Hill View CHS LTD
by JIRAJ DEVELOPER LLP · Borivali West, Mumbai 400058Also near Jogeshwari East, Andheri East, Oshiwara District Centre
What’s in the report? →Possession date of Hill View CHS LTD (MahaRERA P51800007100): 31 December 2027, moved from 30 December 2023 (48 months later). It has 79 homes (1 BHK and 2 BHK, 385–629 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007100, and currently active.
Source: MahaRERA website — records for P51800007100, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Hill View CHS LTD?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hill View CHS LTD has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800019319)
Reason the builder gave MahaRERA: “The required further permissions from the Competent Authority of the plan passing authority were delayed.”
31 March 2026
Extended at the builder's request (MahaRERA application EXT51800025974)
Reason the builder gave MahaRERA: “Due to Delay in Permission from the competent authority, extension required”
31 December 2027
Extended at the builder's request (MahaRERA application EA02052620813)
Reason the builder gave MahaRERA:
“Subject: Submission of Technical Reasons for Delay in Completion of the Project - HILLVIEWCHSLTD Maha RERA Reg. No. P51800007100 Respected Sir, We, JIRAJ DEVELOPERLLP, are the promoters of the real estate project known as "HILL VIEWCHSLTD"…” Read the full reason
“Subject: Submission of Technical Reasons for Delay in Completion of the Project - HILLVIEWCHSLTD Maha RERA Reg. No. P51800007100 Respected Sir, We, JIRAJ DEVELOPERLLP, are the promoters of the real estate project known as "HILL VIEWCHSLTD" bearing Maha RERA Registration No.P51800007100. As the project was affected due to covid-19 and further repercussions of the covid-19 and non- availability of materials and migration of labours due to pandemic and some delay from the contractor side which led to disruption in construction work. and alsoas perour plot there is road width policy as per DCR…”
Source: Hill View CHS LTD’s extension records on MahaRERA (P51800007100), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hill View CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007100
- Status
- Registered and active
- Builder
- JIRAJ DEVELOPER LLP
- Location
- Borivali West, Mumbai · 400058
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2027
- Delay so far
- 48 months
- Homes
- 79
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Hill View CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HILL VIEW CHS WING A | 90% | 65% | 45% | 0% |
| HILL VIEW WING B | 90% | 70% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- HILL VIEW CHS WING A: covers PLINTH LEVEL
- HILL VIEW WING B: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hill View CHS LTD every 1–2 months.
Hill View CHS LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 456 – 629 | 60 |
| 1 BHK | 385 – 441 | 19 |
- Buildings: HILL VIEW CHS WING A (15 floors, 51 units) · HILL VIEW WING B (9 floors, 28 units)
- Land: 1,323 sq m (about 0.3 acres) · sanctioned built-up 2,366 sq m
- Land, as filed: 239 242
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Hill View CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hill View CHS LTD: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hill View CHS LTD
What is the possession date of Hill View CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hill View CHS LTD in Borivali West, Mumbai is 31 December 2027 — 48 months later than 30 December 2023, the date given at registration.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Hill View CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hill View CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2027, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hill View CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "The required further permissions from the Competent Authority of the plan passing authority were delayed."; to 31 March 2026, giving the reason "Due to Delay in Permission from the competent authority, extension required"; to 31 December 2027, giving the reason "Subject: Submission of Technical Reasons for Delay in Completion of the Project - HILLVIEWCHSLTD Maha RERA Reg. No. P51800007100 Respected Sir, We, JIRAJ DEVELOPERLLP, are the promoters of the real estate project known as "HILL VIEWCHSLTD" bearing Maha RERA Registration No.P51800007100. As the project was affected due to covid-19 and further repercussions of the covid-19 and non- availability of materials and migration of labours due to pandemic and some delay from the contractor side which led to disruption in construction work. and alsoas perour plot there is road width policy as per DCR…".
What is the RERA number of Hill View CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hill View CHS LTD in Borivali West, Mumbai is P51800007100.
Is Hill View CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD is registered as P51800007100 and its status is "Registered and active".
What is the current construction status of Hill View CHS LTD? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 65% to 70% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Hill View CHS LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hill View CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD is registered on MahaRERA as P51800007100, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hill View CHS LTD?
Hill View CHS LTD is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Hill View CHS LTD are 385 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hill View CHS LTD?
For a flat in Hill View CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Hill View CHS LTD received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Hill View CHS LTD a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD is a redevelopment: 27 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Hill View CHS LTD uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hill View CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hill View CHS LTD's possession date changes?
The latest dates are on Hill View CHS LTD's MahaRERA page (P51800007100). GharKundli's Kundli Watch sends a free WhatsApp update on Hill View CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hill View CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD has 2 buildings filed: HILL VIEW CHS WING A with 15 floors and 51 units; HILL VIEW WING B with 9 floors and 28 units.
What are the flat sizes (carpet area) in Hill View CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Hill View CHS LTD: 2 BHK: 456 to 629 sq ft carpet (60 homes); 1 BHK: 385 to 441 sq ft carpet (19 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Hill View CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD stands on 1,323 sq m of land (about 0.3 acres), with 2,366 sq m of sanctioned built-up area.
What are the reviews of Hill View CHS LTD?
Google Maps has reviews of Hill View CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hill View CHS LTD?
Hill View CHS LTD by JIRAJ DEVELOPER LLP is in Borivali West, Mumbai, pincode 400058 (near Jogeshwari East, Andheri East, Oshiwara District Centre), Maharashtra, and is registered on MahaRERA as P51800007100, per GharKundli's check of MahaRERA records. Its land is filed as 239 242. GharKundli lists all 148 MahaRERA projects in Andheri West (400058).
How many flats are in Hill View CHS LTD, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD has 79 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Hill View CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill View CHS LTD was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Hill View CHS LTD have any legal issues or court cases?
No court cases are listed for Hill View CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Hill View CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JIRAJ DEVELOPER LLP.
Check it yourself on MahaRERA
- How to check the possession date of Hill View CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Andheri West (400058)
- I Space Urban Vista
- Legacy
- Skylark Heights
- Rajhans
- Avyukta Parijat
- Rite Devangi
- Gautam Prabhu
- Borivali Madhumas CHSL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.