SIDDHARTH NAGAR GULMOHAR CHS LTD
by SHIVAM PARIVAR DEVELOPERS PVT LTD · Goregaon west, MumbaiAlso near Kalanagar, Pahadi goregaon, Goregaon East
Possession date of SIDDHARTH NAGAR GULMOHAR CHS LTD: 30 December 2026, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008681, and currently active. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SIDDHARTH NAGAR GULMOHAR CHS LTD?
How the possession date of SIDDHARTH NAGAR GULMOHAR CHS LTD has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800026074)
Reason the builder gave MahaRERA: “As per attachment”
30 December 2026
Extended at the builder's request (MahaRERA application EA04032620086)
Reason the builder gave MahaRERA:
“The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over spee…” Read the full reason
“The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.Industry Slow Down – As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately…”
Source: SIDDHARTH NAGAR GULMOHAR CHS LTD’s extension records on MahaRERA (P51800008681), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SIDDHARTH NAGAR GULMOHAR CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints and 1 court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008681
- Status
- Registered and active
- Builder
- SHIVAM PARIVAR DEVELOPERS PVT LTD
- Location
- Goregaon west, Mumbai · 400104
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 146
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 1
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of SIDDHARTH NAGAR GULMOHAR CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIDDHARTH NAGAR GULMOHAR CHS LTD | 100% | 94% | 85% | 53% |
Commencement certificate (CC), as filed on MahaRERA
- SIDDHARTH NAGAR GULMOHAR CHS LTD: covers 25 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIDDHARTH NAGAR GULMOHAR CHS LTD every month.
SIDDHARTH NAGAR GULMOHAR CHS LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 504 – 703 | 74 |
| 1 BHK | 342 – 436 | 72 |
| Office Space | 290 – 716 | 5 |
| Shops | 106 – 229 | 4 |
- Buildings: SIDDHARTH NAGAR GULMOHAR CHS LTD (25 floors, 155 units)
- Land: 1,318 sq m (about 0.3 acres) · sanctioned built-up 3,458 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects.
Read Google reviews of SIDDHARTH NAGAR GULMOHAR CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SIDDHARTH NAGAR GULMOHAR CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SIDDHARTH NAGAR GULMOHAR CHS LTD
What is the possession date of SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SIDDHARTH NAGAR GULMOHAR CHS LTD in Goregaon west, Mumbai is 30 December 2026 — 24 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SIDDHARTH NAGAR GULMOHAR CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SIDDHARTH NAGAR GULMOHAR CHS LTD's builder has filed on MahaRERA, the official one, is 30 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SIDDHARTH NAGAR GULMOHAR CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "As per attachment"; to 30 December 2026, giving the reason "The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.Industry Slow Down – As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately…".
What is the RERA number of SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SIDDHARTH NAGAR GULMOHAR CHS LTD in Goregaon west, Mumbai is P51800008681.
Is SIDDHARTH NAGAR GULMOHAR CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD is registered as P51800008681 and its status is "Registered and active".
What is the construction status of SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SIDDHARTH NAGAR GULMOHAR CHS LTD is 94% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does SIDDHARTH NAGAR GULMOHAR CHS LTD have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SIDDHARTH NAGAR GULMOHAR CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD is registered on MahaRERA as P51800008681, its completion date has moved 24 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SIDDHARTH NAGAR GULMOHAR CHS LTD's possession date changes?
The latest dates are on SIDDHARTH NAGAR GULMOHAR CHS LTD's MahaRERA page (P51800008681). GharKundli's Kundli Watch sends a free WhatsApp update on SIDDHARTH NAGAR GULMOHAR CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SIDDHARTH NAGAR GULMOHAR CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD has one building filed: SIDDHARTH NAGAR GULMOHAR CHS LTD with 25 floors and 155 units.
What are the flat sizes (carpet area) in SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SIDDHARTH NAGAR GULMOHAR CHS LTD: 2 BHK: 504 to 703 sq ft carpet (74 homes); 1 BHK: 342 to 436 sq ft carpet (72 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD stands on 1,318 sq m of land (about 0.3 acres), with 3,458 sq m of sanctioned built-up area.
What is the track record of SIDDHARTH NAGAR GULMOHAR CHS LTD's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SIDDHARTH NAGAR GULMOHAR CHS LTD?
Google Maps has reviews of SIDDHARTH NAGAR GULMOHAR CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SIDDHARTH NAGAR GULMOHAR CHS LTD?
SIDDHARTH NAGAR GULMOHAR CHS LTD by SHIVAM PARIVAR DEVELOPERS PVT LTD is in Goregaon west, Mumbai (pincode 400104), near Kalanagar, Pahadi goregaon, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800008681, per GharKundli's check of MahaRERA records.
How many homes are in SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD has 146 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was SIDDHARTH NAGAR GULMOHAR CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHARTH NAGAR GULMOHAR CHS LTD was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SIDDHARTH NAGAR GULMOHAR CHS LTD?
1 court case is listed for SIDDHARTH NAGAR GULMOHAR CHS LTD on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SIDDHARTH NAGAR GULMOHAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVAM PARIVAR DEVELOPERS PVT LTD, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SIDDHARTH NAGAR GULMOHAR CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400104
- EKTA TRIPOLIS PHASE II
- Sunteck Pinnacle 1
- Paras Residency
- DRM Sheetal Landmark
- io Residences by PCPL
- io Tower by PCPL
- Apricus
- Bali Ananda
Other projects by SHIVAM PARIVAR DEVELOPERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.