by Shivam Parivar Developers Pvt Ltd · Motilal Nagar, MumbaiAlso near Goregaon West, Kalanagar, Oshiwara

Possession: Samadhan is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800016620. Status: Completed. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Samadhan?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Samadhan has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009630)

    Reason the builder gave MahaRERA:
    “The under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc. due to the second wave of Covid-19. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of ra…” Read the full reason“The under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc. due to the second wave of Covid-19. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour are still not available for a quick kick-start post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provides minimum assured wages and free essential items at the doorstep respectively, will not let them move out to earn a livelihood. The Government departments and authority…”
  3. 30 December 2022

    Revised completion date on MahaRERA

Source: Samadhan’s extension records on MahaRERA (P51800016620), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Samadhan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800016620
Status
Completed
Builder
Shivam Parivar Developers Pvt Ltd
Location
Motilal Nagar, Mumbai · 400104
Project type
Residential / Group Housing
Registered on
25 May 2018
Completion date at registration
June 2021
Latest completion date
December 2022
Delay so far
18 months
Homes
174
Towers
1
Complaints on MahaRERA
8
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Samadhan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Samadhan100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samadhan every month.

Samadhan: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects.

Read Google reviews of Samadhan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Samadhan: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Samadhan

What is the possession date of Samadhan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Samadhan in Motilal Nagar, Mumbai is 30 December 2022 — 18 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Samadhan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Samadhan's builder has filed on MahaRERA, the official one, is 30 December 2022, already 18 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Samadhan extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan's builder applied to MahaRERA to extend the completion date once: to 30 June 2022, giving the reason "The under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc. due to the second wave of Covid-19. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour are still not available for a quick kick-start post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provides minimum assured wages and free essential items at the doorstep respectively, will not let them move out to earn a livelihood. The Government departments and authority…".

What is the RERA number of Samadhan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Samadhan in Motilal Nagar, Mumbai is P51800016620.

Is Samadhan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan is registered as P51800016620 and its status is "Completed".

What is the construction status of Samadhan?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan's status on MahaRERA is "Completed". As filed by the builder, slab work on Samadhan is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Samadhan have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Samadhan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan is registered on MahaRERA as P51800016620, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Samadhan's possession date changes?

The latest dates are on Samadhan's MahaRERA page (P51800016620). GharKundli's Kundli Watch sends a free WhatsApp update on Samadhan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Samadhan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan has one building filed: Samadhan with 25 floors.

How big is the land of Samadhan?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan stands on 954 sq m of land (about 0.2 acres), with 2,569 sq m of sanctioned built-up area.

What is the track record of Samadhan's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Samadhan?

Google Maps has reviews of Samadhan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Samadhan?

Samadhan by Shivam Parivar Developers Pvt Ltd is in Motilal Nagar, Mumbai (pincode 400104), near Goregaon West, Kalanagar, Oshiwara, Maharashtra, and is registered on MahaRERA as P51800016620, per GharKundli's check of MahaRERA records. Its boundaries filed there include Siddharth Nagar Chawl.

How many homes are in Samadhan?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan has 174 homes in 1 tower registered on MahaRERA.

When was Samadhan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Samadhan was registered on MahaRERA on 25 May 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Samadhan?

No court cases are listed for Samadhan on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Samadhan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shivam Parivar Developers Pvt Ltd, which has 4 other projects registered on MahaRERA.

Other projects in pincode 400104

All 183 projects in Goregaon West (400104) →

Other projects by Shivam Parivar Developers Pvt Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.