by RIGHT CHANNEL CONSTRUCTION PVT LTD · Andheri East, MumbaiAlso near Chakala, Jogeshwari East, Seepz

Possession date of TANDICE69: 31 December 2024, moved from 31 December 2019 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800008220. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about TANDICE69?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TANDICE69 has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800005389)

    Reason the builder gave MahaRERA: “The said is a slum project and there was hindrace and nuisance caused by tenants by not vaccating the land. Later on with instruction from SRA and Police Station the plot was vaccated.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800017556)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.92% allottees for purpose of extension of RERA registration period of the said project.”

Source: TANDICE69’s extension records on MahaRERA (P51800008220), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TANDICE69

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008220
Status
Lapsed (registration period ended)
Builder
RIGHT CHANNEL CONSTRUCTION PVT LTD
Location
Andheri East, Mumbai · 400059
Project type
Others
Registered on
18 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2024
Delay so far
60 months
Homes
38
Sold or booked
84%
Towers
1
Complaints on MahaRERA
6
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of TANDICE69, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing E and Wing F100%100%100%99%

Commencement certificate (CC), as filed on MahaRERA

  • Wing E and Wing F: covers 10 Upper floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TANDICE69 every month.

TANDICE69: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Right Channel Construction (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 26 months); 2 still being built, 2 past the promised date (typically 52 months late); 2 lapsed. 10 complaints on MahaRERA across 2 projects.

Read Google reviews of TANDICE69 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TANDICE69: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TANDICE69

What is the possession date of TANDICE69?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TANDICE69 in Andheri East, Mumbai is 31 December 2024 — 60 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for TANDICE69?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TANDICE69's builder has filed on MahaRERA, the official one, is 31 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TANDICE69 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "The said is a slum project and there was hindrace and nuisance caused by tenants by not vaccating the land. Later on with instruction from SRA and Police Station the plot was vaccated."; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.92% allottees for purpose of extension of RERA registration period of the said project.".

What is the RERA number of TANDICE69?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TANDICE69 in Andheri East, Mumbai is P51800008220.

Is TANDICE69 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69 is registered as P51800008220 and its status is "Lapsed (registration period ended)".

What is the construction status of TANDICE69?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Wing E and Wing F is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does TANDICE69 have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TANDICE69 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69 is registered on MahaRERA as P51800008220, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TANDICE69's possession date changes?

The latest dates are on TANDICE69's MahaRERA page (P51800008220). GharKundli's Kundli Watch sends a free WhatsApp update on TANDICE69 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TANDICE69 have?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69 has one building filed: Wing E and Wing F with 12 floors and 121 units.

How big is the land of TANDICE69?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69 stands on 5,034 sq m of land (about 1.2 acres), with 14,799 sq m of sanctioned built-up area.

What is the track record of TANDICE69's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Right Channel Construction (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 26 months); 2 still being built, 2 past the promised date (typically 52 months late); 2 lapsed. 10 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TANDICE69?

Google Maps has reviews of TANDICE69 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TANDICE69?

TANDICE69 by RIGHT CHANNEL CONSTRUCTION PVT LTD is in Andheri East, Mumbai (pincode 400059), near Chakala, Jogeshwari East, Seepz, Maharashtra, and is registered on MahaRERA as P51800008220, per GharKundli's check of MahaRERA records.

How many homes are in TANDICE69?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69 has 38 homes in 1 tower registered on MahaRERA, and 84% of them are sold or booked.

When was TANDICE69 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TANDICE69 was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TANDICE69?

No court cases are listed for TANDICE69 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of TANDICE69?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RIGHT CHANNEL CONSTRUCTION PVT LTD, which has 5 other projects registered on MahaRERA.

Other projects in Andheri East

All 108 projects in Andheri East (400059) →

Other projects by RIGHT CHANNEL CONSTRUCTION PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.