SAI DARSHAN

by SHAH PATEL & CO · Andheri, MumbaiAlso near Juhu, D. N. Nagar, Vile Parle East

Possession date of SAI DARSHAN: 31 December 2027, moved from 30 December 2021 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800013711, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAI DARSHAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI DARSHAN has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 29 December 2022

    Extended at the builder's request (MahaRERA application EXT51800010967)

    Reason the builder gave MahaRERA:
    “The construction of the project "SAI DARSHAN" got delayed on account of pandemic situation across country due to COVID 19.The construction work on site affected due to non availability of labour. We undertake to complete the project within…” Read the full reason“The construction of the project "SAI DARSHAN" got delayed on account of pandemic situation across country due to COVID 19.The construction work on site affected due to non availability of labour. We undertake to complete the project within applied extension time i.e. 364 days from existing completion date. Hence, we apply for extension of time limit by 364 days and proposed completion date will be 29/12/2022.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800015323)

    Reason the builder gave MahaRERA: “We, hereby apply for extension u/s 7(3) of the registered project beari ng vide no P51800013711”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019093)

    Reason the builder gave MahaRERA:
    “Presently the project in completed in all respect, however we are expecting final Occupancy Certificate within six months’ time. Further we would like reiterate that the construction and development work is completed and the extension is re…” Read the full reason“Presently the project in completed in all respect, however we are expecting final Occupancy Certificate within six months’ time. Further we would like reiterate that the construction and development work is completed and the extension is requested only on account of technical issue of final occupancy certificate. Further we undertake that we will adhere to extension of time limit sought here and complete the formality of completion as per Maha RERA.”
  5. 31 December 2027

    Extended at the builder's request (MahaRERA application EA13062621362)

    Reason the builder gave MahaRERA: “1) Poor booking response from customer. 2) Because of poor response our work was very slow. But now we have completed our 97 % Project”

Source: SAI DARSHAN’s extension records on MahaRERA (P51800013711), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI DARSHAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800013711
Status
Registered and active
Builder
SHAH PATEL & CO
Location
Andheri, Mumbai · 400058
Project type
Residential / Group Housing
Registered on
23 Oct 2017
Completion date at registration
December 2021
Latest completion date
December 2027
Delay so far
72 months
Homes
34
Sold or booked
57%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SAI DARSHAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI DARSAN100%100%100%97%

Commencement certificate (CC), as filed on MahaRERA

  • SAI DARSAN: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI DARSHAN every month.

SAI DARSHAN: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK576 – 66418
1 BHK4238
1 Room Kitchen2798

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI DARSHAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI DARSHAN

What is the possession date of SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI DARSHAN in Andheri, Mumbai is 31 December 2027 — 72 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI DARSHAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI DARSHAN's builder has filed on MahaRERA, the official one, is 31 December 2027, already 72 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI DARSHAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2022, giving the reason "The construction of the project "SAI DARSHAN" got delayed on account of pandemic situation across country due to COVID 19.The construction work on site affected due to non availability of labour. We undertake to complete the project within applied extension time i.e. 364 days from existing completion date. Hence, we apply for extension of time limit by 364 days and proposed completion date will be 29/12/2022."; to 31 December 2023, giving the reason "We, hereby apply for extension u/s 7(3) of the registered project beari ng vide no P51800013711"; to 31 December 2024, giving the reason "Presently the project in completed in all respect, however we are expecting final Occupancy Certificate within six months’ time. Further we would like reiterate that the construction and development work is completed and the extension is requested only on account of technical issue of final occupancy certificate. Further we undertake that we will adhere to extension of time limit sought here and complete the formality of completion as per Maha RERA."; to 31 December 2027, giving the reason "1) Poor booking response from customer. 2) Because of poor response our work was very slow. But now we have completed our 97 % Project".

What is the RERA number of SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI DARSHAN in Andheri, Mumbai is P51800013711.

Is SAI DARSHAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN is registered as P51800013711 and its status is "Registered and active".

What is the construction status of SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI DARSAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI DARSHAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SAI DARSHAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN is registered on MahaRERA as P51800013711, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI DARSHAN's possession date changes?

The latest dates are on SAI DARSHAN's MahaRERA page (P51800013711). GharKundli's Kundli Watch sends a free WhatsApp update on SAI DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI DARSHAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN has one building filed: SAI DARSAN with 11 floors and 34 units.

What are the flat sizes (carpet area) in SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAI DARSHAN: 2 BHK: 576 to 664 sq ft carpet (18 homes); 1 BHK: 423 sq ft carpet (8 homes); 1 Room Kitchen: 279 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN stands on 776 sq m of land (about 0.2 acres), with 823 sq m of sanctioned built-up area.

Where can I read reviews of SAI DARSHAN?

Google Maps has reviews of SAI DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI DARSHAN?

SAI DARSHAN by SHAH PATEL & CO is in Andheri, Mumbai (pincode 400058), near Juhu, D. N. Nagar, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800013711, per GharKundli's check of MahaRERA records. Its boundaries filed there include MATRAPADA ROAD.

How many homes are in SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN has 34 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.

When was SAI DARSHAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DARSHAN was registered on MahaRERA on 23 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI DARSHAN?

No court cases are listed for SAI DARSHAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAI DARSHAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAH PATEL & CO.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400058

All 148 projects in Andheri West (400058) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.