HARI BHAKTI
by KBC GLOBAL LIMITED · Datta Mandir road, NashikAlso near Nashik Road, Deolali Shiwar, Opp Gopal Nagar
Possession date of HARI BHAKTI: 31 December 2024, moved from 30 June 2021 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51600000585. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about HARI BHAKTI?
How the possession date of HARI BHAKTI has moved
30 June 2021
Completion date given when the project was registered
29 June 2022
Extended at the builder's request (MahaRERA application EXT51600009686)
Reason the builder gave MahaRERA: “Due to strict precautionary norms of government during this pandemic the constitution is getting delayed .hence extension is requested”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51600013618)
Reason the builder gave MahaRERA: “Work is being delayed due to unavoidable reasons”
Source: HARI BHAKTI’s extension records on MahaRERA (P51600000585), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HARI BHAKTI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600000585
- Status
- Lapsed (registration period ended)
- Builder
- KBC GLOBAL LIMITED
- Location
- Datta Mandir road, Nashik · 422101
- Project type
- Others
- Registered on
- 18 Jul 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2024
- Delay so far
- 42 months
- Homes
- 115
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 19
Construction progress of HARI BHAKTI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
| B | 0% | 100% | 80% | 0% |
| C | 100% | 100% | 90% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HARI BHAKTI every month.
HARI BHAKTI: buildings, flats and land, as filed on MahaRERA
- Buildings: A (7 floors) · B (14 floors) · C (14 floors)
- Land: 5,066 sq m (about 1.3 acres) · sanctioned built-up 5,408 sq m · recreational space 507 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
KBC Global has 20 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 60 months); 6 lapsed. 16 complaints on MahaRERA across 6 projects.
Read Google reviews of HARI BHAKTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HARI BHAKTI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HARI BHAKTI
What is the possession date of HARI BHAKTI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HARI BHAKTI in Datta Mandir road, Nashik is 31 December 2024 — 42 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for HARI BHAKTI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HARI BHAKTI's builder has filed on MahaRERA, the official one, is 31 December 2024, already 42 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HARI BHAKTI extended?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2022, giving the reason "Due to strict precautionary norms of government during this pandemic the constitution is getting delayed .hence extension is requested"; to 31 December 2024, giving the reason "Work is being delayed due to unavoidable reasons".
What is the RERA number of HARI BHAKTI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HARI BHAKTI in Datta Mandir road, Nashik is P51600000585.
Is HARI BHAKTI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI is registered as P51600000585 and its status is "Lapsed (registration period ended)".
What is the construction status of HARI BHAKTI?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does HARI BHAKTI have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HARI BHAKTI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI is registered on MahaRERA as P51600000585, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HARI BHAKTI's possession date changes?
The latest dates are on HARI BHAKTI's MahaRERA page (P51600000585). GharKundli's Kundli Watch sends a free WhatsApp update on HARI BHAKTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HARI BHAKTI have?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI has 3 buildings filed: A with 7 floors; B with 14 floors; C with 14 floors.
How big is the land of HARI BHAKTI?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI stands on 5,066 sq m of land (about 1.3 acres), with 5,408 sq m of sanctioned built-up area and 507 sq m of recreational open space.
What is the track record of HARI BHAKTI's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), KBC Global has 20 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 60 months); 6 lapsed. 16 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of HARI BHAKTI?
Google Maps has reviews of HARI BHAKTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HARI BHAKTI?
HARI BHAKTI by KBC GLOBAL LIMITED is in Datta Mandir road, Nashik (pincode 422101), near Nashik Road, Deolali Shiwar, Opp Gopal Nagar, Maharashtra, and is registered on MahaRERA as P51600000585, per GharKundli's check of MahaRERA records.
How many homes are in HARI BHAKTI?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI has 115 homes in 3 towers registered on MahaRERA.
When was HARI BHAKTI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HARI BHAKTI was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HARI BHAKTI?
No court cases are listed for HARI BHAKTI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of HARI BHAKTI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KBC GLOBAL LIMITED, which has 19 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of HARI BHAKTI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHREE VISHVA
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- Quillion Residencies at Quillion Park - Phase 2
- SHIV KUNJ
- SARA SERENITY APARTMENT
Other projects by KBC GLOBAL LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.