Vighnahatra Vijaya Heights
by VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED · Borivali West, Mumbai 400092Also near Lower Parel, Babhai NakaRegistered on MahaRERA as “VIJAYA HEIGHTS”
What’s in the report? →Possession date of Vighnahatra Vijaya Heights (MahaRERA P51800007143): 30 April 2031, moved from 28 August 2023 (88 months later). It has 77 homes (3 BHK and 4 BHK, 1085–2133 sq ft carpet), 59% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007143, and currently active. Its completion date has moved from August 2023 to April 2031: 88 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800007143, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vighnahatra Vijaya Heights?
3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vighnahatra Vijaya Heights has moved
28 August 2023
Completion date given when the project was registered
31 December 2030
Extended at the builder's request (MahaRERA application EXT51800017846)
Reason the builder gave MahaRERA:
“The construction activities were halted due to Work Stop Orders issued by the Hon’ble High Court on 13/01/2016 and 07/04/2017, thereby mandating suspension of all construction work pertaining to the said project. We need to construct Mamled…” Read the full reason
“The construction activities were halted due to Work Stop Orders issued by the Hon’ble High Court on 13/01/2016 and 07/04/2017, thereby mandating suspension of all construction work pertaining to the said project. We need to construct Mamledar Office in C Wing of Phase III. Although we applied for the collectors permission in 2010 we received it on 2/08/2022. We were unable to proceed with construction until we received the necessary permissions from the government. The said Work Stop Orders were subsequently revoked by the Hon’ble High Court vide its Orders dated 18/10/2024 and 28/04/2025,…”30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vighnahatra Vijaya Heights’s extension records on MahaRERA (P51800007143), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vighnahatra Vijaya Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007143
- Status
- Registered and active
- Builder
- VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED
- Location
- Borivali West, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- August 2023
- Latest completion date
- April 2031
- Delay so far
- 88 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 77
- Sold or booked
- 59%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Vighnahatra Vijaya Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sale Building | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sale Building: covers 30 floors
Latest CC order on MahaRERA: dated 04/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vighnahatra Vijaya Heights every 1–2 months.
Vighnahatra Vijaya Heights: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,085 – 1,454 | 76 |
| Shops | 583 – 1,117 | 6 |
| Other | 1,722 – 2,380 | 2 |
| 4 BHK | 2,133 | 1 |
- Buildings: Sale Building (30 floors, 85 units)
- Car parking: 176 covered
- Land: 4,278 sq m (about 1.1 acres) · sanctioned built-up 10,600 sq m · recreational space 311 sq m
- Boundaries filed include: CHANDAVARKAR ROAD
- Land, as filed: 472 PT
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vighnahatra Builders AND Projects has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 53 months late). No complaints on MahaRERA.
Read Google reviews of Vighnahatra Vijaya Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vighnahatra Vijaya Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vighnahatra Vijaya Heights
What is the possession date of Vighnahatra Vijaya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vighnahatra Vijaya Heights in Borivali West, Mumbai is 30 April 2031 — 88 months later than 28 August 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 88 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vighnahatra Vijaya Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vighnahatra Vijaya Heights's builder has filed on MahaRERA, the official one, is 30 April 2031, already 88 months later than the 28 August 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vighnahatra Vijaya Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "The construction activities were halted due to Work Stop Orders issued by the Hon’ble High Court on 13/01/2016 and 07/04/2017, thereby mandating suspension of all construction work pertaining to the said project. We need to construct Mamledar Office in C Wing of Phase III. Although we applied for the collectors permission in 2010 we received it on 2/08/2022. We were unable to proceed with construction until we received the necessary permissions from the government. The said Work Stop Orders were subsequently revoked by the Hon’ble High Court vide its Orders dated 18/10/2024 and 28/04/2025,…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vighnahatra Vijaya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vighnahatra Vijaya Heights in Borivali West, Mumbai is P51800007143.
Is Vighnahatra Vijaya Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights is registered as P51800007143 and its status is "Registered and active".
What is the current construction status of Vighnahatra Vijaya Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sale Building is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Vighnahatra Vijaya Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vighnahatra Vijaya Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights is registered on MahaRERA as P51800007143, its completion date has moved 88 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vighnahatra Vijaya Heights?
Vighnahatra Vijaya Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Vighnahatra Vijaya Heights start at 1085 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vighnahatra Vijaya Heights?
For a flat in Vighnahatra Vijaya Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Vighnahatra Vijaya Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vighnahatra Vijaya Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vighnahatra Vijaya Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vighnahatra Vijaya Heights's possession date changes?
The latest dates are on Vighnahatra Vijaya Heights's MahaRERA page (P51800007143). GharKundli's Kundli Watch sends a free WhatsApp update on Vighnahatra Vijaya Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vighnahatra Vijaya Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights has one building filed: Sale Building with 30 floors and 85 units.
What are the flat sizes (carpet area) in Vighnahatra Vijaya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vighnahatra Vijaya Heights: 3 BHK: 1085 to 1454 sq ft carpet (76 homes); 4 BHK: 2133 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Vighnahatra Vijaya Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 176 covered car parking spaces for Vighnahatra Vijaya Heights.
How big is the land of Vighnahatra Vijaya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights stands on 4,278 sq m of land (about 1.1 acres), with 10,600 sq m of sanctioned built-up area and 311 sq m of recreational open space.
What is the track record of Vighnahatra Vijaya Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Builders AND Projects has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 53 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vighnahatra Vijaya Heights?
Google Maps has reviews of Vighnahatra Vijaya Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vighnahatra Vijaya Heights?
Vighnahatra Vijaya Heights by VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED is in Borivali West, Mumbai, pincode 400092 (near Lower Parel, Babhai Naka), Maharashtra, and is registered on MahaRERA as P51800007143, per GharKundli's check of MahaRERA records. Its boundaries filed there include CHANDAVARKAR ROAD. Its land is filed as 472 PT. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).
How many flats are in Vighnahatra Vijaya Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights has 77 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.
When was Vighnahatra Vijaya Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vighnahatra Vijaya Heights was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Vighnahatra Vijaya Heights have any legal issues or court cases?
3 court cases are listed for Vighnahatra Vijaya Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Vighnahatra Vijaya Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vighnahatra Vijaya Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Mumbai Suburban →
Other projects in Borivali West (400092)
- Skylark Heights
- Gaurav Galaxy
- Soni Arcade, Building No 2
- Fortune Avirahi Wing A
- Shraddha Skyline
- Sparkle Umadarshan
- I Space Urban Vista
- Hiranandani Bluecrest
Other projects by VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.