Tridev Balaji Apartment
by TRIDEV REALTY AND CONSTRUCTION PVT LTD · Mulund West, Mumbai 400080Also near Bhandup West, Sion, Off DmartRegistered on MahaRERA as “BALAJI APARTMENT”
What’s in the report? →Possession date of Tridev Balaji Apartment (MahaRERA P51800011083): 30 April 2027, moved from 30 December 2023 (36 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011083, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800011083, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Tridev Balaji Apartment?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Tridev Balaji Apartment has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018789)
Reason the builder gave MahaRERA:
“RCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th Novem…” Read the full reason
“RCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th November-2023. In the light of the abovementioned reasons, we seek extension of one year for due date of completion of the project i.e. 29-Dec-2024. Self Declaration dated 13.01.2024 for extension of due date for the said project is enclosed herewith. Scan copy of Original Notarized Affidavit cum declaration on Rs. 100/- stamp paper in Form B with extension da…”31 December 2026
Extended at the builder's request (MahaRERA application EXT51800027908)
Reason the builder gave MahaRERA:
“Construction of the building is completed at around 99% as evidenced from the latest Architect Certificate for the quarter ended 31-Dec-2025 as uploaded. In light of one Car Lift work, obtaining of the Occupation Certificate (OC) and relate…” Read the full reason
“Construction of the building is completed at around 99% as evidenced from the latest Architect Certificate for the quarter ended 31-Dec-2025 as uploaded. In light of one Car Lift work, obtaining of the Occupation Certificate (OC) and related compliances we seek extension of the project completion date till 31-12-2026. We request you to kindly grant extension of the project completion date till 31-12-2026. More than 51% Allottee's consent (Other than Existing Members) on promoter letter head duly stamped and signed in format B Mentioning Proposed Extension Date (31-Dec-2026) is attached. For…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Tridev Balaji Apartment’s extension records on MahaRERA (P51800011083), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tridev Balaji Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011083
- Status
- Registered and active
- Builder
- TRIDEV REALTY AND CONSTRUCTION PVT LTD
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Tridev Balaji Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BALAJI APARTMENT | 100% | 100% | 100% | 99% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tridev Balaji Apartment every 1–2 months.
Tridev Balaji Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: BALAJI APARTMENT (27 floors)
- Land: 1,672 sq m (about 0.4 acres) · sanctioned built-up 3,950 sq m · recreational space 219 sq m
- Boundaries filed include: NAHUR ROAD, LALA DEVIDAYAL ROAD
- Land, as filed: 1097
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects.
Read Google reviews of Tridev Balaji Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tridev Balaji Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Tridev Balaji Apartment
What is the possession date of Tridev Balaji Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tridev Balaji Apartment in Mulund West, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Tridev Balaji Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tridev Balaji Apartment's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tridev Balaji Apartment extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "RCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th November-2023. In the light of the abovementioned reasons, we seek extension of one year for due date of completion of the project i.e. 29-Dec-2024. Self Declaration dated 13.01.2024 for extension of due date for the said project is enclosed herewith. Scan copy of Original Notarized Affidavit cum declaration on Rs. 100/- stamp paper in Form B with extension da…"; to 31 December 2026, giving the reason "Construction of the building is completed at around 99% as evidenced from the latest Architect Certificate for the quarter ended 31-Dec-2025 as uploaded. In light of one Car Lift work, obtaining of the Occupation Certificate (OC) and related compliances we seek extension of the project completion date till 31-12-2026. We request you to kindly grant extension of the project completion date till 31-12-2026. More than 51% Allottee's consent (Other than Existing Members) on promoter letter head duly stamped and signed in format B Mentioning Proposed Extension Date (31-Dec-2026) is attached. For…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Tridev Balaji Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tridev Balaji Apartment in Mulund West, Mumbai is P51800011083.
Is Tridev Balaji Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment is registered as P51800011083 and its status is "Registered and active".
What is the current construction status of Tridev Balaji Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BALAJI APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Tridev Balaji Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Tridev Balaji Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment is registered on MahaRERA as P51800011083, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Tridev Balaji Apartment?
Tridev Balaji Apartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Tridev Balaji Apartment?
For a flat in Tridev Balaji Apartment (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Tridev Balaji Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Tridev Balaji Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tridev Balaji Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Tridev Balaji Apartment's possession date changes?
The latest dates are on Tridev Balaji Apartment's MahaRERA page (P51800011083). GharKundli's Kundli Watch sends a free WhatsApp update on Tridev Balaji Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tridev Balaji Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment has one building filed: BALAJI APARTMENT with 27 floors.
How big is the land of Tridev Balaji Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment stands on 1,672 sq m of land (about 0.4 acres), with 3,950 sq m of sanctioned built-up area and 219 sq m of recreational open space.
What is the track record of Tridev Balaji Apartment's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Tridev Balaji Apartment?
Google Maps has reviews of Tridev Balaji Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Tridev Balaji Apartment?
Tridev Balaji Apartment by TRIDEV REALTY AND CONSTRUCTION PVT LTD is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Sion, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800011083, per GharKundli's check of MahaRERA records. Its boundaries filed there include NAHUR ROAD, LALA DEVIDAYAL ROAD. Its land is filed as 1097. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
When was Tridev Balaji Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Balaji Apartment was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Tridev Balaji Apartment have any legal issues or court cases?
No court cases are listed for Tridev Balaji Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Tridev Balaji Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TRIDEV REALTY AND CONSTRUCTION PVT LTD, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tridev Balaji Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Old Hemant Villa Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Other projects by TRIDEV REALTY AND CONSTRUCTION PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.