HARI AAKRUTI PHASE II
by KBC GLOBAL LIMITED · Dwarka Corner, NashikAlso near Ojhar A.F. Stn
Possession date of HARI AAKRUTI PHASE II: 31 July 2026, moved from 30 June 2021 (57 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51600014676. Status: Lapsed (registration period ended). Its completion date has moved from June 2021 to July 2026: 57 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about HARI AAKRUTI PHASE II?
How the possession date of HARI AAKRUTI PHASE II has moved
30 June 2021
Completion date given when the project was registered
30 March 2022
Extended at the builder's request (MahaRERA application EXT51600010565)
Reason the builder gave MahaRERA: “There has been delay in construction because of unavoidable problems faced due to pandemic of COVID-19. Hence we hereby request you to allow the extension of a period of 12 months”
28 March 2024
Extended at the builder's request (MahaRERA application EXT51600017547)
Reason the builder gave MahaRERA: “due to unavoidable reasons the construction has been delayed”
31 March 2026
Extended at the builder's request (MahaRERA application EXT51600024615)
Reason the builder gave MahaRERA: “Construction is being delayed due to unavoidable reason”
31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HARI AAKRUTI PHASE II’s extension records on MahaRERA (P51600014676), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HARI AAKRUTI PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600014676
- Status
- Lapsed (registration period ended)
- Builder
- KBC GLOBAL LIMITED
- Location
- Dwarka Corner, Nashik · 422011
- Project type
- Others
- Registered on
- 20 Dec 2017
- Completion date at registration
- June 2021
- Latest completion date
- July 2026
- Delay so far
- 57 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 25
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 19
Construction progress of HARI AAKRUTI PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HARI AAKRUTI PHASE II | 100% | 100% | 80% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HARI AAKRUTI PHASE II every month.
HARI AAKRUTI PHASE II: buildings, flats and land, as filed on MahaRERA
- Buildings: HARI AAKRUTI PHASE II (11 floors)
- Land: 1,808 sq m (about 0.4 acres) · sanctioned built-up 3,227 sq m
The builder’s record and reviews
KBC Global has 20 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 60 months); 6 lapsed. 16 complaints on MahaRERA across 6 projects.
Read Google reviews of HARI AAKRUTI PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HARI AAKRUTI PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HARI AAKRUTI PHASE II
What is the possession date of HARI AAKRUTI PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HARI AAKRUTI PHASE II in Dwarka Corner, Nashik is 31 July 2026 — 57 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for HARI AAKRUTI PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HARI AAKRUTI PHASE II's builder has filed on MahaRERA, the official one, is 31 July 2026, already 57 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HARI AAKRUTI PHASE II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2022, giving the reason "There has been delay in construction because of unavoidable problems faced due to pandemic of COVID-19. Hence we hereby request you to allow the extension of a period of 12 months"; to 28 March 2024, giving the reason "due to unavoidable reasons the construction has been delayed"; to 31 March 2026, giving the reason "Construction is being delayed due to unavoidable reason". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HARI AAKRUTI PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HARI AAKRUTI PHASE II in Dwarka Corner, Nashik is P51600014676.
Is HARI AAKRUTI PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II is registered as P51600014676 and its status is "Lapsed (registration period ended)".
What is the construction status of HARI AAKRUTI PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on HARI AAKRUTI PHASE II is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does HARI AAKRUTI PHASE II have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HARI AAKRUTI PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II is registered on MahaRERA as P51600014676, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 57 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HARI AAKRUTI PHASE II's possession date changes?
The latest dates are on HARI AAKRUTI PHASE II's MahaRERA page (P51600014676). GharKundli's Kundli Watch sends a free WhatsApp update on HARI AAKRUTI PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HARI AAKRUTI PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II has one building filed: HARI AAKRUTI PHASE II with 11 floors.
How big is the land of HARI AAKRUTI PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II stands on 1,808 sq m of land (about 0.4 acres), with 3,227 sq m of sanctioned built-up area.
What is the track record of HARI AAKRUTI PHASE II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), KBC Global has 20 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 60 months); 6 lapsed. 16 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of HARI AAKRUTI PHASE II?
Google Maps has reviews of HARI AAKRUTI PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HARI AAKRUTI PHASE II?
HARI AAKRUTI PHASE II by KBC GLOBAL LIMITED is in Dwarka Corner, Nashik (pincode 422011), near Ojhar A.F. Stn, Maharashtra, and is registered on MahaRERA as P51600014676, per GharKundli's check of MahaRERA records.
How many homes are in HARI AAKRUTI PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II has 25 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was HARI AAKRUTI PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI AAKRUTI PHASE II was registered on MahaRERA on 20 December 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HARI AAKRUTI PHASE II?
No court cases are listed for HARI AAKRUTI PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of HARI AAKRUTI PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KBC GLOBAL LIMITED, which has 19 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of HARI AAKRUTI PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in pincode 422011
- AVANEESH
- OLIVE GARDEN
- GURUSIDDHI KRUPA
- Ace Aria
- EVA LUXURIA - ROW HOUSE
- Ashiyana Luxuria II
- Vraj Darshan
- Fortunes Emerald Park
Other projects by KBC GLOBAL LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.