galaxy royale

by M R REALTORS · Santacruz West, MumbaiAlso near Dahisar East, Borivali West

Possession: galaxy royale is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800010773. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about galaxy royale?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of galaxy royale has moved

  1. 31 December 2017

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800001666)

    Reason the builder gave MahaRERA: “Some approvals pending from govt authorities”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800003925)

    Reason the builder gave MahaRERA:
    “There is a reservation of maternity home in this SRA scheme, which was to be handed over to BMC. The said reservation has been completed and is ready to be handed over. Furthermore, we had requested the BMC to take the possession of the of…” Read the full reason“There is a reservation of maternity home in this SRA scheme, which was to be handed over to BMC. The said reservation has been completed and is ready to be handed over. Furthermore, we had requested the BMC to take the possession of the of the said maternity home and the same is in process of handing over, however it may take some more time.”
  4. 30 October 2020

    Revised completion date on MahaRERA

Source: galaxy royale’s extension records on MahaRERA (P51800010773), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on galaxy royale

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800010773
Status
Completed
Builder
M R REALTORS
Location
Santacruz West, Mumbai · 400068
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2017
Latest completion date
October 2020
Delay so far
34 months
Homes
137
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of galaxy royale, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GALAXY ROYALE100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on galaxy royale every month.

galaxy royale: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

M R Realtors has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 25 months). 3 complaints on MahaRERA across 2 projects.

Read Google reviews of galaxy royale →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

galaxy royale: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about galaxy royale

What is the possession date of galaxy royale?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for galaxy royale in Santacruz West, Mumbai is 30 October 2020 — 34 months later than 31 December 2017, the date given at registration.

Is the builder's possession date different from the MahaRERA date for galaxy royale?

Builders and listing sites often quote an earlier "target" date for handover. The completion date galaxy royale's builder has filed on MahaRERA, the official one, is 30 October 2020, already 34 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of galaxy royale extended?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "Some approvals pending from govt authorities"; to 30 April 2020, giving the reason "There is a reservation of maternity home in this SRA scheme, which was to be handed over to BMC. The said reservation has been completed and is ready to be handed over. Furthermore, we had requested the BMC to take the possession of the of the said maternity home and the same is in process of handing over, however it may take some more time.".

What is the RERA number of galaxy royale?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of galaxy royale in Santacruz West, Mumbai is P51800010773.

Is galaxy royale registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale is registered as P51800010773 and its status is "Completed".

What is the construction status of galaxy royale?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale's status on MahaRERA is "Completed". As filed by the builder, slab work on GALAXY ROYALE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does galaxy royale have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is galaxy royale safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale is registered on MahaRERA as P51800010773, its MahaRERA status is "Completed", its completion date has moved 34 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if galaxy royale's possession date changes?

The latest dates are on galaxy royale's MahaRERA page (P51800010773). GharKundli's Kundli Watch sends a free WhatsApp update on galaxy royale every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does galaxy royale have?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale has one building filed: GALAXY ROYALE with 32 floors.

How big is the land of galaxy royale?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale stands on 5,991 sq m of land (about 1.5 acres), with 8,408 sq m of sanctioned built-up area and 431 sq m of recreational open space.

What is the track record of galaxy royale's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), M R Realtors has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 25 months). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of galaxy royale?

Google Maps has reviews of galaxy royale written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is galaxy royale?

galaxy royale by M R REALTORS is in Santacruz West, Mumbai (pincode 400068), near Dahisar East, Borivali West, Maharashtra, and is registered on MahaRERA as P51800010773, per GharKundli's check of MahaRERA records.

How many homes are in galaxy royale?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale has 137 homes in 1 tower registered on MahaRERA.

When was galaxy royale registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), galaxy royale was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on galaxy royale?

No court cases are listed for galaxy royale on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of galaxy royale?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M R REALTORS.