's Kundli Watch sends a free WhatsApp update on HARI KRISHNA PHASE IV every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HARI KRISHNA PHASE IV have?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV has one building filed: Building A with 9 floors.
How big is the land of HARI KRISHNA PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV stands on 2,600 sq m of land (about 0.6 acres), with 2,465 sq m of sanctioned built-up area and 250 sq m of recreational open space.
What is the track record of HARI KRISHNA PHASE IV's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), KBC Global has 20 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 60 months); 6 lapsed. 16 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of HARI KRISHNA PHASE IV?
Google Maps has reviews of HARI KRISHNA PHASE IV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HARI KRISHNA PHASE IV?
HARI KRISHNA PHASE IV by KBC GLOBAL LIMITED is in Deolali, Nashik (pincode 422101), Maharashtra, and is registered on MahaRERA as P51600020324, per GharKundli's check of MahaRERA records.
How many homes are in HARI KRISHNA PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV has 63 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was HARI KRISHNA PHASE IV registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI KRISHNA PHASE IV was registered on MahaRERA on 5 April 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on HARI KRISHNA PHASE IV?
No court cases are listed for HARI KRISHNA PHASE IV on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of HARI KRISHNA PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KBC GLOBAL LIMITED, which has 19 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of HARI KRISHNA PHASE IV
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Deolali
All 178 projects in Nashik Road (422101) →Other projects by KBC GLOBAL LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.