AMAZON PARK BUILDING NO 2 - WING C

by R.J. CONSTRUCTIONS · Borivali West, MumbaiAlso near I C Colony, Kandivali, Vile Parle East

Possession: AMAZON PARK BUILDING NO 2 - WING C is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002956. Status: Completed. 14 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AMAZON PARK BUILDING NO 2 - WING C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AMAZON PARK BUILDING NO 2 - WING C has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800010057)

    Reason the builder gave MahaRERA: “Due to Pandemic of Covid 19 the construction activity was stopped from March'2020 and after unlock there was non availability of Labour and Building Material because of that the work was slow down.”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800013255)

    Reason the builder gave MahaRERA: “We have already completed 95% of the work and are awaiting certain permissions. We will apply for Occupation Certificate once we received those permissions. please grant us 6 months Extension.”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800017785)

    Reason the builder gave MahaRERA: “The Fire NOC required for obtaining Occupation Certificate is delayed due to some technical reason in the layout”
  5. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51800024604)

    Reason the builder gave MahaRERA: “The Construction activity of the Project is 100% completed except the Installation of Mechanical Parking. The Mechanical Parking work is in progress which is time consuming process.”

Source: AMAZON PARK BUILDING NO 2 - WING C’s extension records on MahaRERA (P51800002956), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AMAZON PARK BUILDING NO 2 - WING C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 14 complaints and 2 court cases, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002956
Status
Completed
Builder
R.J. CONSTRUCTIONS
Location
Borivali West, Mumbai · 400103
Project type
Residential / Group Housing
Registered on
4 Aug 2017
Completion date at registration
June 2021
Latest completion date
March 2025
Delay so far
45 months
Homes
22
Towers
1
Complaints on MahaRERA
14
Court cases listed
2
Appeals at the tribunal
14
Title report on file
Not found

Construction progress of AMAZON PARK BUILDING NO 2 - WING C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AMAZON PARK BUILDING NO 2 - WING C0%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AMAZON PARK BUILDING NO 2 - WING C every month.

AMAZON PARK BUILDING NO 2 - WING C: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sunit Enterprise (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 29 months); 1 still being built, none past the promised date yet. 22 complaints on MahaRERA across 2 projects.

Read Google reviews of AMAZON PARK BUILDING NO 2 - WING C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AMAZON PARK BUILDING NO 2 - WING C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AMAZON PARK BUILDING NO 2 - WING C

What is the possession date of AMAZON PARK BUILDING NO 2 - WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AMAZON PARK BUILDING NO 2 - WING C in Borivali West, Mumbai is 31 March 2025 — 45 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AMAZON PARK BUILDING NO 2 - WING C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AMAZON PARK BUILDING NO 2 - WING C's builder has filed on MahaRERA, the official one, is 31 March 2025, already 45 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AMAZON PARK BUILDING NO 2 - WING C extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "Due to Pandemic of Covid 19 the construction activity was stopped from March'2020 and after unlock there was non availability of Labour and Building Material because of that the work was slow down."; to 30 June 2023, giving the reason "We have already completed 95% of the work and are awaiting certain permissions. We will apply for Occupation Certificate once we received those permissions. please grant us 6 months Extension."; to 30 June 2024, giving the reason "The Fire NOC required for obtaining Occupation Certificate is delayed due to some technical reason in the layout"; to 31 March 2025, giving the reason "The Construction activity of the Project is 100% completed except the Installation of Mechanical Parking. The Mechanical Parking work is in progress which is time consuming process.".

What is the RERA number of AMAZON PARK BUILDING NO 2 - WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AMAZON PARK BUILDING NO 2 - WING C in Borivali West, Mumbai is P51800002956.

Is AMAZON PARK BUILDING NO 2 - WING C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C is registered as P51800002956 and its status is "Completed".

What is the construction status of AMAZON PARK BUILDING NO 2 - WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C's status on MahaRERA is "Completed". As filed by the builder, slab work on AMAZON PARK BUILDING NO 2 - WING C is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AMAZON PARK BUILDING NO 2 - WING C have complaints on MahaRERA?

14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AMAZON PARK BUILDING NO 2 - WING C safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C is registered on MahaRERA as P51800002956, its MahaRERA status is "Completed", its completion date has moved 45 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AMAZON PARK BUILDING NO 2 - WING C's possession date changes?

The latest dates are on AMAZON PARK BUILDING NO 2 - WING C's MahaRERA page (P51800002956). GharKundli's Kundli Watch sends a free WhatsApp update on AMAZON PARK BUILDING NO 2 - WING C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AMAZON PARK BUILDING NO 2 - WING C have?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C has one building filed: AMAZON PARK BUILDING NO 2 - WING C with 18 floors.

How big is the land of AMAZON PARK BUILDING NO 2 - WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C stands on 250 sq m of land (about 0.1 acres), with 2,371 sq m of sanctioned built-up area and 1,843 sq m of recreational open space.

What is the track record of AMAZON PARK BUILDING NO 2 - WING C's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunit Enterprise (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 29 months); 1 still being built, none past the promised date yet. 22 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AMAZON PARK BUILDING NO 2 - WING C?

Google Maps has reviews of AMAZON PARK BUILDING NO 2 - WING C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AMAZON PARK BUILDING NO 2 - WING C?

AMAZON PARK BUILDING NO 2 - WING C by R.J. CONSTRUCTIONS is in Borivali West, Mumbai (pincode 400103), near I C Colony, Kandivali, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800002956, per GharKundli's check of MahaRERA records.

How many homes are in AMAZON PARK BUILDING NO 2 - WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C has 22 homes in 1 tower registered on MahaRERA.

When was AMAZON PARK BUILDING NO 2 - WING C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AMAZON PARK BUILDING NO 2 - WING C was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AMAZON PARK BUILDING NO 2 - WING C?

2 court cases are listed for AMAZON PARK BUILDING NO 2 - WING C on MahaRERA, and 14 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AMAZON PARK BUILDING NO 2 - WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is R.J. CONSTRUCTIONS.

Other projects in Borivali West

All 93 projects in Borivali West (400103) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.