PRABHAT
by SHIVAM PARIVAR DEVELOPERS PVT LTD · Ghakopar East, MumbaiAlso near Ghatkopar Kirol, Pant Nagar, Kurla
Possession date of PRABHAT: 30 December 2025, moved from 30 December 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800024145. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about PRABHAT?
How the possession date of PRABHAT has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018989)
Reason the builder gave MahaRERA: “As per attachment”
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800025818)
Reason the builder gave MahaRERA: “As per attachment”
Source: PRABHAT’s extension records on MahaRERA (P51800024145), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PRABHAT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800024145
- Status
- Lapsed (registration period ended)
- Builder
- SHIVAM PARIVAR DEVELOPERS PVT LTD
- Location
- Ghakopar East, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 21 Jan 2020
- Completion date at registration
- December 2023
- Latest completion date
- December 2025
- Delay so far
- 24 months
- Homes
- 101
- Sold or booked
- 68%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of PRABHAT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PRABHAT | 100% | 52% | 16% | 3% |
Commencement certificate (CC), as filed on MahaRERA
- PRABHAT: covers 22 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRABHAT every month.
PRABHAT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 513 – 639 | 82 |
| 1 BHK | 401 | 19 |
- Buildings: PRABHAT (22 floors, 101 units)
- Land: 693 sq m (about 0.2 acres) · sanctioned built-up 4,414 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects.
Read Google reviews of PRABHAT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PRABHAT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PRABHAT
What is the possession date of PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PRABHAT in Ghakopar East, Mumbai is 30 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for PRABHAT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PRABHAT's builder has filed on MahaRERA, the official one, is 30 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PRABHAT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "As per attachment"; to 30 December 2025, giving the reason "As per attachment".
What is the RERA number of PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PRABHAT in Ghakopar East, Mumbai is P51800024145.
Is PRABHAT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT is registered as P51800024145 and its status is "Lapsed (registration period ended)".
What is the construction status of PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PRABHAT is 52% done and internal work 16%. GharKundli's full report compares construction progress with the deadline.
Does PRABHAT have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PRABHAT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT is registered on MahaRERA as P51800024145, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PRABHAT's possession date changes?
The latest dates are on PRABHAT's MahaRERA page (P51800024145). GharKundli's Kundli Watch sends a free WhatsApp update on PRABHAT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PRABHAT have?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT has one building filed: PRABHAT with 22 floors and 101 units.
What are the flat sizes (carpet area) in PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for PRABHAT: 2 BHK: 513 to 639 sq ft carpet (82 homes); 1 BHK: 401 sq ft carpet (19 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT stands on 693 sq m of land (about 0.2 acres), with 4,414 sq m of sanctioned built-up area.
What is the track record of PRABHAT's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PRABHAT?
Google Maps has reviews of PRABHAT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PRABHAT?
PRABHAT by SHIVAM PARIVAR DEVELOPERS PVT LTD is in Ghakopar East, Mumbai (pincode 400075), near Ghatkopar Kirol, Pant Nagar, Kurla, Maharashtra, and is registered on MahaRERA as P51800024145, per GharKundli's check of MahaRERA records.
How many homes are in PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT has 101 homes in 1 tower registered on MahaRERA, and 68% of them are sold or booked.
When was PRABHAT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PRABHAT was registered on MahaRERA on 21 January 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on PRABHAT?
No court cases are listed for PRABHAT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PRABHAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVAM PARIVAR DEVELOPERS PVT LTD, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PRABHAT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla
- Jai Arihant
- Saptashringi
- SUDHANSHU HEIGHTS
- Heritage Lakeside
- Kalyan Kutir Co-operative Housing Society Limited
- Kanakdhara
- Privilon
- Emerald Isle - T16
Other projects by SHIVAM PARIVAR DEVELOPERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.