by TRIDEV REALTY AND CONSTRUCTION PVT LTD · Mulund West, Mumbai 400080Also near Bhandup West, Chembur West, Nahur

What’s in the report? →

Possession date of Tridev Anubhav (MahaRERA P51800011760): 31 December 2026, moved from 30 December 2023 (36 months later). It has 84 homes (1 BHK, 2 BHK and 3 BHK, 527–891 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011760, and currently active.

Source: MahaRERA website — records for P51800011760, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Tridev Anubhav?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Tridev Anubhav has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018453)

    Reason the builder gave MahaRERA:
    “RCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th Novem…” Read the full reason“RCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th November-2023. In Light of the same we, M/s. Tridev Realty & Construction Private Limited Developer of the aforesaid project seek extension of one year for due date of completion of the project that is 29-Dec-2024. Self Declaration dated 25.12.2023 for extension of due date for the project “Tridev Anubhav" registered with MahaRERA vide registration Number P518…”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800028009)

    Reason the builder gave MahaRERA:
    “More than 90% Construction work of the said project is completed as evidences by the latest Architect Certificate dated 05-04-2025. Other pending work viz. Tower Parking, C P Fitting work, Wires and Switches is on-going. For Completion of t…” Read the full reason“More than 90% Construction work of the said project is completed as evidences by the latest Architect Certificate dated 05-04-2025. Other pending work viz. Tower Parking, C P Fitting work, Wires and Switches is on-going. For Completion of the said pending work and obtaining of OC and other compliances we seek extension of the project completion date up-to 31-12-2025. We have duly complied and updated and corrected the consent table other than existing members with stamp and signature of promoter on each page as annexed herein below. We request you to kindly approve the project completion da…”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA27022620037)

    Reason the builder gave MahaRERA:
    “More than 95% Construction work of the said project is completed as evidenced by the latest Architect Certificate dated 07-04-2026. Other pending work viz. Tower Parking, Part of C P Fitting work, Wires and Switches is on-going. For Complet…” Read the full reason“More than 95% Construction work of the said project is completed as evidenced by the latest Architect Certificate dated 07-04-2026. Other pending work viz. Tower Parking, Part of C P Fitting work, Wires and Switches is on-going. For Completion of the said pending work and obtaining of OC and other compliances we seek extension of the project completion date up-to 31-12-2026. Consent table in Format B other than existing members with stamp and signature of promoter on each page as annexed herein below. In light of the same we request you to kindly approve the project completion date up-to 31…”

Source: Tridev Anubhav’s extension records on MahaRERA (P51800011760), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Tridev Anubhav

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011760
Status
Registered and active
Builder
TRIDEV REALTY AND CONSTRUCTION PVT LTD
Location
Mulund West, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2023
Latest completion date
December 2026
Delay so far
36 months
Homes
84
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Tridev Anubhav, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ANUBHAV CO-OP HSG SOC LTD100%100%100%81.25%

Commencement certificate (CC), as filed on MahaRERA

  • ANUBHAV CO-OP HSG SOC LTD: covers 18th Upper Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tridev Anubhav every 1–2 months.

Tridev Anubhav: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK661 – 74947
3 BHK749 – 89135
Shops259 – 4473
1 BHK5272

The builder’s record and reviews

Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects.

Read Google reviews of Tridev Anubhav →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Tridev Anubhav: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Tridev Anubhav

What is the possession date of Tridev Anubhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tridev Anubhav in Mulund West, Mumbai is 31 December 2026 — 36 months later than 30 December 2023, the date given at registration.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Tridev Anubhav?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Tridev Anubhav's builder has filed on MahaRERA, the official one, is 31 December 2026, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Tridev Anubhav extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "RCC slab work of the building is completed in full and finishing internal work is in progress of the project, as is evidenced by the latest Form 1 that is Architect Certificate dated 23rd December-2023 submitted for the period of 30th November-2023. In Light of the same we, M/s. Tridev Realty & Construction Private Limited Developer of the aforesaid project seek extension of one year for due date of completion of the project that is 29-Dec-2024. Self Declaration dated 25.12.2023 for extension of due date for the project “Tridev Anubhav" registered with MahaRERA vide registration Number P518…"; to 31 December 2025, giving the reason "More than 90% Construction work of the said project is completed as evidences by the latest Architect Certificate dated 05-04-2025. Other pending work viz. Tower Parking, C P Fitting work, Wires and Switches is on-going. For Completion of the said pending work and obtaining of OC and other compliances we seek extension of the project completion date up-to 31-12-2025. We have duly complied and updated and corrected the consent table other than existing members with stamp and signature of promoter on each page as annexed herein below. We request you to kindly approve the project completion da…"; to 31 December 2026, giving the reason "More than 95% Construction work of the said project is completed as evidenced by the latest Architect Certificate dated 07-04-2026. Other pending work viz. Tower Parking, Part of C P Fitting work, Wires and Switches is on-going. For Completion of the said pending work and obtaining of OC and other compliances we seek extension of the project completion date up-to 31-12-2026. Consent table in Format B other than existing members with stamp and signature of promoter on each page as annexed herein below. In light of the same we request you to kindly approve the project completion date up-to 31…".

What is the RERA number of Tridev Anubhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tridev Anubhav in Mulund West, Mumbai is P51800011760.

Is Tridev Anubhav registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav is registered as P51800011760 and its status is "Registered and active".

What is the current construction status of Tridev Anubhav? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANUBHAV CO-OP HSG SOC LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Tridev Anubhav have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Tridev Anubhav safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav is registered on MahaRERA as P51800011760, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Tridev Anubhav?

Tridev Anubhav is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Tridev Anubhav are 527 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Tridev Anubhav?

For a flat in Tridev Anubhav (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Tridev Anubhav received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Tridev Anubhav a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav is a redevelopment: 40 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Tridev Anubhav uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tridev Anubhav was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Tridev Anubhav's possession date changes?

The latest dates are on Tridev Anubhav's MahaRERA page (P51800011760). GharKundli's Kundli Watch sends a free WhatsApp update on Tridev Anubhav every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Tridev Anubhav have?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav has one building filed: ANUBHAV CO-OP HSG SOC LTD with 26 floors and 87 units.

What are the flat sizes (carpet area) in Tridev Anubhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Tridev Anubhav: 2 BHK: 661 to 749 sq ft carpet (47 homes); 3 BHK: 749 to 891 sq ft carpet (35 homes); 1 BHK: 527 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Tridev Anubhav have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered and 32 open car parking spaces for Tridev Anubhav.

How big is the land of Tridev Anubhav?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav stands on 1,897 sq m of land (about 0.5 acres), with 4,029 sq m of sanctioned built-up area and 207 sq m of recreational open space.

What is the track record of Tridev Anubhav's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Realty AND Construction (a group of 5 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 10 still being built, 7 past the promised date (typically 22 months late). 32 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Tridev Anubhav?

Google Maps has reviews of Tridev Anubhav written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Tridev Anubhav?

Tridev Anubhav by TRIDEV REALTY AND CONSTRUCTION PVT LTD is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Chembur West, Nahur), Maharashtra, and is registered on MahaRERA as P51800011760, per GharKundli's check of MahaRERA records. Its land is filed as 702-B. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).

How many flats are in Tridev Anubhav, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav has 84 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Tridev Anubhav registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Tridev Anubhav was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Does Tridev Anubhav have any legal issues or court cases?

No court cases are listed for Tridev Anubhav on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Tridev Anubhav?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TRIDEV REALTY AND CONSTRUCTION PVT LTD, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Mulund West (400080)

All 303 projects in Mulund West (400080) →

Other projects by TRIDEV REALTY AND CONSTRUCTION PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.